Revision History
Rev. |
Description of Modification |
Date |
1. |
First Issue for Comments |
17/01/2024 |
2. |
Revised According to the Comments |
25/01/2024 |
3 |
Revised According to the Comments |
25/01/2024 |
4 |
Revised based on the reporting issue |
07/02/2024 |
5 |
Revised the Coral Monitoring Information |
22/03/2024 |
6 |
Revised the Coral Monitoring Information |
27/03/2024 |
CONTENTS
8. Summary of Exceedance, Complaints, Notification of Summons and Prosecutions.............. 12
Appendix A Master Programme
Appendix B Overview of Desalination Plant in Tseung Kwan O
Appendix C Summary of Implementation Status of Environmental Mitigation
Appendix D Impact Monitoring Schedule
Appendix E Event/Action Plan
Appendix F Landfill Gas Equipment Calibration Certificate
Appendix G Landfill Gas Monitoring Data
Appendix H Waste Flow Table
Appendix I Ecology (Coral) Survey Report
Appendix J Site Inspection Proforma
Appendix K Complaint Log
Appendix L Exceedance Report
Introduction
A1. The Project, Design, Build and Operate First Stage of Tseung Kwan O Desalination Plant (TKODP), is a Designated Project under the Environmental Impact Assessment Ordinance (Cap. 499) (EIAO) and is currently governed by a Further Environmental Permit (EP No. FEP - 01/503/2015/A) for the construction and operation of the Contract.
A2. In accordance with the Environmental Monitoring and Audit (EM&A) Manual for the Contract, EM&A works for marine water quality, noise, waste management and ecology should be carried out by Environmental Team (ET), Acuity Sustainability Consulting Limited (ASCL), during the construction phase of the Contract.
A3. This is the 46th Monthly EM&A Report, prepared by ASCL, for the Contract summarizing the monitoring results and audit findings of the EM&A programme at and around Tseung Kwan O Area 137 (TKO 137) during the reporting period from 1 December to 31 December 2023.
A4. The EM&A programme for this contract has covered environmental monitoring on construction noise level at selected NSRs and Contractor’s environmental performance auditing in the aspects of construction dust, construction noise, water quality, waste management, Landscape and Visual and Ecology.
Summary of Main Works Undertaken & Key Mitigation Measures Implemented
A5. Key activities carried out in this reporting period for the Contract included the followings:
Administration Building - Carrying out the floor tiles works at G/F - External wall painting works - Construction of block work for pipe duct - Installation of building services, cable laying, electrical switchboard, testing and commissioning |
Chemical building - Installation of leakage collection pit cover - Underground utility construction work - Landscape work at roof - Defect rectification |
Main Electrical & Central Chiller Plant Building - Installation of chillers, building services, electrical switchboard and cable laying - Installation of Roof Tile for Fuel Tank Room |
ActiDAFF - Underground utility construction work - Installation of access opening cover - Construction of staircase no 2 - Installation of mechanical equipment, piping system, installation of building services, electrical switchboards and cable laying, fiber-reinforced plastic cover Installation |
Product Water Storage Tank Building - Installation of Cat Ladders in Water Tank A - Sealing slab opening in water Tank A - Re-construction of Wall PW8 in Water Tank A -
Installation of metal
cladding, building
services, cable laying, mechanical equipment, steel pipe - Underground utility construction |
OSCG Building - Protective Coating for dangerous goods Rooms - Placing Soil Mix at Roof - Installation of Metal Cladding (at East Side) and Roller Shutters and Window - Underground utility construction work - Installation of building services, mechanical equipment and cable laying, testing and commissioning |
Reverse Osmosis Building - Installation of building services, electrical switchboard, cable laying, Installation of mechanical equipment, steel pipe, Glass Reinforced Plastic pipe, raised floor, testing and commissioning - Installation of metal cladding, handrailing, roller shutters, glass canopy and glass house - Underground utility construction work - Construction of Reinforced Concrete External Wall for Male Toilet |
Post Treatment Building - Installation of building services, Installation of mechanical equipment and piping system, Pressure Test - Underground utility construction work - Installation of Cat Ladders in Water Tanks - Installation of Metal Cladding - Placing Soil Mix at Roof |
Inspection corridor - Installation of building services, Lift installation - Construction of roof tiling works and staircases no. 2 - Installation of Movement Joints and glass window |
CO2 Tanks - Installation of pipes and electrical wiring, testing and commissioning Combined Shaft and Pump room - Finishing, Grating; window; louvre installation Other - Watermain works at CLP 132 kV Substation - Staircases construction; Steel Bridge assembly and installation at elevated walkway - Road Construction, Footpath Construction, Landscape Construction, Irrigation System Construction, Water Pressure Test for Fire Services and Plumbing System in Zone A, B, C - Structure Construction, steel fence erection of Wave Deflector Wall at seawall area |
A6. The major environmental impacts brought by the above construction works include:
- Construction dust and noise generation from construction works and excavation works;
- Waste generation from the construction activities
A7. The key environmental mitigation measures implemented for the Contract in this reporting period associated with the above construction works include:
- Dust suppression by regular wetting and water spraying for construction works;
- Reduction of noise from equipment and machinery on-site and regular inspection to machinery and plants/vehicles on-site to ensure proper functioning;
- Deployment of silt curtain at the marine areas; and
- Sorting and storage of general refuse and construction waste;
Summary of exceedance & investigation & follow-up
A8. No noise monitoring was conducted during the reporting period since there are no Contract -related construction activities undertaken within a radius of 300m from the monitoring locations. No exceedance of the action Level was recorded during the reporting period.
A9. The construction phase marine water quality programme was ceased from 1 September 2023 due to the completion of marine-related construction works.
A10. The EM&A works for commissioning phase water quality were conducted during the reporting period in accordance with the EM&A Manual. Thirty-five (35) of the commissioning phase water quality monitoring results of SS obtained had exceeded the Action Level. Twenty-seven (27) of the commissioning phase water quality monitoring results of SS obtained during the reporting period had exceeded the Limit Level. After investigation, all exceedances were concluded unrelated to the Project.
A11. Seven (7) of dechlorinated effluent sample were taken in contact tank/ product water tank on 3 December 2023. No TRC exceedance of action or limit levels was obtained during the discharge of dechlorinated effluent.
A12. Pre-operation phase coral monitoring works was conducted on 28 December 2023. All tagged coral colonies showed good health condition during the December 2023 monitoring survey. There was no increased level of mortality, bleaching and sediment in other tagged coral colonies when compared with the baseline results. There is no AL/LL exceedance during the monitoring period.
A13. In this reporting period, 72 times of landfill gas monitoring were conducted at TKO Area 137 (Ch1+340 - Ch1+600). No action or limit level exceedance was recorded during the reporting period.
A14. Joint site inspections of the construction work by ET and IEC were carried out on 5, 12, 19, 27 December 2023 to audit the mitigation measures implementation status. Reminders were recorded in the site inspection checklists and provided to the contractors together with the appropriate follow-up actions where necessary.
Complaint Handling and
Prosecution
A15. No environmental complaint, notification of summons and prosecution was received in the reporting period.
Reporting Change
A16. There was no change to be reported that may affect the on-going EM&A programme.
Summary of Upcoming
Key Issues and Key Mitigation Measures
A17. Key activities anticipated in the next reporting period for the Contract will include the followings:
Administration Building - Landscaping works on roof of building. - External wall aluminum features installation - Finishing works for doghouse. - Installation of building services, cable laying, electrical switchboard, Pressure Test, electrical switchboard, testing and commissioning |
Chemical building - Landscape work at roof - Construction of hose reel cabinet. - Defect rectification |
Main Electrical & Central Chiller Plant Building - Installation of Roof Tile for Fuel Tank Room - Minor Installation of building services, electrical switchboard, cable laying, pressure test |
ActiDAFF - Underground utility construction work - Installation of access opening covers for filtered water tank - Carrying out finishing works for staircase no. 3 - Minor Installation of mechanical equipment, piping system, building services, electrical switchboards and cable laying, fiber-reinforced plastic cover Installation |
Product Water Storage Tank Building - Water Test in Tank A - Waterproofing work at Roof Slab on Tank A - Tank A water test and defect rectification - Installation of building services, cable laying, Installation of mechanical equipment, steel pipe, Pressure Test |
OSCG Building - Installation of Railing on Brine Maker Tank - Protective Coating for dangerous goods Rooms - Installation of building services, mechanical equipment and cable laying, Lightning Installation, testing and commissioning |
Reverse Osmosis Building - Installation of Handrailings - Installation of Glass House - Installation of building services, electrical switchboard, cable laying, Photovoltaic Panel. Minor Installation of mechanical equipment and raised floor, testing and commissioning - Underground utility construction work |
Post Treatment Building - Installation of Cat Ladders in Water Tanks - Placing Soil Mix at Roof - Curb Construction for Rescue Opening at Water Tanks - Installation of building services, mechanical equipment and piping system, Pressure Test |
Inspection corridor - Construction of roof tiling works - Installation of steel balustrade at roof - Installation of Movement Joints - Installation of glass window - Installation of building services, Lift Installation |
CO2 Tanks - Tank surface cleaning, testing and commissioning Combined Shaft and Pump room - Internal finishing, defect rectification Guard House -
Installation
of Building Services - Workshop construction work Other - Glass Roof and Glass Canopy installation at elevated walkway - Security Fence footing construction work - Manhole 5 Glass Reinforced Plastic Installation work - Underground utility rectification work - Road Construction - Traffic signage work - Footpath Construction - Landscape Construction - Landscape planting work - Irrigation System Construction - Slope work - Shotcreteing; Rock anchor installation, Rock break - Water Pressure Test for Fire Services and Plumbing System - Open Channel and Wave deflector Wall - Traffic signage work |
A18. The major environmental impacts brought by the above construction works will include:
- Construction dust and noise generation from excavation and construction works;
- Waste generation from construction activities
A19. The key environmental mitigation measures for the Contract in the coming reporting period associated with the above construction works will include:
- Reduction of noise from equipment and machinery on-site;
- Dust suppression by regular wetting and water spraying for construction works and at main haul road;
- Sorting and storage of general refuse and construction waste; and
- Deployment of silt curtain at the marine areas.
Background
1.1. The Acciona Agua, S.A. Trading, Jardine Engineering Corporation, Limited and China State Construction Engineering (Hong Kong) Limited as AJC Joint Venture (AJCJV) is contracted to carry out the Design, Build and Operate First Stage of Tseung Kwan O Desalination Plant (DPTKO) under Contract No. 13/WSD/17 (the Contract).
1.2. Acuity Sustainability Consulting Limited (ASCL) is commissioned by AJCJV to undertake the Environmental Team (ET) services as required and/or implied, both explicitly and implicitly, in the Environmental Permit (EP), Environmental Impact Assessment Report (EIA Report) (Register No. AEIAR-192/2015) and Environmental Monitoring and Audit Manual (EM&A Manual) for the Contract; and to carry out the Environmental Monitoring and Audit (EM&A) programme in fulfillment of the EIA Report’s EM&A requirements and Contract No. 13/WSD/17 Specification requirements.
1.3. Pursuant to the Environmental Impact Assessment Ordinance (EIAO), the Director of Environmental Protection granted the Environmental Permit (No. EP-01/503/2015) and Variation of Environmental Permit (No. EP-01/503/2015/A) to Water Supplies Department (WSD); and granted the Further Environmental Permit (No. FEP- 01/503/2015/A) to AJCJV for the Contract.
The Reporting Scope
1.4. This is the 46th Monthly EM&A Report for the Contract which summarizes the key findings of the EM&A programme during the reporting period from 1 December to 31 December 2023.
Contract Organization
1.5. The Contract Organization structure for Construction Phase is presented in Figure 1.1.
Figure 1.1 Contract Organization Chart
1.6. Contact details of the key personnel are presented in Table 1.1 below:
Table 1.1 Contact Details
of Key Personnel
Party |
Position |
Name |
Telephone no. |
Contract Proponent (Water Supplies Department) |
SE/CM2 |
Milton Law |
2634-3573 |
Supervising Officer (Binnies Hong Kong Limited) |
Project Manager |
Christina Ko |
2608-7302 |
Chief Resident Engineer |
Roger Wu |
6343-1002 |
|
The Jardine Engineering Corporation, Limited, China State Construction Engineering (Hong Kong) Limited and Acciona Agua, S.A. Trading |
Project Manager |
Stephen Yeung |
2807-4665 |
Environmental Monitoring Manager |
Brian Kam |
9456-9541 |
|
Environmental Monitoring Manager |
Joy Chan |
6468-1782 |
|
Acuity Sustainability Consulting Limited |
Environmental Team Leader |
Jacky Leung |
2698-6833 |
ANewR Consulting Limited |
Independent Environmental Checker (IEC) |
Mr. CHAN Yi Chun, Alex |
2618-2831 |
Summary of Construction Works
1.7. Details of the major construction activities undertaken in this reporting period are shown below. The master programme is presented in Appendix A.
1.8. Key activities carried out in this reporting period for the Contract included the followings:
Administration Building - Carrying out the floor tiles works at G/F - External wall painting works - Construction of block work for pipe duct - Installation of building services, cable laying, electrical switchboard, testing and commissioning |
Chemical building - Installation of leakage collection pit cover - Underground utility construction work - Landscape work at roof - Defect rectification |
Main Electrical & Central Chiller Plant Building - Installation of chillers, building services, electrical switchboard and cable laying - Installation of Roof Tile for Fuel Tank Room |
ActiDAFF - Underground utility construction work - Installation of access opening cover - Construction of staircase no 2 - Installation of mechanical equipment, piping system, installation of building services, electrical switchboards and cable laying, fiber-reinforced plastic cover Installation |
Product Water Storage Tank Building - Installation of Cat Ladders in Water Tank A - Sealing slab opening in water Tank A - Re-construction of Wall PW8 in Water Tank A -
Installation of metal cladding, building services, cable
laying, mechanical equipment,
steel pipe - Underground utility construction |
OSCG Building - Protective Coating for dangerous goods Rooms - Placing Soil Mix at Roof - Installation of Metal Cladding (at East Side) and Roller Shutters and Window - Underground utility construction work - Installation of building services, mechanical equipment and cable laying, testing and commissioning |
Reverse Osmosis Building - Installation of building services, electrical switchboard, cable laying, Installation of mechanical equipment, steel pipe, Glass Reinforced Plastic pipe, raised floor, testing and commissioning - Installation of metal cladding, handrailing, roller shutters, glass canopy and glass house - Underground utility construction work - Construction of reinforced concrete External Wall for Male Toilet |
Post Treatment Building - Installation of building services, Installation of mechanical equipment and piping system, Pressure Test - Underground utility construction work - Installation of Cat Ladders in Water Tanks - Installation of Metal Cladding - Placing Soil Mix at Roof |
Inspection corridor - Installation of building services, Lift installation - Construction of roof tiling works and staircases no. 2 - Installation of Movement Joints and glass window |
CO2 Tanks - Installation of pipes and electrical wiring, testing and commissioning Combined Shaft and Pump room - Finishing, Grating; window; louvre installation Other - Watermain works at CLP 132 kV Substation - Staircases construction; Steel Bridge assembly and installation at elevated walkway - Road Construction, Footpath Construction, Landscape Construction, Irrigation System Construction, Water Pressure Test for Fire Services and Plumbing System in Zone A, B, C - Structure Construction, steel fence erection of Wave Deflector Wall at seawall area |
1.9. A summary of the valid permits, licences, and/or notifications on environmental protection for this Contract is presented in Table 1.2.
Table 1.2 Summary
of the Status of Valid Environmental Licence, Notification, Permit and
Documentations
Permit/ Licences |
Valid Period |
Status |
Remark |
|
From |
To |
|||
Environmental Permit |
||||
EP-503/2015/A |
Throughout the Contract |
Valid |
- |
|
FEP - 01/503/2015/A |
Throughout the Contract |
Valid |
- |
|
Notification of Construction Works under the Air Pollution Control (Construction
Dust) Regulation (Form NA) |
||||
451539 |
Throughout the Contract |
Valid |
- |
|
Billing Account for Disposal of Construction Waste |
||||
7036276 |
Throughout the Contract |
Valid |
- |
|
Chemical Waste
Producer Registration |
||||
5213-839-A2987-01 |
Throughout the Contract |
Valid |
- |
|
Wastewater Discharge Licence (Land and Marine works) |
||||
WT00035775-2020 |
23/08/2021 |
31/07/2025 |
Valid |
- |
WT00044188-2023 |
16/06/2023 |
30/06/2028 |
Valid |
For Plant T&C and operation |
Permit/ Licences |
Valid Period |
Status |
Remark |
|
From |
To |
|||
Construction Noise
Permit |
||||
GW-RE0640-23 |
22/06/2023 |
21/12/2023 |
Valid |
Expired in the reporting month |
GW-RE1514-23 |
22/12/2023 |
21/06/2024 |
Valid |
- |
1.10. The status for all environmental aspects is presented in Table 1.3.
Table 1.3 Summary
of Status for Key Environmental Aspects under the EM&A Manual
Parameters |
Status |
Water Quality |
|
Baseline Monitoring under EM&A Manual |
The baseline water quality monitoring was conducted between 12 May 2020 to 6 Jun 2020. |
Construction Phase Impact Monitoring |
Ceased from 1 September 2023 |
Commissioning Phase Marine Impact Monitoring |
On-going |
Impact Monitoring of Effluent Discharge from Main Disinfection |
On-going |
Noise |
|
Baseline Monitoring |
The baseline noise monitoring result has been reported in Baseline Monitoring Report and submitted to EPD under EP Condition 3.4 |
Impact Monitoring |
Completed |
Waste Management |
|
Mitigation Measures in Waste Management Plan |
On-going |
Landfill Gas |
|
Regular Monitoring when construction works are within the 250 m Consultation Zone |
On-going |
Ecology (Coral) |
|
Pre-operation phase Regular Coral Monitoring (Monthly) |
On-going |
Parameters |
Status |
Ecology (Landscape) |
|
Pre-operation phase Landscape and Visual Site Inspection |
On-going |
Environmental Audit |
|
Site Inspection covering Measures of Air Quality, Noise Impact, Water Quality, Waste, Ecological Quality, Fisheries, Landscape and Visual |
On-going |
1.11. Other than the EM&A work by ET, environmental briefings, trainings, and regular environmental management meetings were conducted, in order to enhance environmental awareness and closely monitor the environmental performance of the contractors.
1.12. The EM&A programme has been implemented in accordance with the recommendations presented in the approved EIA Report and the EM&A Manual. A summary of implementation status of the environmental mitigation measures for the construction phase of the Contract during the reporting period is provided in Appendix C.
Monitoring Requirements
2.1. To ensure no adverse noise impact, noise monitoring is recommended to be carried out within 300m radius from the nearby noise sensitive receivers (NSRs), during construction phase. The NSRs selected as monitoring station are (i) NSR4 - Creative Secondary School, (ii) NSR24 - PLK Laws Foundation College, and (iii) NSR31 - School of Continuing and Professional Studies - CUHK respectively.
2.2. Construction noise level were measured in terms of the A-weighted equivalent continuous sound pressure level (LAeq). Leq 30min was used as the monitoring parameter for the time period between 0700 and 1900 on normal weekdays. Construction works would follow stipulations of the valid Construction Noise Permits if works had to be conducted during restricted hours or public holidays. Table 2.1 summarizes the monitoring parameters, frequency, and duration of the impact noise monitoring.
Table 2.1 Noise Monitoring Parameters, Time, Frequency
and Duration
Time |
Duration |
Interval |
Parameters |
Daytime: 0700-1900 |
Day time: 0700-1900 (during normal weekdays) |
Continuously in Leq 5min/Leq 30min (average of 6 consecutive Leq 5min) |
Leq 30min L10 30min & L90 30min |
Monitoring Locations
2.3. The monitoring locations were normally made at a point 1m from the exterior of the NSRs building façade and be at a position 1.2m above the ground. A correction of +3dB(A) should be made to the free-field measurements.
2.4. According to the environmental findings detailed in the EIA report and Baseline Monitoring Report, the designated locations for the construction noise monitoring are listed in Table 2.2 below.
Table 2.2 Noise Sensitive
Receivers
NSR ID |
Noise Sensitive Receivers |
Monitoring Location |
Position |
NSR 4 |
Creative Secondary School |
Roof Floor |
1 m from facade |
NSR 24 |
PLK Laws Foundation College |
Pedestrian Road on Ground Floor |
Free-field |
NSR 31 |
School of Continuing and Professional Studies - CUHK |
Roof Floor |
1 m from facade |
2.5. Three noise monitoring locations for impact monitoring at the nearby sensitive receivers are shown in Figure 2.1-2.3.
|
Figure 2.1 NSR4
Creative Secondary School |
|
Figure 2.2 NSR24
PLK Laws Foundation College |
|
Figure 2.3 NSR31 School
of Continuing and Professional Studies - CUHK |
Impact Monitoring Methodology
2.6. Integrated sound level meter will be used for the noise monitoring. The meter will be in compliance with the International Electrotechnical Commission Publications 651: 1979 (Type 1) and 804: 1985 (Type 1) specifications. Immediately prior to and following each noise measurement the accuracy of the sound level meter will be checked using an acoustic calibrator generating a known sound pressure level at a known frequency. Measurements will be accepted as valid only if the calibration levels before and after the noise measurements agree to within 1.0 dB(A).
2.7. Noise measurements were not made in the presence of fog, rain, wind with a steady speed exceeding 5 m/s or wind with gusts exceeding 10 m/s. The wind speed shall be checked with a portable wind speed meter capable of measuring the wind speed in m/s.
Action and Limit Levels
2.8. The Action/Limit Levels are in line with the criteria of Practice Note for Professional Persons (ProPECC PN 2/93) “Noise from Construction Activities - Non-statutory Controls” and Technical Memorandum on Environmental Impact Assessment Process issued by HKSAR Environmental Protection Department [“EPD”] under the Environmental Impact Assessment Ordinance, Cap 499, S.16 are presented in Table 2.3.
Table 2.3 Action and Limit Levels for Noise per EM&A
Manual
Time Period |
Action |
Limit (dB(A)) |
0700-1900 on normal weekdays |
When one documented complaint is received from any one of the noise sensitive receivers |
- 70 dB(A) for school and - 65 dB(A) during examination period |
Note: Limits specified in the GW-TM
and IND-TM for construction and operation noise,
respectively.
2.9. If exceedances were found during noise monitoring, the actions in accordance with the Event and Action Plan shall be carried out according to Appendix E.
Monitoring Results
and Observations
2.10. Referring to EM&A Manual Section 4.1.2, the impact noise monitoring should be carried out when there are Contract-related construction activities undertaken within a radius of 300m from the monitoring stations. No monitoring station was located within a radius of 300m of the Contract site as shown in Figure 2.4, no impact noise monitoring was conducted in the reporting period.
Figure 2.4 Site Layout
Plan with Noise Sensitive Receivers and Desalination Plant
3.1. In accordance with the recommendations of the EIA, water quality monitoring is required during dredging for the submarine pipelines and, during operation phase. The following Section provides details of the water quality monitoring to be undertaken by the Environmental Team (ET) to verify the distance of sediment and brine plume dispersion and to identify whether the potential exists for any indirect impacts to occur to ecological sensitive receivers.
3.2. The water quality monitoring programme was be carried out to allow any deteriorating water quality to be readily detected and timely action taken to rectify the situation.
3.3. Water quality monitoring for the Contract can be divided into the following stages:
- Dredging activities during construction phase;
- Discharge of effluent from main disinfection during construction phase; and
- Operation activities during commissioning phase
Water Quality
Parameters
3.4. The parameters that have been selected for measurement in situ and in the laboratory are those that were either determined in the EIA to be those with the most potential to be affected by the construction works or are a standard check on water quality conditions. Parameters to be measured in the impact monitoring are listed in Table 3.1.
Table 3.1 Parameters measured in the Impact Marine Water Quality Monitoring
Parameters |
Unit |
Abbreviation |
In-situ measurements |
||
Dissolved oxygen |
mg/L |
DO |
Temperature |
oC |
- |
pH |
- |
- |
Turbidity |
NTU |
- |
Salinity |
0/00 |
- |
Total Residual Chlorine NOTE1 |
mg/L |
TRC |
Laboratory measurements |
||
Suspended Solids |
mg/L |
SS |
Iron-Soluble |
mg/L |
Fe |
Anti-scalant as Reactive Phosphorus |
mg/L |
PO4 as P- |
NOTE 1: Monitoring of Total Residual
Chlorine will be conducted
when cleaning and sterilization of the new freshwater main is carried out.
3.5. In addition to the water quality parameters, other relevant data were also being measured and recorded in Water Quality Monitoring Logs, including the location of the sampling stations, water depth, time, weather conditions, sea conditions, tidal stage, current direction and velocity, special phenomena and work activities undertaken around the monitoring and works area that may influence the monitoring results.
Monitoring Equipment
3.6. For water quality monitoring, the following equipment were used:
Dissolved Oxygen and Temperature Measuring Equipment - The instrument was a portable, weatherproof dissolved oxygen measuring instrument complete with cable, sensor, comprehensive operation manuals, and was operable from a DC power source. It was capable of measuring: dissolved oxygen levels in the range of 0 - 20 mg/L and 0 - 200% saturation; and a temperature of 0 - 45 degrees Celsius. It has a membrane electrode with automatic temperature compensation complete with a cable of not less than 35 m in length. Sufficient stocks of spare electrodes and cables were available for replacement where necessary (e.g. YSI model 59 DO meter, YSI 5739 probe, YSI 5795A submersible stirrer with reel and cable or an approved similar instrument).
Turbidity Measurement Equipment - The instrument was a portable, weatherproof turbidity-measuring unit complete with cable, sensor and comprehensive operation manuals. The equipment was operated from a DC power source, it has a photoelectric sensor capable of measuring turbidity between 0 - 1000 NTU and complete with a cable with at least 35 m in length (for example Hach 2100P or an approved similar instrument).
Salinity Measurement Instrument - A portable salinometer capable of measuring salinity in the range of 0 - 40 ppt was provided for measuring salinity of the water at each monitoring location.
Water Depth Gauge - A portable, battery-operated echo sounder (for example Seafarer 700 or a similar approved instrument) was used for the determination of water depth at each designated monitoring station. This unit will preferably be affixed to the bottom of the work boat if the same vessel is to be used throughout the monitoring programme. The echo sounder was suitably calibrated.
Positioning Device - A Global Positioning System (GPS) was used during monitoring to allow accurate recording of the position of the monitoring vessel before taking measurements. The Differential GPS, or equivalent instrument, was suitably calibrated at appropriate checkpoint (e.g. Quarry Bay Survey Nail) to verify that the monitoring station is at the correct position before the water quality monitoring commence.
Water Sampling Equipment - A water sampler, consisting of a PVC or glass cylinder of not less than two litres, which can be effectively sealed with cups at both ends, was used. The water sampler has a positive latching system to keep it open and prevent premature closure until released by a messenger when the sampler is at the selected water depth.
Total Residual Chlorine -Total residual chlorine (TRC) shall be measured in-situ using approved test kit.
Sampling / Testing Protocols
3.7. All in situ monitoring instruments were checked, calibrated, and certified by a laboratory accredited under HOKLAS or any other international accreditation scheme before use, and subsequently re-calibrated at monthly intervals throughout the stages of the water quality monitoring. Responses of sensors and electrodes were checked with certified standard solutions before each use.
3.8. On-site calibration of field equipment was following the “Guide to On-Site Test Methods for the Analysis of Waters”, BS 1427: 2009. Sufficient stocks of spare parts were maintained for replacements when necessary. Backup monitoring equipment was made available so that monitoring can proceed uninterrupted even when equipment is under maintenance, calibration etc.
Laboratory Measurement and Analysis
3.9. Sufficient volume of each water sample was collected for carrying out the laboratory analyses. Using chain of custody forms, collected water samples were transferred to a HOKLAS accredited laboratory (Acumen Laboratory and Testing Limit - HOKLAS 241) for immediate processing. The determination work was start within the next working day after collection of the water samples. Analytical methodology and sample preservation of other parameters were based on the latest edition of Standard Methods for the Examination of Waste and Wastewater published by APHA, AWWA and WPCF and methods by USEPA, or suitable method in accordance with requirements of HOKLAS or another internationally accredited scheme. The QA/QC details were in accordance with the requirements of HOKLAS or another internationally accredited scheme.
3.10. Parameters for laboratory measurements, standard methods and detection limits are presented in Table 3.2.
Table 3.2 Laboratory measurements, standard methods, and corresponding
detection limits of marine water quality monitoring
Parameters |
Standard Methods |
Detection Limit |
Reporting Limit |
Precision |
Dissolved oxygen |
Instrumental, CTD |
0.1 |
- |
+-25% |
Temperature |
Instrumental, CTD |
0.1 |
- |
+-25% |
pH |
Instrumental, CTD |
0.1 |
- |
+-25% |
Turbidity |
Instrumental, CTD |
0.1 |
- |
+-25% |
Salinity |
Instrumental, CTD |
0.1 |
- |
+-25% |
Suspended Solids |
APHA 23rd Ed 2540D |
1.0 |
2.5 |
+-17% |
Iron |
APHA 3111 B |
0.2 |
- |
+-25% |
Total residual chlorine |
HACH DR300 Test- kit |
Lowest limit
= 0.01mg/L; Upper limit
= 8 mg/L |
- |
+-25% |
Lovibond MD200 |
Lowest limit
= 0.01mg/L; Upper limit
= 6 mg/L |
- |
+-25% |
Monitoring Location
Construction Phase
3.11. The Impact water quality monitoring was ceased from 1 September 2023 due to the completion of marine-related construction works.
Commissioning Phase
3.12. The commissioning phase impact water quality monitoring locations are in accordance with the EM&A Manual and detailed in Table 3.3 below. A schedule for water quality monitoring was prepared by the ET and submitted to IEC and EPD prior to the commencement of the monitoring.
Table 3.3 Location
of Impact Water Quality Monitoring Stations
Station |
Easting |
Northing |
Description |
CE |
843550 |
815243 |
Upstream control station at ebb tide |
CF |
846843 |
810193 |
Upstream control station at flood tide |
WSR1 |
846864 |
812014 |
Ecological sensitive receiver at Tung Lung Chau |
WSR2 |
847645 |
812993 |
Fisheries sensitive receiver at Tung Lung Chau |
WSR3 |
848023 |
813262 |
Ecological sensitive receiver at Tung Lung Chau |
WSR4 |
847886 |
814154 |
Ecological sensitive receiver at Tai Miu Wan |
WSR16 |
845039 |
815287 |
Ecological sensitive receiver at Fat Tong Chau |
WSR33 |
847159 |
814488 |
Ecological sensitive receiver at Tai Miu Wan |
WSR36 |
846878 |
814081 |
Ecological sensitive receiver at Kwun Tsai |
WSR37 |
846655 |
813810 |
Ecological sensitive receiver at Tit Cham Chau |
NF1 |
846542 |
813614 |
Edge of Mixing zone, ~ 200m west of outfall diffuser |
NF2 |
846942 |
813614 |
Edge of Mixing zone, ~ 200m east of outfall diffuser |
NF3 |
846742 |
813414 |
Edge of Mixing zone, ~ 200m south of outfall diffuser |
3.13. WSR1 to WSR37 were identified in accordance with Annex 14 of the EIAO-TM as well as Clause 3.4.4.2 of the Environmental Impact Assessment Study Brief for Desalination Plant at Tseung Kwan O (No. ESB-266/2013). WSR1 to WSR3 are sited near the Tung Lung Chau Fish Culture Zone; WSR16 and WSR36 are sited near the coral assemblages along the coastlines of Fat Tong Chau and Kwun Tsai respectively; WSR 4 and WSR33 are sited near the Coastal Protection Area and coral assemblages in waters of Tai Miu Wan; WSR37 is sited near the fisheries resource including spawning and nursery grounds at the coastal water of Tit Cham Chau. NF1 to NF3 are the Edge of mixing zone.
Figure 3.1 Impact water quality monitoring locations under EM&A
Manual Disinfection
3.14. Effluent of disinfection from desalination plant shall be collected at a suitable location after all treatment process before discharge. The sampling location should be agreed with WSD and EPD, and should fulfil the following requirements:
- Effluent collected at the sampling location is representative to the effluent discharged at the outfall diffuser.
- Sampling works at the sampling location would not interfere with the desalination plant operation.
- Sampling works at the sampling location would not induce safety hazard (e.g. staff sampling effluent drops into the culvert)
3.15. According to the approved Flushing and Disinfection Procedure and Supplementary of the Disinfection Procedure for Desalination Plant at Tseung Kwan O, the sampling point of the dechlorinated effluent was located at Contact tank/Product Water Tank (PWT) and T1GKC01AA502/manhole 18. The approved sampling location was shown in Table 3.4, Figure 3.2 and Figure 3.3 below.
Table 3.4 Sampling location of dechlorinated effluent
System/Loop |
Discharge location |
Sampling Location |
Contact tank/ Product Water Tank (PWT) |
Culvert |
Contact tank/PWT |
Connection to dist. network |
Manhole 18 in connection point |
Sampling point T1GKC01AA502/manhole 18 |
Figure 3.2 Impact water quality
monitoring point for dechlorinated effluent (Contact
tank/PWT)
Figure 3.3 Impact water quality
monitoring point for dechlorinated effluent (Sampling
point T1GKC01AA502/manhole 18)
Sampling Frequency
Commissioning Phase
3.16. Impact water quality monitoring were carried out three days per week during the commissioning phase. Monitoring at each station was undertaken once per day. The interval between two sets of monitoring was not less than 36 hours. The monitoring frequency would be increased in the case of exceedances of Action/Limit Levels if considered necessary by ET. Monitoring frequency would be maintained as far as practicable.
Disinfection
3.17. For the discharge of dechlorinated effluent used after main sterilization, in-situ testing of total residual chlorine should be conducted every 1 hour (not less than) at the discharge point(s) when dechlorinated effluent is being discharged.
Sampling Depths & Replication
3.18. During impact water quality monitoring, each station was sampled, and measurements/ water samples were taken at three depths, 1 m below the sea surface, mid-depth, and 1 m above the seabed. For in situ measurements, duplicate readings were made at each water depth at each station. Duplicate water samples were collected at each water depth at each station.
Action and Limit Levels
Commissioning Phase
3.19. The Action and Limit Levels have been set based on the derivation criteria specified in the EM&A Manual. The Action/Limit Levels have been derived and are presented in Table 3.6.
Disinfection
3.20. The Action and Limit Levels have been set in accordance with the approved EM&A Manual and presented in Table 3.5. For the TRC, the discharge should be suspended if the TRC level of the dechlorinated effluent exceeds the 0.1 mg/L. Chlorinated water should be fully neutralized before discharge. Discharge of the water will be done once it is ensured that the chlorine has been neutralized and it is below the discharge limit.
Table 3.5 Derived Action and Limit Levels for Water Quality
Parameters |
Action |
Limit |
Commissioning Phase
Impact Monitoring |
||
DO in
mg/L |
Surface and
Middle 7.30 mg L-1 Bottom 7.31 mg L-1 Tung Lung Chau Fish
Culture Zone 5.1 mgL-1 or level at control station (Whichever the lower) |
Surface and Middle 4 mg L-1 Bottom 2 mg L-1 Tung Lung Chau Fish
Culture Zone 5.0 mgL-1 or level at control station (Whichever the lower) |
SS in mg/L (Depth-
averaged) |
5.00 mg L-1 or 20% exceedance of value at any impact station
compared with corresponding data from control station |
6.00 mg L-1 or 30% exceedance of value at any
impact station compared with corresponding data from control station |
Turbidity in NTU (Depth- averaged) |
2.41 NTU or 20% exceedance of
value at any impact station compared with corresponding data from control station |
2.84 NTU or 30% exceedance of
value at any impact station compared with corresponding data from control station |
Salinity in PSU (Depth- averaged) |
34.25 PSU or 9% exceedance of
value at any impact station compared with corresponding data from control station |
34.56 PSU or 10% exceedance of value at any impact station compared
with corresponding data from control station |
Iron in mg/L (Depth-
averaged) |
0.3 mg/L |
0.3 mg/L |
Total residual chlorine in mg/L |
0.01 mg/L |
0.01 mg/L |
Total residual chlorine in mg/L (Disinfection) |
0.1 mg/L |
0.1 mg/L |
Notes:
i. "Depth-averaged" is calculated by taking the arithmetic means
of reading of all three
depths.
ii. For DO, non-compliance of the water
quality limits occurs
when monitoring result is lower than the limits.
iii. For Turbidity, SS,
iron and Salinity, non-compliance of the water quality limits occurs when
monitoring result is higher than the
limits.
iv. Monitoring of Total Residual
Chlorine (Disinfection) will be conducted when cleaning and sterilization of the new freshwater
main is carried out.
Monitoring Results and Observations
Construction Phase
3.21. Referring to EM&A Manual, the general water quality monitoring should be carried out when there are marine-related construction activities undertaken. General water quality monitoring at the ten monitoring stations (CE, CF, WSR1, WSR2, WSR3, WSR4, WSR16, WSR33, WSR36 and WSR37) was ceased from 1 September 2023 due to the completion of marine-related construction works.
Commissioning Phase
3.22. Considering the first testing and commissioning(T&C) phase of Tseung Kwan O Desalination Plant was started in the reporting period, additional marine water quality monitoring was conducted at the thirteen monitoring stations (CE, CF, WSR1, WSR2, WSR3, WSR4, WSR16, WSR33, WSR36, WSR37, NF1, NF2 and NF3) from 12 December
2023. The Action and Limit Level would be referred to the approved EM&A Manual Table
5.4 First-year Operation Phase Marine Water Monitoring
3.23. Thirty-five (35) of the commissioning phase water quality monitoring results of SS obtained had exceeded the Action Level. Twenty-seven (27) of the commissioning phase water quality monitoring results of SS obtained during the reporting period had exceeded the Limit Level.
3.24. Investigation on the reason of exceedance has been carried out, where the exceedances of SS on 12, 14, 16, 19, 21, 23, 26 and 28 December 2023 were concluded to be unrelated to the Contract as detailed in the Incident Reports on Action Level or Limit Level Non- compliance along with supporting materials in Appendix L.
3.25. Monitoring results of 8 key parameters: Salinity, DO, turbidity, SS, pH, temperature, Total Residual Chlorine and Iron in this reporting, are summarized in Table 3.6, and detailed results are presented in Appendix G.
Table 3.6 Summary of Impact Water Quality Monitoring Results
Locations |
Parameters |
|||||||||
Salinity
(ppt) |
Dissolved Oxygen (mg/L) |
pH |
Turbidity
(NTU) |
Suspended Solids (mg/L) |
Temp. (oC) |
TRC (mg/L) |
Iron (mg/L) |
|||
Surface & Middle |
Bottom |
|||||||||
CE |
Avg. |
33.1 |
9.1 |
9.0 |
7.2 |
3.0 |
3.9 |
21.8 |
<0.01 |
<0.1 |
Min. |
32.1 |
7.4 |
7.4 |
6.6 |
2.2 |
3.0 |
21.0 |
<0.01 |
<0.1 |
|
Max. |
34.5 |
10.1 |
10.1 |
7.6 |
3.8 |
6.0 |
22.4 |
<0.01 |
<0.1 |
|
CF |
Avg. |
33.0 |
9.2 |
9.2 |
7.1 |
3.2 |
3.8 |
21.9 |
<0.01 |
<0.1 |
Min. |
32.3 |
7.9 |
7.8 |
6.6 |
2.5 |
2.5 |
20.9 |
<0.01 |
<0.1 |
|
Max. |
34.2 |
10.0 |
10.1 |
7.4 |
4.0 |
7.0 |
22.6 |
<0.01 |
<0.1 |
|
WSR1 |
Avg. |
33.2 |
9.0 |
9.1 |
7.2 |
2.2 |
4.0 |
21.9 |
<0.01 |
<0.1 |
Min. |
32.3 |
7.8 |
7.9 |
6.6 |
1.7 |
2.5 |
21.2 |
<0.01 |
<0.1 |
|
Max. |
34.4 |
10.3 |
10.3 |
7.4 |
2.5 |
6.0 |
22.8 |
<0.01 |
<0.1 |
|
WSR2 |
Avg. |
33.0 |
9.0 |
8.9 |
7.5 |
2.2 |
3.8 |
23.7 |
<0.01 |
<0.1 |
Min. |
32.1 |
7.7 |
7.6 |
6.7 |
1.4 |
2.5 |
21.1 |
<0.01 |
<0.1 |
|
Max. |
33.7 |
9.9 |
9.9 |
8.4 |
2.6 |
8.0 |
28.0 |
<0.01 |
<0.1 |
|
WSR3 |
Avg. |
33.1 |
9.2 |
9.3 |
7.2 |
2.1 |
4.1 |
21.9 |
<0.01 |
<0.1 |
Min. |
32.5 |
7.8 |
7.9 |
6.7 |
1.2 |
2.5 |
21.1 |
<0.01 |
<0.1 |
|
Max. |
33.5 |
10.1 |
10.1 |
7.4 |
2.6 |
7.0 |
22.6 |
<0.01 |
<0.1 |
|
WSR4 |
Avg. |
33.1 |
9.1 |
9.0 |
7.1 |
2.0 |
4.0 |
22.0 |
<0.01 |
<0.1 |
Min. |
32.4 |
7.3 |
7.3 |
6.6 |
1.2 |
2.5 |
21.2 |
<0.01 |
<0.1 |
|
Max. |
34.2 |
10.5 |
10.4 |
7.5 |
2.5 |
7.0 |
22.8 |
<0.01 |
<0.1 |
|
WSR16 |
Avg. |
33.1 |
9.1 |
9.2 |
7.1 |
2.1 |
4.3 |
22.0 |
<0.01 |
<0.1 |
Min. |
32.3 |
8.4 |
8.4 |
6.6 |
1.1 |
2.5 |
21.1 |
<0.01 |
<0.1 |
|
Max. |
34.2 |
10.4 |
10.4 |
7.4 |
2.8 |
10.0 |
22.7 |
<0.01 |
<0.1 |
Locations |
Parameters |
|||||||||
Salinity
(ppt) |
Dissolved Oxygen (mg/L) |
pH |
Turbidity
(NTU) |
Suspended Solids (mg/L) |
Temp. (oC) |
TRC (mg/L) |
Iron (mg/L) |
|||
Surface & Middle |
Bottom |
|||||||||
WSR33 |
Avg. |
33.1 |
9.0 |
8.9 |
7.2 |
2.2 |
3.9 |
22.0 |
<0.01 |
<0.1 |
Min. |
32.3 |
8.2 |
8.2 |
6.8 |
1.9 |
2.5 |
21.2 |
<0.01 |
<0.1 |
|
Max. |
33.7 |
10.1 |
10.1 |
7.4 |
2.8 |
7.0 |
22.7 |
<0.01 |
<0.1 |
|
WSR36 |
Avg. |
33.5 |
9.2 |
9.2 |
7.2 |
2.4 |
4.1 |
21.9 |
<0.01 |
<0.1 |
Min. |
32.7 |
8.2 |
8.2 |
6.7 |
2.1 |
2.5 |
21.1 |
<0.01 |
<0.1 |
|
Max. |
34.6 |
10.3 |
10.5 |
7.5 |
2.6 |
8.0 |
22.6 |
<0.01 |
<0.1 |
|
WSR37 |
Avg. |
33.0 |
9.0 |
9.0 |
7.5 |
2.2 |
4.1 |
23.7 |
<0.01 |
<0.1 |
Min. |
31.8 |
7.5 |
7.5 |
6.7 |
1.8 |
2.5 |
21.1 |
<0.01 |
<0.1 |
|
Max. |
33.8 |
10.3 |
10.2 |
8.4 |
2.5 |
9.0 |
28.0 |
<0.01 |
<0.1 |
|
NF1 |
Avg. |
33.1 |
9.0 |
9.0 |
7.2 |
2.2 |
4.1 |
21.9 |
<0.01 |
<0.1 |
Min. |
32.5 |
8.2 |
8.2 |
6.7 |
1.6 |
2.5 |
20.9 |
<0.01 |
<0.1 |
|
Max. |
33.6 |
9.8 |
10.1 |
7.4 |
2.5 |
8.0 |
22.8 |
<0.01 |
<0.1 |
|
NF2 |
Avg. |
32.9 |
9.0 |
9.0 |
7.1 |
2.0 |
4.0 |
21.8 |
<0.01 |
<0.1 |
Min. |
32.3 |
7.4 |
7.4 |
6.5 |
1.3 |
2.5 |
20.9 |
<0.01 |
<0.1 |
|
Max. |
33.5 |
10.1 |
10.1 |
7.4 |
2.6 |
7.0 |
22.6 |
<0.01 |
<0.1 |
|
NF3 |
Avg. |
33.0 |
9.0 |
8.8 |
7.2 |
2.1 |
4.1 |
21.9 |
<0.01 |
<0.1 |
Min. |
32.3 |
7.6 |
7.6 |
6.6 |
1.3 |
2.5 |
20.9 |
<0.01 |
<0.1 |
|
Max. |
34.0 |
10.1 |
10.0 |
7.5 |
2.6 |
8.0 |
22.8 |
<0.01 |
<0.1 |
Notes:
i.
"Avg", “Min” and “Max” is the average,
minimum and maximum
respectively of the data from measurements conducted under mid-flood and mid-ebb tides at three
water depths, except that of
DO where the data for “Surface
& Middle” and “Bottom” are calculated separately.
ii.
Measurement data of Suspending Solids
would be rounding
to 2.5mg/L if the value was less than 2.5mg/L
to facilitate data analysing.
Disinfection
3.26. Dechlorinated effluent monitoring at two sampling locations (Contact Tank / Product Water Tank) was carried out by AJCJV on 24 November 2023. The disinfection for the Connection to distribution network was carried out on 2 & 3 December 2023.
3.27. Seven (7) of dechlorinated effluent sample were taken in contact tank/ product water tank.
3.28. No TRC exceedance of action or limit levels was obtained during the discharge of dechlorinated effluent.
3.29. Monitoring results of TRC in this reporting month summarized in Table 3.7.
Table 3.7 Summary of dechlorinated effluent
Monitoring Results
Location |
Contact Tank
/ Product Water
Tank flushing after
neutralization |
||||||
Date |
02 Dec 2023 |
03 Dec 2023 |
03 Dec 2023 |
03 Dec 2023 |
03 Dec 2023 |
03 Dec 2023 |
03 Dec 2023 |
Time |
23:59 |
01:00 |
02:00 |
03:00 |
04:00 |
05:00 |
06:00 |
TRC (mg/L) |
0.04 |
0.04 |
0.03 |
0.02 |
0.01 |
0.00 |
0.01 |
4.1. The waste generated from this Contract includes inert construction and demolition (C&D) materials, and non-inert C&D materials. Non-inert C&D materials are made up of general refuse, vegetative wastes and recyclable wastes such as plastics and paper/cardboard packaging waste. Steel materials generated from the Contract are also grouped into non-inert C&D materials as the materials were not disposed of with other inert C&D materials. With reference to relevant handling records and trip tickets of this Contract, the quantities of different types of waste generated in the reporting month are summarized in Table 4.1. Details of cumulative waste management data are presented as a waste flow table in Appendix H.
Table 4.1 Quantities of Waste Generated from the Contract
during the reporting period
Reporting
Month |
Actual Quantities of Inert C&D Materials Generated Monthly |
Actual Quantities of C&D Wastes
Generated Monthly |
|||||||||
Total Quantity Generated |
Hard Rock and Large Broken Concrete |
Reused in the Contract |
Reused in other
Projects |
Disposed
as Public Fill |
Imported Fill |
Metals |
Paper / cardboard packaging |
Plastics (1) |
Chemical Waste |
Others, e.g., general
refuse |
|
(in ’000kg) |
(in ’000kg) |
(in ’000kg) |
(in ’000kg) |
(in ’000kg) |
(in ’000kg) |
(in ’000kg) |
(in ’000kg) |
(in ’000kg) |
(in ’000kg) |
(in ’000kg) |
|
Dec 2023 |
215.229 |
0.000 |
0.000 |
0.000 |
215.220 |
0.000 |
0.000 |
0.000 |
0.000 |
0.000 |
79.680 |
Notes: (1) Plastics
refer to plastic
bottles / containers, plastic sheets / foam from packaging material
Monitoring Requirement
5.1. In accordance with Section 11 of the EM&A Manual, monitoring of landfill gas is required for construction works within the 250m Consultation Zone. Part of the desalination plant and the indicative area of natural slope mitigation works fall within the SENT Landfill Extension Consultation Zone; and part of the 1,200 mm diameter fresh water mains along Wan Po Road falls within the SENT Landfill and SENT Landfill Extension Consultation Zones, TKO Stage II/III Restored Landfill and TKO Stage I Restored Landfill Consultation Zones.
Monitoring Programme
5.2. Since part of the desalination plant (Wan Po Road and MIC compound/Basketball Court) and the indicative area of natural slope mitigation works fall within the SENT Landfill Extension Consultation Zone in this contract (Figure 5.1), landfill gas monitoring would be required for Wan Po Road and MIC compound/Basketball Court (Figure 5.2) if excavations were conducted at more than 300mm deep. Although SENT Landfill Extension has commenced operation since November 2021, no excavation works were conducted at MIC compound/Basketball Court. Hence no landfill gas monitoring would be scheduled for MIC compound/Basketball Court at the current stage.
Monitoring Location
5.3. Monitoring of oxygen, methane, carbon dioxide and barometric pressure would be performed for excavations at 1m depth or more within the consultation Zone.
5.4. During construction of works within the consultation zones, excavations of 1m depth or more was monitored:
- At the ground surface before excavation commences;
- Immediately before any worker enters the excavation;
- At the beginning of each working day for the entire period the excavation remains open; and
- Periodically through the working day whilst workers are in the excavation.
5.5. For excavations between 300mm and 1m deep, measurements were carried out:
- Directly after the excavation has been completed; and
- Periodically whilst the excavation remains open.
5.6. The area required to be monitored for landfill gas in the reporting period is shown in Figure 5.1.
Figure 5.1 Overview of the SENT Extension Consultation Zone and the Contract Site Area
MONITORING PARAMETERS
5.7. The landfill gas monitoring parameters and the action and limit level are summarized in Table 5.1.
Table 5.1 Action and Limit Level
for Landfill Gas Monitoring Equipment
Parameters |
Action Level |
Limit Level |
Oxygen (O2) |
<19% O2 |
<19% O2 |
Methane (CH4) |
>10% LEL |
>20% LEL |
Carbon Dioxide (CO2) |
>0.5% CO2 |
>1.5% CO2 |
MONITORING EQUIPMENT
5.8. Landfill Gas monitoring was carried out using intrinsically-safe, portable multi-gas monitoring instruments. The gas monitoring equipment is:
- Complying with the Landfill Gas Hazard Assessment Guidance Note as intrinsically safe;
- Capable of continuous barometric pressure and gas pressure measurements;
- Normally operated in diffusion mode unless required for spot sampling, when it should be capable of operating by means of an aspirator or pump;
- Having low battery, fault and over range indication incorporated;
- Capable of storing monitoring data, and shall be capable of being downloaded directly;
- Measure in the following ranges:
methane |
0-100% Lower Explosion Limit (LEL) and 0-100% v/v; |
oxygen |
0-25% V/V; |
carbon dioxide |
0-5% v/v; and |
barometric pressure |
mBar (absolute) |
- alarm (both audibly and visually) in the event that the concentrations of the following are exceeded:
methane |
>10% LEL; |
oxygen |
<19% |
carbon dioxide |
>0.5% by volume |
barometric pressure |
mBar (absolute) |
5.9. Monitoring equipment used in the reporting period are summarized in Table 5.2. The Landfill Gas monitoring equipment calibration certificate is presented in Appendix F.
Table 5.2 Landfill Gas Monitoring Equipment
Equipment |
Brand and Model |
Calibration Expiry
Date |
Portable Gas Detector |
GMI PS500 - 25492809/21 |
21 August 2024 |
Figure 5.2 Location Map for Landfill
Gas Monitoring at TKO Area 137 (-0+440
- -0+760)
Figure 5.3 Location Map for Landfill
Gas Monitoring at TKO Area 137 (-0+740
- -1+060)
MONITORING
RESULTS AND OBSERVATIONS
5.10. In this reporting period, 72 times of landfill gas monitoring were conducted during excavations at 1m depth or more within the consultation zone and whenever workers entered the excavation on the day at TKO Area 137 (Ch1+340 - Ch1+600). No exceedance of action or limit levels for methane, oxygen and carbon dioxide was recorded. Detail of landfill gas monitoring results are presented in Appendix G.
Monitoring Requirements
6.1. In accordance with Section 8.1 of the EM&A Manual, weekly site audit shall be carried out by the ET include checking whether good site practices are being properly implemented by the Contractor and the extent of the works area within the Clear Water Bay Country Park should be checked by the ET during the weekly site audit.
Site Inspection
6.2. Weekly site audit was carried out by the ET in the reporting month, no trespass by the Contractor outside the works area of the Project and Clear Water Bay Country Park, and no damage to the vegetation and rocky shore outside the Project area was observed in the reporting month. Retained trees was properly protected during the construction works, no unacceptable construction works was observed.
6.3. If non-compliance were found during the construction works, the actions in accordance with the Event and Action Plan will be carried out according to Appendix E.
7.1. Under the approval conditions of the EIA Report for the Project, an EM&A programme on coral for the pre-operation phase of the Project is recommended. Pursuant to these EIA approval conditions and Condition 3.1 of the EP and FEP, details of the regular coral monitoring programme have been proposed based on the baseline coral monitoring results in the Report on Pre-Operation Baseline Coral Monitoring and Regular Coral Monitoring Methodology.
Monitoring Location
7.2. In accordance with Appendix B Section 5.1 of the approved supplementary EM&A Manual, two indirect impact sites (C2 and C3) and one control site (C8) as shown in Figure 7.1 should be monitored during the pre-operation Phase. Pre- operation coral survey should be conducted at the indirect impact and control sites. Ten selected hard coral colonies with similar species should be tagged at each of the control and indirect impact sites before commencement of the operation phase. Tagged hard coral colonies should be monitored in open waters during the pre- operation phase and operation phase.
Action
and Limit Levels
7.3. The Action and Limit Levels have been set based on the derivation criteria specified in the EM&A Manual. The Action/Limit Levels have been derived and are presented in Table 7.1.
Table 7.1 Action and Limit Level for Coral
Monitoring Equipment
Parameter |
Action Level Definition |
Limit Level Definition |
Mortality |
If during Impact Monitoring a 15% increase in the percentage of partial mortality on the corals occurs at more than
20% of the tagged indirect impact site coral colonies that is not
recorded on the
tagged corals at the control site, then the Action Level is exceeded |
If during Impact Monitoring a 25% increase in the percentage of partial mortality on the corals occurs at more
than 20% of the tagged indirect impact
site coral colonies that
is not recorded on the tagged corals at the
control site,
then the Limit Level is exceeded |
Note: If the defined
Action Level or Limit Level for coral monitoring is exceeded, the actions as set out in Table E3 will be implemented.
7.4. If non-compliance were found during the monitoring, the actions in accordance with the Event and Action Plan will be carried out according to Appendix E.
Monitoring Frequency
7.5. Pre-operation phase coral monitoring shall be monitored once per month as the requirement of the first year of operational phase.
Monitoring Result and
Observation
7.6. Pre-operation phase coral monitoring works was conducted on 28 December 2023. All tagged coral colonies showed good health condition during the December 2023 monitoring survey. There was no increased level of mortality, bleaching and sediment in other tagged coral colonies when compared with the baseline results. There is no AL/LL exceedance during the monitoring period.
7.7. The details of the monitoring carried out on 28 December 2023 are presented in Appendix I.
8.
Summary of Exceedance, Complaints, Notification of Summons
and Prosecutions
8.1. The Environmental Complaint Handling Procedure is shown in below Figure 8.1:
Figure 8.1 Environmental Complaint
Handling Procedures
8.2. No noise monitoring was conducted during the reporting period since there are no Contract-related construction activities undertaken within a radius of 300m from the monitoring locations. No action Level exceedance for construction noise monitoring was recorded in the reporting month.
8.3. General water quality monitoring at the ten monitoring stations (CE, CF, WSR1, WSR2, WSR3, WSR4, WSR16, WSR33, WSR36 and WSR37) are ceased from 1 September 2023 due to the completion of marine-related construction works.
8.4. The EM&A works for commissioning phase water quality were conducted during the reporting period in accordance with the EM&A Manual
8.5. Thirty-five (35) of the commissioning phase water quality monitoring results of SS obtained had exceeded the Action Level. Twenty-seven (27) of the commissioning phase water quality monitoring results of SS obtained during the reporting period had exceeded the Limit Level. After investigation, all exceedances were concluded unrelated to the Project.
8.6. Seven (7) of dechlorinated effluent sample were taken in contact tank/ product water tank on 3 December 2023.
8.7. No TRC exceedance of action or limit levels was obtained during the discharge of dechlorinated effluent.
8.8. Pre-operation phase coral monitoring works was conducted on 28 December 2023. All tagged coral colonies showed good health condition during the December 2023 monitoring survey. There was no increased level of mortality, bleaching and sediment in other tagged coral colonies when compared with the baseline results. There is no AL/LL exceedance during the monitoring period.
8.9. In this reporting period, 72 times of landfill gas monitoring were conducted at TKO Area 137 (Ch1+340 - Ch1+600). No action or limit level exceedance was recorded during the reporting period.
8.10. No environmental complaint, notification of summons and prosecution was received in the reporting month. Statistics on complaint and notification of summons and prosecution are summarized in Appendix K.
9.1. Site inspections were carried out on a weekly basis to monitor the implementation of proper environmental pollution control and mitigation measures under the Contract. In the reporting period, site inspections were carried out on 5, 12, 19 and 27 December 2023 at the site portions listed in Table 9.1 below.
Table 9.1 Summaries of Site Inspection Record
Date |
Inspected Site
Portion |
Time |
5 December 2023 |
TKO Area 137 |
14:30 - 15:30 |
12 December 2023 |
TKO Area 137 |
14:30 - 15:30 |
19 December 2023 |
TKO Area 137 |
14:30 - 15:30 |
27 December 2023 |
TKO Area 137 |
09:15 - 10:45 |
9.2. Joint site inspections with IEC were carried out on 12 and 27 December 2023.
9.3. Environmental deficiencies were observed during weekly site inspection. Key observations during the site inspections and during the reporting period are summarized in Table 9.2.
Table 9.2 Site Observations
Date |
Environmental Observations |
Follow-up Status |
5 Dec 2023 |
No major environmental deficiency was observed. |
N/A |
12 Dec 2023 |
No major environmental deficiency was observed. |
N/A |
19 Dec 2023 |
No major environmental deficiency was observed. |
N/A |
27 Dec 2023 |
No major environmental deficiency was observed. |
N/A |
9.4. According to the EIA Study Report, Environmental Permit, contract documents and EM&A Manual, the mitigation measures detailed in the documents should be implemented as much as practical during the reporting period. An updated Implementation Status of Environmental Mitigation Measures (EMIS) is provided in Appendix C. Site inspection proforma of the reporting period is provided in Appendix J.
10.1. Works to be undertaken in the next reporting month are:
Administration Building - Landscaping works on roof of building. - External wall aluminum features installation - Finishing works for dog house. - Installation of building services, cable laying, electrical switchboard, Pressure Test, electrical switchboard, testing and commissioning |
Chemical building - Landscape work at roof - Construction of hose reel cabinet. - Defect rectification |
Main Electrical & Central Chiller Plant Building - Installation of Roof Tile for Fuel Tank Room - Minor Installation of building services, electrical switchboard, cable laying, Pressure Test |
ActiDAFF - Underground utility construction work - Installation of access opening covers for filtered water tank - Carrying out finishing works for staircase no. 3 - Minor Installation of mechanical equipment, piping system, building services, electrical switchboards and cable laying, fiber-reinforced plastic cover Installation |
Product Water Storage Tank Building - Water Test in Tank A - Waterproofing work at Roof Slab on Tank A - Tank A water test and defect rectification - Installation of building services, cable laying, Installation of mechanical equipment, steel pipe, Pressure Test |
OSCG Building - Installation of Railing on Brine Maker Tank - Protective Coating for dangerous goods Rooms - Installation of building services, mechanical equipment and cable laying, Lightning Installation, testing and commissioning |
Reverse Osmosis Building - Installation of Handrailings - Installation of Glass House |
- Installation of building services, electrical switchboard, cable laying, Photovoltaic Panel. Minor Installation of mechanical equipment and raised floor, testing and commissioning - Underground utility construction work |
Post Treatment Building - Installation of Cat Ladders in Water Tanks - Placing Soil Mix at Roof - Curb Construction for Rescue Opening at Water Tanks - Installation of building services, mechanical equipment and piping system, Pressure Test |
Inspection corridor - Construction of roof tiling works - Installation of steel balustrade at roof - Installation of Movement Joints - Installation of glass window - Installation of building services, Lift Installation |
CO2 Tanks - Tank surface cleaning, testing and commissioning Combined Shaft and Pump room - Internal finishing, defect rectification Guard House -
Installation
of Building Services - Workshop construction work Other - Glass Roof and Glass Canopy installation at elevated walkway - Security Fence footing construction work - Manhole 5 Glass Reinforced Plastic Installation work - Underground utility rectification work - Road Construction - Traffic signage work - Footpath Construction - Landscape Construction - Landscape planting work - Irrigation System Construction - Slope work - Shotcreteing; Rock anchor installation, Rock break - Water Pressure Test for Fire Services and Plumbing System - Open Channel and Wave deflector Wall - Traffic signage work |
10.2. The major environmental impacts brought by the above construction works will include:
- Construction dust and noise generation from excavation and construction works;
- Waste generation from construction activities
10.3. The key environmental mitigation measures for the Project in the coming reporting period associated with the above construction works will include:
- Dust suppression by regular wetting and water spraying for construction works;
- Reduction of noise from equipment and machinery on-site by regular checking of on-site plant/vehicle to ensure proper functioning;
- Sorting and storage of general refuse and construction waste; and
- Deployment of silt curtain at the marine areas.
11. Conclusions and Recommendations
11.1. This is the 46th Monthly EM&A Report for the Project which summarizes the key findings of the EM&A programme during the reporting period from 1 December to 31 December 2023, in accordance with the EM&A Manual and the requirement under FEP- 01/503/2015/A.
11.2. No noise monitoring was conducted in the reporting period due to the over distant monitoring station from the works location, in which construction activities were not undertaken within a radius of 300m from the monitoring locations.
11.3. The marine water quality programme was ceased from 1 September 2023 due to the completion of marine-related construction works.
11.4. The EM&A works for commissioning phase water quality were conducted during the reporting period in accordance with the EM&A Manual
11.5. Thirty-five (35) of the commissioning phase water quality monitoring results of SS obtained had exceeded the Action Level. Twenty-seven (27) of the commissioning phase water quality monitoring results of SS obtained during the reporting period had exceeded the Limit Level. After investigation, all exceedances were concluded unrelated to the Project.
11.6. Seven (7) of dechlorinated effluent sample were taken in contact tank/ product water tank on 3 December 2023.
11.7. No TRC exceedance of action or limit levels was obtained during the discharge of dechlorinated effluent.
11.8. Pre-operation phase coral monitoring works was conducted on 28 December 2023. All tagged coral colonies showed good health condition during the February 2024 Monitoring survey. There was no increased level of mortality, bleaching and sediment in other tagged coral colonies when compared with the baseline results. There is no AL/LL exceedance during the monitoring period.
11.9. In this reporting period, 72 times of landfill gas monitoring were conducted at TKO Area 137 (Ch2+340 -Ch1+600). No action or limit level exceedance was recorded in the reporting period.
11.10. Weekly environmental site
inspections were conducted during the reporting period. Observations and
reminders were reported during the site inspections. All items are rectified within
the reporting period. The environmental performance of the project
was therefore considered satisfactory.
11.11. According to the environmental
site inspections performed in the reporting month, the Contractor is reminded
to pay attention on chemical storage, site hygiene and dust suppression
mitigation measures.
11.12. No environmental complaint,
notification of summons and prosecution was received in the reporting period.
11.13. The ET will keep track on the construction works to confirm
compliance of environmental requirements and the proper
implementation of all necessary mitigation measures.
Appendix A
Master Programme
Appendix B
Overview of Desalination Plant in Tseung Kwan O
Appendix
C
Summary of Implementation Status of Environmental Mitigation
EIA Reference |
Recommended Environmental Protection Measures/ Mitigation Measures |
Objectives of the recommended measures & main concerns to address |
Implementation Agent |
Implementation Stage |
Implementation status |
Relevant Legislation & Guidelines |
||
D |
C |
O |
||||||
Air Quality |
|
|||||||
S4.8.1 |
Impervious dust screen or sheeting will be provided to enclose scaffolding from the ground floor level of building for construction of superstructure of the new buildings. |
Land site/ During Construction |
Contractor(s) |
|
ü |
|
Implemented |
Air Pollution Control (Construction Dust) |
S4.8.1 |
Impervious sheet will be provided for skip hoist for material transport. |
Land site/ During Construction, particularly dry season |
Contractor(s) |
|
ü |
|
NA |
- |
S4.8.1 |
The area where dusty work takes place should be sprayed with water or a dust suppression chemical immediately prior to, during and immediately after dusty activities as far as practicable. |
Land site/ During Construction |
Contractor(s) |
|
ü |
|
Implemented |
- |
S4.8.1 |
All dusty materials should be sprayed with water or a dust suppression chemical immediately prior to any loading, unloading or transfer operation. |
Land site/ During Construction |
Contractor(s) |
|
ü |
|
Implemented |
- |
S4.8.1 |
Dropping heights for excavated materials should be controlled to a practical height to minimize the fugitive dust arising from unloading. |
Land site/ During Construction |
Contractor(s) |
|
ü |
|
Implemented |
- |
S4.8.1 |
During transportation by truck, materials should not be loaded to a level higher than the side and tail boards and should be dampened or covered before transport. |
Land site/ During Construction |
Contractor(s) |
|
ü |
|
Implemented |
- |
S4.8.1 |
Wheel washing device should be provided at the exits of the work sites. Immediately before leaving a construction site, every vehicle shall be washed to remove any dusty material from its body and wheels as far as practicable. |
Land site/ During Construction |
Contractor(s) |
|
ü |
|
Implemented |
- |
S4.8.1 |
Road sections between vehicle-wash areas and vehicular entrance will be paved. |
Land site/ During Construction |
Contractor(s) |
|
ü |
|
Implemented |
- |
S4.8.1 |
Hoarding of not less than 2.4m high from ground level will be provided along the length of the Project Site boundary. |
Land site/ During construction |
Contractor(s) |
ü |
ü |
|
N/A |
- |
S4.8.1 |
Haul roads will be kept clear of dusty materials and will be sprayed with water so as to maintain the entire road surface wet at all times. |
Land site/ During construction |
Contractor(s) |
|
ü |
|
Implemented after reminder |
- |
EIA Reference |
Recommended Environmental Protection Measures/ Mitigation Measures |
Objectives of the recommended measures & main concerns to address |
Implementation Agent |
Implementation Stage |
Implementation status |
Relevant Legislation & Guidelines |
||
D |
C |
O |
||||||
S4.8.1 |
Temporary stockpiles of dusty materials will be either covered entirely by impervious sheets or sprayed with water to maintain the entire surface wet all the time. |
Land site/ During construction |
Contractor(s) |
|
ü |
|
Implemented after reminder |
- |
S4.8.1 |
Stockpiles of more than 20 bags of cement, dry pulverised fuel ash and dusty construction materials will be covered entirely by impervious sheeting sheltered on top and 3-sides. |
Land site/ During construction |
Contractor(s) |
|
ü |
|
Implemented |
- |
S4.8.1 |
All exposed areas will be kept wet always to minimise dust emission. |
Land site/ During construction |
Contractor(s) |
|
ü |
|
Implemented |
- |
S4.8.1 |
Ultra-low-sulphur diesel (ULSD) will be used for all construction plant on-site, as defined as diesel fuel containing not more than 0.005% sulphur by weight) as stipulated in Environment, Transport and Works Bureau Technical Circular (ETWB-TC(W)) No 19/2005 on Environmental Management on Construction Sites. |
Land site/ During construction/ During Operation |
Contractor(s) |
|
ü |
ü |
Implemented |
Environment, Transport and Works Bureau Technical Circular (ETWB- TC(W)) No 19/2005 on Environmental Management on Construction Sites |
S4.8.1 |
The engine of the construction equipment during idling will be switched off. |
Land site/ During construction |
Contractor(s) |
|
ü |
|
Implemented |
- |
S4.8.1 |
Concrete batching plant will be required on site. control measures recommended in the Guidance Note on a Best Practicable Means for Cement Works (Concrete Batching Plant) (BPM 3/2 (93)) will be implemented. The control measures recommended in the Guidance Note on a Best Practicable Means for Cement Works (Concrete Batching Plant) (BPM 3/2 (93)) will be implemented. |
Land site/ During construction |
Contractor(s) |
|
ü |
|
N/A |
- |
S4.8.1 |
Regular maintenance of construction equipment deployed on-site will be conducted to prevent black smoke emission. |
Land site/ During construction |
Contractor(s) |
|
ü |
|
Implemented after observation |
- |
S4.10 |
To ensure proper implementation of the recommended dust mitigation measures and good construction site practices during the construction phase, environmental site audits on weekly basis is recommended throughout the construction period. |
Land site/ During construction |
Contractor(s)/ Environmental Team (ET) & Independent Environmental Checker (IEC) |
|
ü |
|
Implemented |
- |
Note: D - Design stage C - Construction O - Operation
EIA Reference |
Recommended Environmental Protection Measures/ Mitigation Measures |
Objectives of the recommended measures & main concerns to address |
Implementation Agent |
Implementation Stage |
Implementation status |
Relevant Legislation & Guidelines |
||
D |
C |
O |
||||||
Noise |
||||||||
S5.7 |
Only well-maintained plant will be operated on-site and plant will be serviced regularly during the construction phase. |
All area/ During construction |
Contractor(s) |
|
ü |
|
Implemented |
A Practical Guide for the Reduction of Noise from Construction Works |
S5.7 |
Silencers or mufflers on construction equipment will be utilised and will be properly maintained during the construction phase. |
Noise control/ During construction |
Contractor(s) |
|
ü |
|
N/A |
A Practical Guide for the Reduction of Noise from Construction Works |
S5.7 |
Mobile plant, if any, will be sited as far away from NSRs as possible. |
Noise control/ During construction |
Contractor(s) |
|
ü |
|
N/A |
A Practical Guide for the Reduction of Noise from Construction Works |
S5.7 |
Machines and plant (such as trucks) that may be in intermittent use will be shut down between work periods or will be throttled down to a minimum. |
Noise control/ During construction |
Contractor(s) |
|
ü |
|
Implemented |
A Practical Guide for the Reduction of Noise from Construction Works |
S5.7 |
Plants known to emit noise strongly in one direction will, wherever possible, be orientated so that the noise is directed away from the nearby NSRs. |
Noise control/ During construction |
Contractor(s) |
|
ü |
|
N/A |
A Practical Guide for the Reduction of Noise from Construction Works |
S5.7 |
Material stockpiles and other structures will be effectively utilised, wherever practicable, in screening noise from on-site construction activities. |
Noise control/ During construction |
Contractor(s) |
|
ü |
|
N/A |
A Practical Guide for the Reduction of Noise from Construction Works |
S5.7 |
Use of Quite Powered Mechanical Equipment (QPME). |
Noise control/ During construction |
Contractor(s) |
|
ü |
|
Implemented |
A Practical Guide for the Reduction of Noise from Construction Works |
S5.7 |
Movable noise barriers of 3m in height with skid footing should be used and located within a few metres of stationary plant and mobile plant such that the line of sight to the NSR is blocked by the barriers. The length of the barrier should be at least five times greater than its height. The noise barrier material should have a superficial surface density of at least 7 kg m-2 and have no o or gappeningss. |
Noise control/ During construction |
Contractor(s) |
|
ü |
|
N/A |
A Practical Guide for the Reduction of Noise from Construction Works |
S5.7 |
The noise insulating sheet should be deployed such that there would be no opening or gaps on the joints. |
Noise control/ During construction |
Contractor(s) |
|
ü |
|
N/A |
A Practical Guide for the Reduction of Noise from Construction Works |
S5.7 |
Construction activities (e.g. excavation/shoring, reinstatement (asphalt), and pipe jacking) will be planned and carried out in sequence, such that items of PME proposed for these activities will not be operated simultaneously. |
Noise control/ During construction |
Contractor(s) |
ü |
ü |
|
Implemented |
A Practical Guide for the Reduction of Noise from Construction Works |
S5.7 |
PMEs will not be used at the works areas near educational institutions with residual impact (ie the “influence
area” within a |
Noise control / During construction |
Contractor(s) |
|
ü |
|
N/A |
A Practical Guide for the Reduction of Noise from |
EIA Reference |
Recommended Environmental Protection Measures/ Mitigation Measures |
Objectives of the recommended measures & main concerns to address |
Implementation Agent |
Implementation Stage |
Implementation status |
Relevant Legislation & Guidelines |
||
D |
C |
O |
||||||
|
radius of 40m) during school hours in order to reduce impact to the educational institutions. |
|
|
|
|
|
|
Construction Works |
S5.7 |
Noise enclosures or acoustic sheds would be used to cover stationary PME such as generators. Portable/Movable noise enclosure made of material with superficial surface density of at least 7 kg m-2 may be used for screening the noise from operation of the saw/groover, concrete. |
Noise control/ Pre- construction/ During construction |
Contractor(s) |
ü |
ü |
|
N/A |
- |
S5.9 |
Sawcutting pavement, breaking up of pavement, excavation /shoring, pipe laying, backfilling, reinstatement (concrete) and pipe jacking shall be scheduled outside the examination period. |
Noise control/ Pre- construction/ During construction |
Contractor(s) |
ü |
ü |
|
N/A |
- |
S5.9 |
In view the duration of noise exceedance at Creative Secondary School, PLK Laws Foundation College, TKO Kei Tak Primary School and School of Continuing and Professional Studies-CUHK is limited to 8 weeks, the construction work in the influence areas near the four schools shall be scheduled during long school holidays (eg summer holiday, Easter holiday or Christmas holiday, etc) as far as practicable. Scheduling the construction work for the four schools. |
Noise control/ Pre- construction/ During construction |
Contractor(s) |
ü |
ü |
|
N/A |
- |
S5.10 |
A noise monitoring programme shall be implemented for the construction phase. |
Designated monitoring stations as defined in EM&A Manual/During construction phase |
Environmental Team |
|
ü |
|
N/A |
- |
S5.10 |
The effectiveness of on-site control measures could also be evaluated through the regular site audits. |
All facilities/ During construction |
Contractor(s)/ ET & Independent Environmental Checker (IEC) |
|
ü |
|
Implemented |
- |
Note: D - Design stage C - Construction O - Operation
EIA Reference |
Recommended Environmental Protection Measures/ Mitigation Measures |
Objectives of the recommended measures & main concerns to address |
Implementation Agent |
Implementation Stage |
Implementation status |
Relevant Legislation & Guidelines |
||
D |
C |
O |
||||||
Water Quality |
||||||||
S6.9 |
Dredged marine sediment will be disposed of in a gazetted marine disposal area in accordance with marine dumping permit conditions of the Dumping at Sea Ordinance (DASO). |
Marine Dredging/ During construction |
Contractor(s) |
|
ü |
|
Implemented |
Dumping at Sea Ordinance (DASO) |
S6.9 |
Disposal vessels will be fitted with tight bottom seals in order to prevent leakage of material during transport. |
Marine Dredging/ During construction |
Contractor(s) |
|
ü |
|
Implemented |
- |
S6.9 |
Barges will be filled to a level, which ensures that material does not spill over during transport to the disposal site and that adequate freeboard is maintained to ensure that the decks are not washed by wave action. |
Marine Dredging/ During construction |
Contractor(s) |
|
ü |
|
Implemented |
- |
S6.9 |
After dredging, any excess materials will be cleaned from decks and exposed fittings before the vessel is moved from the dredging area. |
Marine Dredging/ During construction |
Contractor(s) |
|
ü |
|
Implemented |
- |
S6.9 |
All vessels should be well maintained and inspected before use to limit any potential discharges to the marine environment. |
Marine Dredging/ During construction |
Contractor(s) |
|
ü |
|
Implemented |
- |
S6.9 |
All vessels must have a clean ballast system. |
Marine Dredging/ During construction |
Contractor(s) |
|
ü |
|
Implemented |
- |
S6.9 |
No discharge of sewage/grey wastewater should be allowed. Wastewater from potentially contaminated area on working vessels should be minimized and collected. These kinds of wastewater should be brought back to port and discharged at appropriate collection and treatment system. |
Marine Dredging/ During construction |
Contractor(s) |
|
ü |
|
Implemented |
- |
S6.9 |
No soil waste is allowed to be disposed overboard. |
Marine Dredging/ During construction |
Contractor(s) |
|
ü |
|
N/A |
- |
S6.9 |
Silt removal facilities such as silt traps or sedimentation facilities will be provided to remove silt particles from runoff to meet the requirements of the TM standard under the WPCO. The design of silt removal facilities will be based on the guidelines provided in ProPECC PN 1/94. All drainage facilities and erosion and sediment control structures will be inspected on a regular basis and maintained to confirm proper and efficient operation at all times and particularly during rainstorms. Deposited silt and grit will be removed regularly. |
Land site & drainage/ During construction |
Contractor(s) |
|
ü |
|
Implemented |
ProPECC PN 1/94 TM Standard under the WPCO |
S6.9 |
Earthworks to form the final surfaces will be followed up with surface protection and drainage works to prevent erosion caused by rainstorms. |
Land site & drainage/ During construction |
Contractor(s) |
|
ü |
|
Implemented |
- |
EIA Reference |
Recommended Environmental Protection Measures/ Mitigation Measures |
Objectives of the recommended measures & main concerns to address |
Implementation Agent |
Implementation Stage |
Implementation status |
Relevant Legislation & Guidelines |
||
D |
C |
O |
||||||
S6.9 |
Appropriate surface drainage will be designed and provided where necessary. |
Land site & drainage/ During construction |
Contractor(s) |
|
ü |
|
Implemented |
- |
S6.9 |
The precautions to be taken at any time of year when rainstorms are likely together with the actions to be taken when a rainstorm is imminent or forecasted and actions to be taken during or after rainstorms are summarized in Appendix A2 of ProPECC PN 1/94. |
Land site & drainage/ During construction |
Contractor(s) |
ü |
ü |
|
Implemented |
ProPECC PN 1/94 |
S6.9 |
Oil interceptors will be provided in the drainage system where necessary and regularly emptied to prevent the release of oil and grease into the storm water drainage system after accidental spillages. |
Land site & drainage/ During construction |
Contractor(s) |
|
ü |
|
N/A |
- |
S6.9 |
Temporary and permanent drainage pipes and culverts provided to facilitate runoff discharge, if any, will be adequately designed for the controlled release of storm flows. |
Land site & drainage/ During construction |
Contractor(s) |
|
ü |
|
Implemented |
- |
S6.9 |
The temporary diverted drainage, if any, will be reinstated to the original condition when the construction work has finished or when the temporary diversion is no longer required. |
Land site & drainage/ During construction |
Contractor(s) |
|
ü |
|
N/A |
- |
S6.9 |
Appropriate numbers of portable toilets shall be provided by a licensed contractor to serve the construction workers over the construction site to prevent direct disposal of sewage into the water environment. |
Land site & drainage/ During construction |
Contractor(s) |
|
ü |
|
Implemented |
- |
S6.9 and S6.12 |
The sterilization water should be dechlorinated with total residual chlorine (TRC) level below 1 mg/L before discharge to public sewer. In situ testing of TRC should also be conducted for the discharge of chlorinated water for pipeline disinfection to ensure sufficient dechlorination before discharge to public sewer. |
Sterilization of water mains prior to commissioning |
Contractor(s) |
|
ü |
ü |
N/A |
Technical Memorandum for Effluents Discharged into Drainage and Sewerage Systems Inland and Coastal Waters |
S6.9 |
The cleaning and flushing water should also be treated and desilted to the relevant discharge requirement stipulated in TM-DSS before discharging. |
Sterilization of water mains prior to commissioning |
Contractor(s) |
|
ü |
ü |
Implemented |
|
S6.9 |
Site drainage should be well maintained, and good construction practices should be observed to ensure that oil, fuels, solvents, and other chemicals are managed, stored and handled properly and do not enter the nearby water streams. |
Land site & drainage/ During construction/ During operation |
Contractor(s) |
|
ü |
ü |
Implemented |
- |
S6.12 |
Regular site inspections will be carried out in order to confirm that regulatory requirements are being met and that contractors are implementing the standard site practice and mitigation measures as proposed to reduce potential impacts to water quality. |
During construction |
Contractor(s)/ ET & IEC |
|
ü |
|
Implemented |
- |
Note: D - Design stage C - Construction O - Operation
EIA Reference |
Recommended Environmental Protection Measures/ Mitigation Measures |
Objectives of the recommended measures & main concerns to address |
Implementation Agent |
Implementation Stage |
Implementation Status |
Relevant Legislation & Guidelines |
||
D |
C |
O |
||||||
Waste Management |
||||||||
S8.5 |
Nomination of approved personnel to be responsible for standard site practices, arrangements for collection and effective disposal to an appropriate facility of all wastes generated at the site. |
Contract mobilization/ During construction |
Contractor(s) |
|
ü |
|
Implemented |
- |
S8.5 |
Training of site personnel in proper waste management and chemical handling procedures. Training will be provided to workers on the concepts of site cleanliness and appropriate waste management procedures, including waste reduction, reuse, and recycling at the beginning of the construction works. |
Contract mobilization/ During construction |
Contractor(s) |
|
ü |
|
Implemented |
- |
S8.5 |
Provision of sufficient waste disposal points and regular collection for disposal. |
All area/ During construction/ During operation |
Contractor(s) |
|
ü |
ü |
Implemented |
DEVB TC(W) No. 8/2010, Enhanced Specification for Site Cleanliness and Tidiness. |
S8.5 |
Appropriate measures to reduce windblown litter and dust transportation of waste by either covering trucks or by transporting wastes in enclosed containers. |
All area/ During construction |
Contractor(s) |
|
ü |
|
Implemented |
DEVB TC(W) No. 8/2010, Enhanced Specification for Site Cleanliness and Tidiness. |
S8.5 |
A waste management plan
(WMP) as stated in the “ETWB TC(W) No. 19/2005, Environmental Management on Construction Sites” for the amount of waste generated, recycled and disposed of (including the disposal sites) will be established and implemented during the construction phase as part of the Environmental Management Plan (EMP). The Contractor will be required to prepare the EMP and submits it to the Architect/ Engineer under the Contract for approval prior to implementation. |
All area/ During construction |
Contractor(s) |
|
ü |
|
Implemented |
ETWB TC(W) No. 19/2005, Environmental Management on Construction Sites |
S8.5 |
Separation of chemical wastes for special handling and appropriate treatment at the Chemical Waste Treatment Centre at Tsing Yi. |
All area/ During construction |
Contractor(s) |
|
ü |
|
Implemented |
Chapters 2 & 3 Code of Practice on the Packaging, Labelling & Storage of Chemical Wastes published under the Waste Disposal Ordinance (Cap 354), Section 35 |
S8.5 |
Regular cleaning and maintenance programme for drainage systems, sumps and oil interceptors. |
Land site/ During construction |
Contractor(s) |
|
ü |
|
Implemented |
Waste Disposal Ordinance (Cap 354) |
EIA Reference |
Recommended Environmental Protection Measures/ Mitigation Measures |
Objectives of the recommended measures & main concerns to address |
Implementation Agent |
Implementation Stage |
Implementation Status |
Relevant Legislation & Guidelines |
||
D |
C |
O |
||||||
S8.5 |
A recording system for the amount of wastes generated/ recycled and disposal sites. The trip- ticket system will be included as one of the contractual requirements and implemented by the contractor(s). |
Land site/ During construction |
Contractor(s) |
|
ü |
|
Implemented |
DEVB TC(W) No. 6/2010, Trip Ticket System for Disposal of Construction & Demolition Materials |
S8.5 |
Segregation and storage of different types of waste in different containers, skips or stockpiles to enhance reuse or recycling of material and their proper disposal. |
Land site/ During construction/ During operation |
Contractor(s) |
|
ü |
|
Implemented |
WBTC 32/92, The Use of Tropical Hard Wood on Construction Site |
S8.5 |
Encourage collection of aluminium cans and wastepaper by individual collectors during construction with separate labelled bins provided to segregate these wastes from other general refuse by the workforce. |
Land site/ During construction |
Contractor(s) |
|
ü |
|
Implemented |
ETWB TCW No. 33/2002, Management of Construction and Demolition Material Including Rock |
S8.5 |
Any unused chemicals and those with remaining functional capacity will be recycled as far as possible. |
Land site/ During construction |
Contractor(s) |
|
ü |
|
N/A |
- |
S8.5 |
Use of reusable non-timber formwork to reduce the amount of C&D materials. |
All areas/ During construction |
Contractor(s) |
|
ü |
|
Implemented |
WBTC 32/92, The Use of Tropical Hard Wood on Construction Site |
S8.5 |
Prior to disposal of construction waste, wood, steel, and other metals will be separated to the extent practical, for re-use and/or recycling to reduce the quantity of waste to be disposed of to landfill. |
All areas/ During construction |
Contractor(s) |
|
ü |
|
Implemented |
DEVB TC(W) No. 6/2010, Trip Ticket System for Disposal of Construction & Demolition Materials |
S8.5 |
Proper storage and site practices to reduce the potential for damage or contamination of construction materials. |
All areas/ During construction |
Contractor(s) |
|
ü |
|
Implemented |
- |
S8.5 |
Plan and stock construction materials carefully to reduce amount of waste generated and avoid unnecessary generation of waste. |
All areas/ During construction |
Contractor(s) |
|
ü |
|
Implemented |
- |
S8.5 |
A Sediment Quality Report (SQR) for sampling and chemical testing of the sediment will be prepared and submitted to the EPD for approval. The approved detailed sampling and chemical testing will be carried out prior to the commencement of the dredging activities to confirm the sediment disposal method. |
Marine works/ During construction |
Contractor(s) |
|
ü |
|
N/A |
ETWB TC(W) No. 34/2002 and Dumping at Sea Ordinance (DASO) |
EIA Reference |
Recommended Environmental Protection Measures/ Mitigation Measures |
Objectives of the recommended measures & main concerns to address |
Implementation Agent |
Implementation Stage |
Implementation Status |
Relevant Legislation & Guidelines |
||
D |
C |
O |
||||||
S8.5 |
The management of dredged/ excavated sediment management requirement from ETWB TC(W) No. 34/2002 will be incorporated in the Specification of the Contract Documents. |
Marine works/ During construction |
WSD/ Contractor(s) |
|
ü |
|
Implemented |
ETWB TC(W) No. 34/2002 and Dumping at Sea Ordinance (DASO) |
S8.5 |
The contractor will open a billing account with EPD in accordance with the Waste Disposal (Charges for Disposal of Construction Waste) Regulation for the payment of disposal charges. |
Contract mobilization/ During construction |
Contractor(s) |
|
ü |
|
Implemented |
Cap 354N Waste Disposal (Charges for Disposal of Construction Waste) Regulation |
S8.5 |
A trip-ticket system will be established in accordance with DEVB TC(W) No. 6/2010 to monitor the reuse of surplus excavated materials off-site and disposal of construction waste and general refuse at transfer facilities/ landfills, and to control fly-tipping. |
Contract mobilization/ During construction |
Contractor(s) |
|
ü |
|
Implemented |
DEVB TC(W) No. 6/2010, Trip Ticket System for Disposal of Construction & Demolition Materials |
S8.5 |
The project proponent will also conduct regular inspection of the waste management measures implemented on site as described in the Waste Management Plan. |
All area/ During construction |
Contractor(s)/ Environmental Team (ET) & Independent Environmental Checker (IEC) |
|
ü |
|
Implemented |
ETWB TC(W) No. 19/2005, Environmental Management on Construction Sites |
S8.5 |
A recording system (similar to summary table as shown in Annex 5 and Annex 6 of Appendix G of ETWB TC(W) No. 19/2005) for the amount of waste generated, recycled and disposed of (including the disposal sites) will be established during the construction phase. |
All area/ During construction |
Contractor(s) |
|
ü |
|
Implemented |
Annex 5 and Annex 6 of Appendix G of ETWB TC(W) No. 19/2005 |
S8.5 |
Inert C&D materials (public fill) will be reused within the Project as far as practicable. |
All area/ During construction |
Contractor(s) |
|
ü |
|
Implemented |
- |
S8.5 |
Public fill and construction waste shall be segregated and stored in different containers or skips to facilitate reuse or recycling of materials and their proper disposal. |
All area/ During construction |
Contractor(s) |
|
ü |
|
Implemented |
- |
S8.5 |
Specific areas of the work site will be designated for such segregation and storage if immediate use is not practicable. |
All area/ During construction |
Contractor(s) |
|
ü |
|
Implemented |
- |
S8.5 |
To reduce the potential dust and water quality impacts of site formation works, C&D materials will be wetted as quickly as possible to the extent practice after filling. |
All area/ During construction |
Contractor(s) |
|
ü |
|
Implemented |
Air Pollution Control (Construction Dust) Regulation (Cap 311R); WPCO (Cap 358) |
EIA Reference |
Recommended Environmental Protection Measures/ Mitigation Measures |
Objectives of the recommended measures & main concerns to address |
Implementation Agent |
Implementation Stage |
Implementation Status |
Relevant Legislation & Guidelines |
||
D |
C |
O |
||||||
S8.5 |
Open stockpiles of excavated/ fill materials or construction wastes on-site should be covered with tarpaulin or similar fabric. |
Land site/ During Construction, particularly dry season |
Contractor(s) |
|
ü |
|
Implemented |
Air Pollution Control (Construction Dust) Regulation (Cap 311R) |
S8.5 |
Chemical waste container shall be suitable for the substance they are holding, resistant to corrosion, maintained in a good condition, and securely closed. |
All area/ During construction/ During operation |
Contractor(s)/ WSD |
|
ü |
ü |
Implemented |
Waste Disposal (Chemical Waste) (General) Regulation; Code of Practice on the Packaging, Handling and Storage of Chemical Wastes |
S8.5 |
Chemical waste container shall have a capacity of less than 450 L unless the specifications have been approved by the EPD. |
All area/ During construction/ During operation |
Contractor(s)/ WSD |
|
ü |
ü |
Implemented |
|
S8.5 |
A label in English and Chinese shall be displayed on the chemical container in accordance with instructions prescribed in Schedule 2 of the Regulations. |
All area/ During construction/ During operation |
Contractor(s)/ WSD |
|
ü |
ü |
Implemented |
|
S8.5 |
Storage areas for chemical waste shall be enclosed on at least 3 sides. |
All area/ During construction/ During operation |
Contractor(s)/ WSD |
|
ü |
ü |
Implemented |
|
S8.5 |
Storage areas for chemical waste shall have an impermeable floor and bunding, of capacity to accommodate 110% of the volume of the largest container or 20% by volume of the chemical waste stored in that area, whichever is the greatest. |
All area/ During construction/ During operation |
Contractor(s)/ WSD |
|
ü |
ü |
Implemented |
|
S8.5 |
Storage areas for chemical waste shall have adequate ventilation. |
All area/ During construction/ During operation |
Contractor(s)/ WSD |
|
ü |
ü |
Implemented |
|
S8.5 |
Storage areas for chemical waste shall be covered to prevent rainfall entering (water collected within the bund must be tested and disposed of as chemical waste, if necessary). |
All area/ During construction/ During operation |
Contractor(s)/ WSD |
|
ü |
ü |
Implemented |
|
S8.5 |
Storage areas for chemical waste shall be arranged so that incompatible materials are appropriately separated. |
All area/ During construction/ During operation |
Contractor(s)/ WSD |
|
ü |
ü |
Implemented |
|
S8.5 |
General refuse will be stored in enclosed bins or compaction units separately from construction and chemical wastes. |
All area/ During construction/ During operation |
Contractor(s)/ WSD |
|
ü |
ü |
Implemented after reminder |
|
S8.5 |
Adequate number of waste containers will be provided to avoid over-spillage of waste. |
All area/ During construction/ During operation |
Contractor(s)/ WSD |
|
ü |
ü |
Implemented |
DEVB TC(W) No. 8/2010 Enhanced Specification for Site Cleanliness and Tidiness. |
EIA Reference |
Recommended Environmental Protection Measures/ Mitigation Measures |
Objectives of the recommended measures & main concerns to address |
Implementation Agent |
Implementation Stage |
Implementation Status |
Relevant Legislation & Guidelines |
||
D |
C |
O |
||||||
S8.5 |
A reputable waste collector will be employed by the Contractor to remove general refuse from the site, separately from construction and chemical wastes, on a daily basis to minimize odour, pest and litter impacts. |
All area/ During construction/ During operation |
Contractor(s)/ WSD |
|
ü |
ü |
Implemented |
- |
S8.5 |
Recycling bins will be provided at strategic locations within the Site to facilitate recovery of recyclable materials (including aluminum can, wastepaper, glass bottles and plastic bottles) from the Site. Materials recovered will be sold for recycling. |
All area/ During construction/ During operation |
Contractor(s)/ WSD |
|
ü |
ü |
Implemented |
- |
S8.5 |
To avoid any odour and litter impact, accurate number of portable toilets will be provided for workers on-site. |
All area/ During construction |
Contractor(s) |
|
ü |
|
Implemented |
- |
S8.5 |
The burning of refuse on construction sites is prohibited by law. |
All area/ During construction |
Contractor(s) |
|
ü |
|
Implemented |
Air Pollution Control Ordinance (Cap 311) |
S8.7 |
To facilitate monitoring and control over the contractors’ performance on waste management, a waste inspection and audit programme will be implemented throughout the construction phase. |
All facilities/ During construction |
ET/ IEC |
|
ü |
|
Implemented |
- |
Note: D - Design stage C - Construction O - Operation
EIA Reference |
Recommended Environmental Protection Measures/ Mitigation Measures |
Objectives of the recommended measures & main concerns to address |
Implementation Agent |
Implementation Stage |
Implementation Status |
Relevant Legislation & Guidelines |
||
D |
C |
O |
||||||
Ecology |
||||||||
S9.7 |
For slope mitigation works within the Clear Water Bay Country Park, to avoid tree felling and damages to trees, the exact locations of the flexible barrier foundation plates, soil nails and rock dowels can be adjusted during detailed design, and a setback distance from existing trees is recommended to be maintained as far as practical. A detailed specification describing the exact locations of the flexible barrier foundation plates, soil nails and rock dowels will be prepared to illustrate how the setback distance from existing trees would be implemented for tree avoidance. |
Slope mitigation works area/ During detailed design/ During construction |
Contractor(s) |
ü |
ü |
|
Implemented |
- |
S9.7 |
Pruning of tree canopies along the alignment of the flexible barriers shall be limited to a minimum. |
Slope mitigation works area/ During construction |
Contractor(s) |
|
ü |
|
Implemented |
|
S9.7 |
The alignment of flexible barriers shall be optimized to preserve all species of conservation interest and minimize the impact to the existing vegetation as far as practicable. All individuals of Marsdenia lachnostoma within the slope mitigation areas shall be retained in- situ, by positioning the alignment of flexible barrier at a minimum 1.5m in a radius away from these individuals. |
Slope mitigation works area/ During detailed design/ During construction |
Contractor(s) |
ü |
ü |
|
Implemented |
- |
S9.7 and 9.10 |
At the detailed design stage prior to the commencement of the slope mitigation works, a vegetation survey shall be carried out at the slope mitigation areas within the Clear Water Bay Country Park to assess the condition and identify the location of each individual of Marsdenia lachnostoma and other flora species of conservation interest that may be directly affected by the construction works. |
Slope mitigation works area/ During detailed design/ During construction |
Contractor(s) |
ü |
|
|
Implemented |
- |
S9.7 |
Temporary fencing will be installed to fence off the concerned species either in groups of individually within the works area and in the close proximity to prevent from being damaged and disturbed during construction. A sign identifying the site shall be attached to the fence and flagging tape shall be attached to the individuals to visualize their locations. |
Slope mitigation works area/ During construction |
Contractor(s) |
|
ü |
|
Implemented |
- |
S9.7 and S9.10 |
A specification for fencing and demarcating individuals of Marsdenai lachnostoma (or other flora species of conservation interest, if found) adjacent to the proposed alignment of the flexible barriers will be prepared to protect the species. |
Slope mitigation works area/ During construction |
Contractor(s) |
|
ü |
|
Implemented |
- |
S9.7 |
Induction training shall also be provided to all site personnel in order to brief them on this flora of conservation interest including the locations and their importance. |
Slope mitigation works area/ During construction |
Contractor(s) |
|
ü |
|
Implemented |
- |
EIA Reference |
Recommended Environmental Protection Measures/ Mitigation Measures |
Objectives of the recommended measures & main concerns to address |
Implementation Agent |
Implementation Stage |
Implementation Status |
Relevant Legislation & Guidelines |
||
D |
C |
O |
||||||
S9.7 |
The resident site supervisory staff will closely monitor the conditions of concerned individuals during construction of flexible barriers in the close proximity. |
Slope mitigation works area/ During construction |
Contractor(s) |
|
ü |
|
Implemented |
- |
S9.7 |
Erect fences along the boundary of the works area before the commencement of works to prevent vehicle movements and encroachment of personnel onto adjacent areas. |
All area/ During construction |
Contractor(s) |
|
ü |
|
Implemented |
- |
S9.7 |
Regularly check the work site boundaries to ensure that they are not breached, and that damage does not occur to surrounding areas. |
All area/ During construction |
Contractor(s)/ ET |
|
ü |
|
Implemented |
- |
S9.7 |
Avoid any damage and disturbance, particularly those caused by filling and illegal dumping, to the surrounding habitats through proper management of waste disposal. |
All area/ During construction |
Contractor(s) |
|
ü |
|
Implemented |
- |
S9.7 |
Reinstate temporarily affected areas, particularly the habitats of plantation and shrubland-grassland immediately after completion of construction works, through on-site tree/shrub planting. The tree/shrub species will be chosen with reference to those in the surrounding area. |
All area/ During construction |
Contractor(s) |
|
ü |
|
To be implemented |
- |
S9.7 |
Affected habitats within the Clear Water Bay Country Bay shall be reinstated by hydro-seeding and planting of climbers and native shrub seedlings where practical upon completion of the slope mitigation works. |
All area/ During construction |
Contractor(s) |
|
ü |
|
To be implemented |
- |
Note: D - Design stage C - Construction O - Operation
EIA Reference |
Recommended Environmental Protection Measures/ Mitigation Measures |
Objectives of the recommended measures & main concerns to address |
Implementation Agent |
Implementation Stage |
Implementation Status |
Relevant Legislation & Guidelines |
||
D |
C |
O |
||||||
Landscape & Visual |
||||||||
S11.10 & 11.11 |
The construction area and area allowed for temporary structures, such as the contractor’s
office, will be minimized to a practical minimum. (MM1) |
All area/ Detailed design/ During construction/ During operation |
WSD/ Contractor(s) |
ü |
ü |
ü |
Implemented |
- |
S11.10 & 11.11 |
At the detailed design stage, the design team will seek to minimize the landscape footprint of the Project and above ground facilities, while satisfying all other requirements. (MM2) |
All area/ Detailed design/ During construction/ During operation |
WSD/ Contractor(s) |
ü |
ü |
ü |
Implemented |
- |
S11.10 & 11.11 |
Design principles will be adopted to take into account the surrounding area, particularly Clear Water Bay Country Park behind and the nearby waterfront, with due consideration given to: - green roofs where practical (i.e. without equipment on the roof); - roadside planting; - aesthetic treatment of all structures; - vertical greening; - screen planting along application site; and - landscape enhancement with amenity planting where practical including planting along the edge (site boundary) fence with native shrubs where feasible, to reduce their visual impact and blend them into the surrounding landscape. (MM3) |
All area/ Detailed design/ During construction/ During operation |
WSD/ Contractor(s) |
ü |
ü |
ü |
Implemented |
- |
S11.10 & 11.11 |
All trees within the Project Site or the potential slope mitigation works area will be carefully protected during construction according to DEVB TCW No. 10/2013 - Tree Preservation (MM4) |
All area/ Detailed design/ During construction/ During operation |
WSD/ Contractor(s) |
ü |
ü |
ü |
Implemented |
ETWB TCW No. 3/2006 - Tree Preservation. |
S11.10 & 11.11 |
No tree within the Country Park will be felled. Trees within the Site unavoidably affected by the works will be transplanted where necessary and practical. For trees that need to be felled, compensatory planting will be provided to the satisfaction of |
All area/ Detailed design/ During construction/ During operation |
WSD/ Contractor(s) |
ü |
ü |
ü |
Implemented |
DEVB TC(W) No. 10/2013 |
|
relevant Government departments. |
|
|
|
|
|
|
|
|
A compensatory tree planting proposal including locations of |
|
|
|
|
|
|
|
|
tree compensation will be submitted to seek relevant |
|
|
|
|
|
|
|
|
government department’s approval, in accordance with DEVB |
|
|
|
|
|
|
|
|
TC(W) No. 10/2013. (MM5) |
|
|
|
|
|
|
|
S11.10 & 11.11 |
Any slope mitigation works necessary to address natural terrain hazards, will be minimized to minimize any potential environmental impact to the Country Park e.g. soil nailing and rock stabilization will aim to avoid existing trees e.g. should any restoration of vegetation be necessary, the best planting matrix with native species will be established, with the aim of resembling the existing vegetation. (MM6) |
All area/ Detailed design/ During construction/ During operation |
WSD/ Contractor(s) |
ü |
ü |
ü |
Implemented |
|
EIA Reference |
Recommended Environmental Protection Measures/ Mitigation Measures |
Objectives of the recommended measures & main concerns to address |
Implementation Agent |
Implementation Stage |
Implementation Status |
Relevant Legislation & Guidelines |
||
D |
C |
O |
||||||
S11.10 & 11.11 |
Dredging works for the installation of intake structures and outfall diffusers should be minimized to avoid or reduce any potential environmental impacts to as low as reasonably practicable (ALARP). The intake and outfall structures (e.g. intake openings and diffuser heads) will be prefabricated and transferred to site for installation. (MM7) |
All area/ Detailed design/ During construction/ During operation |
WSD/ Contractor(s) |
ü |
ü |
ü |
Implemented |
|
S11.10 & 11.11 |
All night-time lighting will be reduced to a practical minimum both in terms of number of level and will be hooded and directional. (MM8) units and lux level and will be hooded and directional. (MM8) |
All area/ Detailed design/ During construction/ During operation |
WSD/ Contractor(s) |
ü |
ü |
ü |
Implemented |
- |
Note: D - Design stage C - Construction O - Operation
EIA Reference |
Recommended Environmental Protection Measures/ Mitigation Measures |
Objectives of the recommended measures & main concerns to address |
Implementation Agent |
Implementation Stage |
Implementation Status |
Relevant Legislation & Guidelines |
||
D |
C |
O |
||||||
Landfill Gas Hazard |
||||||||
S12.7 |
During all works, safety procedures should be implemented to minimize the risks of fires and explosions, asphyxiation of workers and toxicity effects resulting from contact with contaminated soil and groundwater. |
All area/ Detailed design/ During construction/operation |
Contractor(s) |
ü |
ü |
ü |
Implemented |
- |
S12.7 |
During trenching and excavation as well as creation of confined spaces at near to or below ground level, precautions should be clearly laid down and rigidly Gas detection equipment and appropriate breathing apparatus should be available and used when entering confined spaces or trenches deeper than 1 meter. |
All area/ Detailed design/ During construction/operation |
Contractor(s) |
ü |
ü |
ü |
Implemented |
|
S12.7 |
The Contractor should make the workers are aware of potential hazards of working in confined spaces (any chamber, manhole or culvert which is large enough to permit access to personnel). Such work in confined spaces is controlled by the Factories and Industrial Undertakings (Confined Spaces) Regulations of the Factories and Industrial Undertakings Ordinance. Following the Safety Guide to Working in Confined Spaces ensures compliance with the above regulations. |
All area/ Detailed design/ During construction/operation |
Contractor(s) |
ü |
ü |
ü |
Implemented |
|
S12.7 |
Safety officers, specifically trained with regard to landfill gas and leachate related hazards and the appropriate actions to take in adverse circumstances, should be present on the site throughout the works, in particular, when works are undertaken below grade. |
All area/ Detailed design/ During construction/operation |
Contractor(s) |
ü |
ü |
ü |
Implemented |
|
S12.7 |
All personnel who work on site and all visitors to the site should be made aware of the possibility of ignition of gas in the vicinity of the works, the possible presence of contaminated water and the need to avoid physical contact with it. |
All area/ Detailed design/ During construction/operation |
Contractor(s) |
ü |
ü |
ü |
Implemented |
|
S12.7 |
Monitoring for landfill gas should be undertaken in all excavations, manholes, chambers (particularly during pipe jacking) and any confined spaces through the use of an intrinsically safe portable instrument, appropriately calibrated and capable of measuring the concentrations of methane. carbon dioxide and oxygen. |
All area/ Detailed design/ During construction/operation |
Contractor(s) |
ü |
ü |
ü |
Implemented |
|
S12.7 |
Monitoring frequency and areas to be monitored should be specified prior to commencement of groundwork, either by the Safety Officer, or by an appropriately qualified person. All measurements should be recorded and documented. |
All area/ Detailed design/ During construction/operation |
Contractor(s) |
ü |
ü |
ü |
Implemented |
|
S12.7 |
Proceed drilling with adequate care and precautions against the potential hazards which may be encountered. |
All area/ Detailed design/ During construction/operation |
Contractor(s) |
ü |
ü |
ü |
Implemented |
|
EIA Reference |
Recommended Environmental Protection Measures/ Mitigation Measures |
Objectives of the recommended measures & main concerns to address |
Implementation Agent |
Implementation Stage |
Implementation Status |
Relevant Legislation & Guidelines |
||
D |
C |
O |
||||||
S12.7 |
Prior to the commencement of the site works, the drilling contractor should devise a 'method-of- working' statement covering all normal and emergency procedures (including but not limited to number of operatives, experience and special skills of operatives, normal method of operations, emergency procedures, supervisors responsibilities, storage and use of safety equipment, safety procedures and signs, barriers and guarding). The site supervisor and all operatives must be familiar with this statement. |
All area/ During construction/operation |
Contractor(s) |
ü |
ü |
ü |
Implemented |
|
S12.7 |
Where below ground service entries are necessary to the Incoming Switchgear Room, 132 kV Substation and Chlorine Store (I) and (II), the entry point should be sealed to prevent gas entry. In addition, any below grade cable trenches entering the Incoming Switchgear Room and 132 kV Substation can become the pathway for landfill gas and hence grilled metal covers should be used. |
All area/ Detailed design/ During construction/operation |
Contractor(s) |
ü |
ü |
ü |
N/A |
|
S12.7 |
It is recommended regular landfill gas monitoring should be carried out at the Incoming Switchgear Room, 132 kV Substation and Chlorine Store (I) and (II). The monitoring frequency will be monthly for the first year of operation. If the monitoring results show no sign of landfill gas migration, reduce the monitoring frequency to once every six months. |
All area/ Detailed design/ During construction/operation |
Contractor(s) |
ü |
ü |
ü |
N/A |
|
S12.7 |
The manholes and utility pits within the Project Site and along the fresh water mains. Each manhole/ utility pit should be monitored with two measurements (at mid depth and base). Each measurement should be monitored for a minimum of 10 minutes. A steady reading and peak reading should be recorded at each manhole/ utility pit and for each measurement. The need for venting the manhole/ utility pit and further monitoring will be reviewed after the initial monitoring. |
All area/ Detailed design/ During construction/operation |
Contractor(s) |
ü |
ü |
ü |
Implemented |
|
S12.7 |
All construction, operation and maintenance personnel working on-site as well as visitors should be made aware of the hazards of landfill gas and its possible presence on-site. This should be achieved through a combination of posting warning signs in prominent places and also by access to detailed information on landfill gas hazards and the designs and procedural means by which these hazards are being minimized on-site. |
All area/ Detailed design/ During construction/operation |
Contractor(s) |
ü |
ü |
ü |
Implemented |
|
Note: D - Design stage C - Construction O - Operation
Table E1 Event and Action Plan for Construction Noise Monitoring
Table E2 Event and Action Plan for Water Quality Monitoring
Table E2 Event and Action Plan for Ecology during Construction Phase
Table E3 Event and Action Plan for Pre-Operation Phase Coral Monitoring
Appendix F
Water Quality Monitoring Equipment and Landfill Gas Equipment
Calibration Certification
Appendix G
Water Quality Monitoring Data & Landfill Gas Monitoring Data
Location Date Tidal Weather Sea Condition Water Level Depth (m) Time DO (mg/L) pH Sal (ppt) Temp (°C) Turbidty (NTU) SS (mg/L) Iron (mg/L) Total Chlorine
CE |
12/12/2023 |
Mid-ebb |
Sunny |
Moderate |
S |
1 |
10:06:00 AM |
9.5 |
6.7 |
32.1 |
22.1 |
3.6 |
4.0 |
<0.10 |
<0.01 |
CE |
12/12/2023 |
Mid-ebb |
Sunny |
Moderate |
S |
1 |
10:06:00 AM |
9.4 |
6.7 |
32.2 |
22.1 |
3.5 |
5.0 |
<0.10 |
<0.01 |
CE |
12/12/2023 |
Mid-ebb |
Sunny |
Moderate |
M |
12 |
10:07:00 AM |
9.4 |
6.7 |
32.3 |
22.1 |
3.6 |
4.0 |
<0.10 |
<0.01 |
CE |
12/12/2023 |
Mid-ebb |
Sunny |
Moderate |
M |
12 |
10:07:00 AM |
9.4 |
6.6 |
32.3 |
22.1 |
3.6 |
4.0 |
<0.10 |
<0.01 |
CE |
12/12/2023 |
Mid-ebb |
Sunny |
Moderate |
B |
23 |
10:08:00 AM |
9.5 |
6.7 |
32.3 |
22.2 |
3.7 |
5.0 |
<0.10 |
<0.01 |
CE |
12/12/2023 |
Mid-ebb |
Sunny |
Moderate |
B |
23 |
10:08:00 AM |
9.5 |
6.7 |
32.4 |
22.2 |
3.6 |
4.0 |
<0.10 |
<0.01 |
CF |
12/12/2023 |
Mid-ebb |
Sunny |
Moderate |
S |
1 |
12:37:00 PM |
9.9 |
6.6 |
32.5 |
21.9 |
3.2 |
4.0 |
<0.10 |
<0.01 |
CF |
12/12/2023 |
Mid-ebb |
Sunny |
Moderate |
S |
1 |
12:37:00 PM |
10.0 |
6.7 |
32.3 |
21.9 |
3.2 |
3.0 |
<0.10 |
<0.01 |
CF |
12/12/2023 |
Mid-ebb |
Sunny |
Moderate |
M |
10 |
12:38:00 PM |
10.0 |
6.6 |
32.6 |
21.9 |
3.1 |
4.0 |
<0.10 |
<0.01 |
CF |
12/12/2023 |
Mid-ebb |
Sunny |
Moderate |
M |
10 |
12:38:00 PM |
9.9 |
6.6 |
32.4 |
21.9 |
3.1 |
4.0 |
<0.10 |
<0.01 |
CF |
12/12/2023 |
Mid-ebb |
Sunny |
Moderate |
B |
19 |
12:39:00 PM |
10.1 |
6.7 |
32.7 |
21.9 |
3.1 |
4.0 |
<0.10 |
<0.01 |
CF |
12/12/2023 |
Mid-ebb |
Sunny |
Moderate |
B |
19 |
12:39:00 PM |
10.0 |
6.7 |
32.4 |
21.9 |
3.1 |
5.0 |
<0.10 |
<0.01 |
WSR01 |
12/12/2023 |
Mid-ebb |
Sunny |
Moderate |
S |
1 |
12:11:00 PM |
9.8 |
6.6 |
32.9 |
22.1 |
2.4 |
3.0 |
<0.10 |
<0.01 |
WSR01 |
12/12/2023 |
Mid-ebb |
Sunny |
Moderate |
S |
1 |
12:11:00 PM |
9.8 |
6.6 |
33.1 |
22.1 |
2.4 |
4.0 |
<0.10 |
<0.01 |
WSR01 |
12/12/2023 |
Mid-ebb |
Sunny |
Moderate |
M |
4 |
12:12:00 PM |
9.8 |
6.7 |
33.0 |
22.1 |
2.4 |
4.0 |
<0.10 |
<0.01 |
WSR01 |
12/12/2023 |
Mid-ebb |
Sunny |
Moderate |
M |
4 |
12:12:00 PM |
9.7 |
6.7 |
33.0 |
22.1 |
2.4 |
5.0 |
<0.10 |
<0.01 |
WSR01 |
12/12/2023 |
Mid-ebb |
Sunny |
Moderate |
B |
8 |
12:13:00 PM |
9.7 |
6.7 |
33.0 |
22.0 |
2.4 |
3.0 |
<0.10 |
<0.01 |
WSR01 |
12/12/2023 |
Mid-ebb |
Sunny |
Moderate |
B |
8 |
12:13:00 PM |
9.7 |
6.7 |
33.0 |
22.0 |
2.5 |
3.0 |
<0.10 |
<0.01 |
WSR02 |
12/12/2023 |
Mid-ebb |
Sunny |
Moderate |
S |
1 |
11:50:00 AM |
9.7 |
6.8 |
32.1 |
22.1 |
2.5 |
3.0 |
<0.10 |
<0.01 |
WSR02 |
12/12/2023 |
Mid-ebb |
Sunny |
Moderate |
S |
1 |
11:50:00 AM |
9.8 |
6.8 |
32.1 |
22.1 |
2.4 |
6.0 |
<0.10 |
<0.01 |
WSR02 |
12/12/2023 |
Mid-ebb |
Sunny |
Moderate |
M |
5 |
11:51:00 AM |
9.7 |
6.8 |
32.3 |
22.1 |
2.4 |
6.0 |
<0.10 |
<0.01 |
WSR02 |
12/12/2023 |
Mid-ebb |
Sunny |
Moderate |
M |
5 |
11:51:00 AM |
9.7 |
6.8 |
32.5 |
22.1 |
2.5 |
4.0 |
<0.10 |
<0.01 |
WSR02 |
12/12/2023 |
Mid-ebb |
Sunny |
Moderate |
B |
9 |
11:52:00 AM |
9.7 |
6.8 |
32.4 |
22.1 |
2.3 |
4.0 |
<0.10 |
<0.01 |
WSR02 |
12/12/2023 |
Mid-ebb |
Sunny |
Moderate |
B |
9 |
11:52:00 AM |
9.6 |
6.9 |
32.1 |
22.1 |
2.3 |
4.0 |
<0.10 |
<0.01 |
WSR03 |
12/12/2023 |
Mid-ebb |
Sunny |
Moderate |
S |
1 |
11:32:00 AM |
10.0 |
6.8 |
33.4 |
21.9 |
2.2 |
4.0 |
<0.10 |
<0.01 |
WSR03 |
12/12/2023 |
Mid-ebb |
Sunny |
Moderate |
S |
1 |
11:32:00 AM |
10.1 |
6.8 |
33.3 |
22.0 |
2.3 |
3.0 |
<0.10 |
<0.01 |
WSR03 |
12/12/2023 |
Mid-ebb |
Sunny |
Moderate |
M |
4 |
11:33:00 AM |
9.9 |
6.7 |
33.4 |
21.9 |
2.4 |
5.0 |
<0.10 |
<0.01 |
WSR03 |
12/12/2023 |
Mid-ebb |
Sunny |
Moderate |
M |
4 |
11:33:00 AM |
10.0 |
6.8 |
33.2 |
21.9 |
2.4 |
4.0 |
<0.10 |
<0.01 |
WSR03 |
12/12/2023 |
Mid-ebb |
Sunny |
Moderate |
B |
7 |
11:34:00 AM |
9.9 |
6.7 |
33.2 |
21.9 |
2.6 |
3.0 |
<0.10 |
<0.01 |
WSR03 |
12/12/2023 |
Mid-ebb |
Sunny |
Moderate |
B |
7 |
11:34:00 AM |
10.1 |
6.8 |
33.1 |
22.0 |
2.5 |
2.5 |
<0.10 |
<0.01 |
WSR04 |
12/12/2023 |
Mid-ebb |
Sunny |
Moderate |
S |
1 |
11:17:00 AM |
9.1 |
6.8 |
33.4 |
22.1 |
2.2 |
5.0 |
<0.10 |
<0.01 |
WSR04 |
12/12/2023 |
Mid-ebb |
Sunny |
Moderate |
S |
1 |
11:17:00 AM |
9.1 |
6.7 |
33.6 |
22.2 |
2.2 |
5.0 |
<0.10 |
<0.01 |
WSR04 |
12/12/2023 |
Mid-ebb |
Sunny |
Moderate |
M |
3 |
11:18:00 AM |
8.9 |
6.8 |
33.7 |
22.1 |
2.2 |
4.0 |
<0.10 |
<0.01 |
WSR04 |
12/12/2023 |
Mid-ebb |
Sunny |
Moderate |
M |
3 |
11:18:00 AM |
9.1 |
6.8 |
33.7 |
22.2 |
2.2 |
4.0 |
<0.10 |
<0.01 |
WSR04 |
12/12/2023 |
Mid-ebb |
Sunny |
Moderate |
B |
6 |
11:19:00 AM |
9.1 |
6.8 |
33.5 |
22.2 |
2.3 |
6.0 |
<0.10 |
<0.01 |
WSR04 |
12/12/2023 |
Mid-ebb |
Sunny |
Moderate |
B |
6 |
11:19:00 AM |
9.1 |
6.7 |
33.8 |
22.2 |
2.2 |
5.0 |
<0.10 |
<0.01 |
Location Date Tidal Weather Sea Condition Water Level Depth (m) Time DO (mg/L) pH Sal (ppt) Temp (°C) Turbidty (NTU) SS (mg/L) Iron (mg/L) Total Chlorine
WSR16 |
12/12/2023 |
Mid-ebb |
Sunny |
Moderate |
S |
1 |
10:31:00 AM |
9.2 |
6.7 |
32.9 |
21.9 |
2.1 |
4.0 |
<0.10 |
<0.01 |
WSR16 |
12/12/2023 |
Mid-ebb |
Sunny |
Moderate |
S |
1 |
10:31:00 AM |
9.5 |
6.7 |
32.9 |
22.0 |
2.2 |
4.0 |
<0.10 |
<0.01 |
WSR16 |
12/12/2023 |
Mid-ebb |
Sunny |
Moderate |
M |
8 |
10:32:00 AM |
9.5 |
6.7 |
33.1 |
22.0 |
2.2 |
4.0 |
<0.10 |
<0.01 |
WSR16 |
12/12/2023 |
Mid-ebb |
Sunny |
Moderate |
M |
8 |
10:32:00 AM |
9.3 |
6.7 |
33.1 |
21.9 |
2.3 |
5.0 |
<0.10 |
<0.01 |
WSR16 |
12/12/2023 |
Mid-ebb |
Sunny |
Moderate |
B |
16 |
10:33:00 AM |
9.3 |
6.7 |
33.0 |
21.9 |
2.8 |
8.0 |
<0.10 |
<0.01 |
WSR16 |
12/12/2023 |
Mid-ebb |
Sunny |
Moderate |
B |
16 |
10:33:00 AM |
9.2 |
6.7 |
33.1 |
21.9 |
2.8 |
10.0 |
<0.10 |
<0.01 |
WSR33 |
12/12/2023 |
Mid-ebb |
Sunny |
Moderate |
S |
1 |
11:00:00 AM |
10.1 |
6.8 |
33.0 |
22.3 |
2.3 |
5.0 |
<0.10 |
<0.01 |
WSR33 |
12/12/2023 |
Mid-ebb |
Sunny |
Moderate |
S |
1 |
11:00:00 AM |
9.9 |
6.8 |
32.9 |
22.2 |
2.3 |
5.0 |
<0.10 |
<0.01 |
WSR33 |
12/12/2023 |
Mid-ebb |
Sunny |
Moderate |
M |
4 |
11:01:00 AM |
10.1 |
6.8 |
32.9 |
22.3 |
2.4 |
3.0 |
<0.10 |
<0.01 |
WSR33 |
12/12/2023 |
Mid-ebb |
Sunny |
Moderate |
M |
4 |
11:01:00 AM |
9.8 |
6.8 |
32.8 |
22.3 |
2.3 |
5.0 |
<0.10 |
<0.01 |
WSR33 |
12/12/2023 |
Mid-ebb |
Sunny |
Moderate |
B |
7 |
11:02:00 AM |
10.1 |
6.8 |
33.0 |
22.2 |
2.4 |
5.0 |
<0.10 |
<0.01 |
WSR33 |
12/12/2023 |
Mid-ebb |
Sunny |
Moderate |
B |
7 |
11:02:00 AM |
10.0 |
6.8 |
32.8 |
22.3 |
2.3 |
5.0 |
<0.10 |
<0.01 |
WSR36 |
12/12/2023 |
Mid-ebb |
Sunny |
Moderate |
S |
1 |
10:44:00 AM |
10.2 |
6.9 |
33.7 |
22.0 |
2.3 |
8.0 |
<0.10 |
<0.01 |
WSR36 |
12/12/2023 |
Mid-ebb |
Sunny |
Moderate |
S |
1 |
10:44:00 AM |
10.3 |
6.8 |
33.7 |
21.9 |
2.4 |
5.0 |
<0.10 |
<0.01 |
WSR36 |
12/12/2023 |
Mid-ebb |
Sunny |
Moderate |
M |
3 |
10:45:00 AM |
10.3 |
6.8 |
33.7 |
21.9 |
2.3 |
4.0 |
<0.10 |
<0.01 |
WSR36 |
12/12/2023 |
Mid-ebb |
Sunny |
Moderate |
M |
3 |
10:45:00 AM |
10.3 |
6.9 |
33.6 |
22.0 |
2.3 |
8.0 |
<0.10 |
<0.01 |
WSR36 |
12/12/2023 |
Mid-ebb |
Sunny |
Moderate |
B |
5 |
10:45:00 AM |
10.2 |
6.8 |
33.6 |
22.0 |
2.3 |
8.0 |
<0.10 |
<0.01 |
WSR36 |
12/12/2023 |
Mid-ebb |
Sunny |
Moderate |
B |
5 |
10:45:00 AM |
10.5 |
6.8 |
33.8 |
22.0 |
2.3 |
6.0 |
<0.10 |
<0.01 |
WSR37 |
12/12/2023 |
Mid-ebb |
Sunny |
Moderate |
S |
1 |
10:38:00 AM |
9.9 |
6.9 |
31.8 |
22.0 |
2.2 |
6.0 |
<0.10 |
<0.01 |
WSR37 |
12/12/2023 |
Mid-ebb |
Sunny |
Moderate |
S |
1 |
10:38:00 AM |
9.9 |
6.8 |
31.9 |
22.0 |
2.3 |
8.0 |
<0.10 |
<0.01 |
WSR37 |
12/12/2023 |
Mid-ebb |
Sunny |
Moderate |
M |
4 |
10:39:00 AM |
10.1 |
6.8 |
31.8 |
22.0 |
2.3 |
7.0 |
<0.10 |
<0.01 |
WSR37 |
12/12/2023 |
Mid-ebb |
Sunny |
Moderate |
M |
4 |
10:39:00 AM |
10.0 |
6.8 |
31.8 |
22.0 |
2.2 |
7.0 |
<0.10 |
<0.01 |
WSR37 |
12/12/2023 |
Mid-ebb |
Sunny |
Moderate |
B |
7 |
10:40:00 AM |
9.9 |
6.9 |
32.0 |
22.0 |
2.3 |
7.0 |
<0.10 |
<0.01 |
WSR37 |
12/12/2023 |
Mid-ebb |
Sunny |
Moderate |
B |
7 |
10:40:00 AM |
10.0 |
6.8 |
32.0 |
21.9 |
2.2 |
8.0 |
<0.10 |
<0.01 |
NF1 |
12/12/2023 |
Mid-ebb |
Sunny |
Moderate |
S |
1 |
10:55:00 AM |
9.8 |
6.8 |
33.2 |
22.0 |
2.1 |
7.0 |
<0.10 |
<0.01 |
NF1 |
12/12/2023 |
Mid-ebb |
Sunny |
Moderate |
S |
1 |
10:55:00 AM |
9.8 |
6.8 |
32.8 |
21.9 |
2.2 |
5.0 |
<0.10 |
<0.01 |
NF1 |
12/12/2023 |
Mid-ebb |
Sunny |
Moderate |
M |
7 |
10:56:00 AM |
9.8 |
6.8 |
33.1 |
22.0 |
2.1 |
6.0 |
<0.10 |
<0.01 |
NF1 |
12/12/2023 |
Mid-ebb |
Sunny |
Moderate |
M |
7 |
10:56:00 AM |
9.6 |
6.8 |
33.2 |
22.0 |
2.2 |
5.0 |
<0.10 |
<0.01 |
NF1 |
12/12/2023 |
Mid-ebb |
Sunny |
Moderate |
B |
12 |
10:57:00 AM |
9.5 |
6.8 |
33.2 |
21.9 |
2.2 |
4.0 |
<0.10 |
<0.01 |
NF1 |
12/12/2023 |
Mid-ebb |
Sunny |
Moderate |
B |
12 |
10:57:00 AM |
9.6 |
6.8 |
32.9 |
21.9 |
2.1 |
6.0 |
<0.10 |
<0.01 |
NF2 |
12/12/2023 |
Mid-ebb |
Sunny |
Moderate |
S |
1 |
11:12:00 AM |
9.1 |
6.7 |
33.1 |
21.8 |
2.2 |
5.0 |
<0.10 |
<0.01 |
NF2 |
12/12/2023 |
Mid-ebb |
Sunny |
Moderate |
S |
1 |
11:12:00 AM |
9.3 |
6.6 |
33.0 |
21.7 |
2.2 |
7.0 |
<0.10 |
<0.01 |
NF2 |
12/12/2023 |
Mid-ebb |
Sunny |
Moderate |
M |
5 |
11:13:00 AM |
9.3 |
6.6 |
33.3 |
21.8 |
2.4 |
4.0 |
<0.10 |
<0.01 |
NF2 |
12/12/2023 |
Mid-ebb |
Sunny |
Moderate |
M |
5 |
11:13:00 AM |
9.2 |
6.6 |
33.0 |
21.8 |
2.5 |
5.0 |
<0.10 |
<0.01 |
NF2 |
12/12/2023 |
Mid-ebb |
Sunny |
Moderate |
B |
9 |
11:14:00 AM |
9.3 |
6.5 |
33.3 |
21.8 |
2.6 |
4.0 |
<0.10 |
<0.01 |
NF2 |
12/12/2023 |
Mid-ebb |
Sunny |
Moderate |
B |
9 |
11:14:00 AM |
9.4 |
6.6 |
33.3 |
21.8 |
2.5 |
5.0 |
<0.10 |
<0.01 |
Location Date Tidal Weather Sea Condition Water Level Depth (m) Time DO (mg/L) pH Sal (ppt) Temp (°C) Turbidty (NTU) SS (mg/L) Iron (mg/L) Total Chlorine
NF3 |
12/12/2023 |
Mid-ebb |
Sunny |
Moderate |
S |
1 |
11:20:00 AM |
9.5 |
6.6 |
32.9 |
22.3 |
2.3 |
5.0 |
<0.10 |
<0.01 |
NF3 |
12/12/2023 |
Mid-ebb |
Sunny |
Moderate |
S |
1 |
11:20:00 AM |
9.4 |
6.7 |
32.8 |
22.2 |
2.3 |
5.0 |
<0.10 |
<0.01 |
NF3 |
12/12/2023 |
Mid-ebb |
Sunny |
Moderate |
M |
6 |
11:21:00 AM |
9.4 |
6.7 |
32.8 |
22.2 |
2.4 |
6.0 |
<0.10 |
<0.01 |
NF3 |
12/12/2023 |
Mid-ebb |
Sunny |
Moderate |
M |
6 |
11:21:00 AM |
9.6 |
6.7 |
32.6 |
22.2 |
2.3 |
4.0 |
<0.10 |
<0.01 |
NF3 |
12/12/2023 |
Mid-ebb |
Sunny |
Moderate |
B |
11 |
11:22:00 AM |
9.6 |
6.6 |
32.5 |
22.2 |
2.5 |
4.0 |
<0.10 |
<0.01 |
NF3 |
12/12/2023 |
Mid-ebb |
Sunny |
Moderate |
B |
11 |
11:22:00 AM |
9.5 |
6.6 |
32.8 |
22.2 |
2.6 |
4.0 |
<0.10 |
<0.01 |
CE |
14/12/2023 |
Mid-flood |
Sunny |
Moderate |
S |
1 |
11:21:00 AM |
9.5 |
7.3 |
33.1 |
21.4 |
2.8 |
4.0 |
<0.10 |
<0.01 |
CE |
14/12/2023 |
Mid-flood |
Sunny |
Moderate |
S |
1 |
11:21:00 AM |
9.6 |
7.4 |
33.0 |
21.5 |
2.9 |
3.0 |
<0.10 |
<0.01 |
CE |
14/12/2023 |
Mid-flood |
Sunny |
Moderate |
M |
12 |
11:22:00 AM |
9.6 |
7.4 |
33.0 |
21.5 |
2.8 |
3.0 |
<0.10 |
<0.01 |
CE |
14/12/2023 |
Mid-flood |
Sunny |
Moderate |
M |
12 |
11:22:00 AM |
9.7 |
7.4 |
32.9 |
21.4 |
2.8 |
4.0 |
<0.10 |
<0.01 |
CE |
14/12/2023 |
Mid-flood |
Sunny |
Moderate |
B |
23 |
11:23:00 AM |
9.7 |
7.3 |
32.9 |
21.5 |
2.6 |
4.0 |
<0.10 |
<0.01 |
CE |
14/12/2023 |
Mid-flood |
Sunny |
Moderate |
B |
23 |
11:23:00 AM |
9.5 |
7.3 |
32.9 |
21.5 |
2.5 |
4.0 |
<0.10 |
<0.01 |
CF |
14/12/2023 |
Mid-flood |
Sunny |
Moderate |
S |
1 |
8:03:00 AM |
8.8 |
7.2 |
32.3 |
21.8 |
3.4 |
4.0 |
<0.10 |
<0.01 |
CF |
14/12/2023 |
Mid-flood |
Sunny |
Moderate |
S |
1 |
8:03:00 AM |
8.8 |
7.3 |
32.4 |
21.7 |
3.3 |
3.0 |
<0.10 |
<0.01 |
CF |
14/12/2023 |
Mid-flood |
Sunny |
Moderate |
M |
10 |
8:04:00 AM |
8.7 |
7.2 |
32.3 |
21.7 |
3.2 |
4.0 |
<0.10 |
<0.01 |
CF |
14/12/2023 |
Mid-flood |
Sunny |
Moderate |
M |
10 |
8:04:00 AM |
8.9 |
7.2 |
32.3 |
21.7 |
3.3 |
3.0 |
<0.10 |
<0.01 |
CF |
14/12/2023 |
Mid-flood |
Sunny |
Moderate |
B |
20 |
8:05:00 AM |
8.8 |
7.2 |
32.3 |
21.8 |
3.2 |
3.0 |
<0.10 |
<0.01 |
CF |
14/12/2023 |
Mid-flood |
Sunny |
Moderate |
B |
20 |
8:05:00 AM |
8.8 |
7.2 |
32.3 |
21.7 |
3.3 |
3.0 |
<0.10 |
<0.01 |
WSR01 |
14/12/2023 |
Mid-flood |
Sunny |
Moderate |
S |
1 |
8:29:00 AM |
8.9 |
7.1 |
33.3 |
21.7 |
2.0 |
3.0 |
<0.10 |
<0.01 |
WSR01 |
14/12/2023 |
Mid-flood |
Sunny |
Moderate |
S |
1 |
8:29:00 AM |
8.8 |
7.1 |
33.2 |
21.7 |
2.0 |
2.5 |
<0.10 |
<0.01 |
WSR01 |
14/12/2023 |
Mid-flood |
Sunny |
Moderate |
M |
4 |
8:30:00 AM |
8.8 |
7.1 |
33.2 |
21.6 |
2.1 |
4.0 |
<0.10 |
<0.01 |
WSR01 |
14/12/2023 |
Mid-flood |
Sunny |
Moderate |
M |
4 |
8:30:00 AM |
9.0 |
7.1 |
33.2 |
21.7 |
2.0 |
4.0 |
<0.10 |
<0.01 |
WSR01 |
14/12/2023 |
Mid-flood |
Sunny |
Moderate |
B |
7 |
8:31:00 AM |
8.9 |
7.1 |
33.3 |
21.7 |
1.9 |
4.0 |
<0.10 |
<0.01 |
WSR01 |
14/12/2023 |
Mid-flood |
Sunny |
Moderate |
B |
7 |
8:31:00 AM |
8.9 |
7.1 |
33.2 |
21.7 |
2.0 |
3.0 |
<0.10 |
<0.01 |
WSR02 |
14/12/2023 |
Mid-flood |
Sunny |
Moderate |
S |
1 |
8:50:00 AM |
8.9 |
7.2 |
33.0 |
21.8 |
1.4 |
5.0 |
<0.10 |
<0.01 |
WSR02 |
14/12/2023 |
Mid-flood |
Sunny |
Moderate |
S |
1 |
8:50:00 AM |
9.1 |
7.2 |
33.0 |
21.8 |
1.4 |
3.0 |
<0.10 |
<0.01 |
WSR02 |
14/12/2023 |
Mid-flood |
Sunny |
Moderate |
M |
5 |
8:51:00 AM |
8.9 |
7.2 |
32.9 |
21.8 |
1.5 |
4.0 |
<0.10 |
<0.01 |
WSR02 |
14/12/2023 |
Mid-flood |
Sunny |
Moderate |
M |
5 |
8:51:00 AM |
9.0 |
7.2 |
32.9 |
21.8 |
1.5 |
5.0 |
<0.10 |
<0.01 |
WSR02 |
14/12/2023 |
Mid-flood |
Sunny |
Moderate |
B |
8 |
8:52:00 AM |
8.9 |
7.2 |
33.1 |
21.7 |
1.5 |
4.0 |
<0.10 |
<0.01 |
WSR02 |
14/12/2023 |
Mid-flood |
Sunny |
Moderate |
B |
8 |
8:52:00 AM |
8.9 |
7.2 |
33.0 |
21.8 |
1.5 |
3.0 |
<0.10 |
<0.01 |
WSR03 |
14/12/2023 |
Mid-flood |
Sunny |
Moderate |
S |
1 |
9:06:00 AM |
9.6 |
7.1 |
33.1 |
21.5 |
1.3 |
6.0 |
<0.10 |
<0.01 |
WSR03 |
14/12/2023 |
Mid-flood |
Sunny |
Moderate |
S |
1 |
9:06:00 AM |
9.4 |
7.1 |
33.0 |
21.5 |
1.4 |
4.0 |
<0.10 |
<0.01 |
WSR03 |
14/12/2023 |
Mid-flood |
Sunny |
Moderate |
M |
4 |
9:07:00 AM |
9.4 |
7.1 |
33.0 |
21.5 |
1.3 |
3.0 |
<0.10 |
<0.01 |
WSR03 |
14/12/2023 |
Mid-flood |
Sunny |
Moderate |
M |
4 |
9:07:00 AM |
9.5 |
7.1 |
33.0 |
21.6 |
1.2 |
4.0 |
<0.10 |
<0.01 |
WSR03 |
14/12/2023 |
Mid-flood |
Sunny |
Moderate |
B |
7 |
9:08:00 AM |
9.4 |
7.2 |
33.1 |
21.5 |
1.4 |
3.0 |
<0.10 |
<0.01 |
WSR03 |
14/12/2023 |
Mid-flood |
Sunny |
Moderate |
B |
7 |
9:08:00 AM |
9.4 |
7.2 |
33.1 |
21.5 |
1.3 |
4.0 |
<0.10 |
<0.01 |
Location Date Tidal Weather Sea Condition Water Level Depth (m) Time DO (mg/L) pH Sal (ppt) Temp (°C) Turbidty (NTU) SS (mg/L) Iron (mg/L) Total Chlorine
WSR04 |
14/12/2023 |
Mid-flood |
Sunny |
Moderate |
S |
1 |
9:22:00 AM |
9.3 |
7.3 |
33.3 |
21.8 |
1.5 |
4.0 |
<0.10 |
<0.01 |
WSR04 |
14/12/2023 |
Mid-flood |
Sunny |
Moderate |
S |
1 |
9:22:00 AM |
9.1 |
7.3 |
33.2 |
21.8 |
1.6 |
5.0 |
<0.10 |
<0.01 |
WSR04 |
14/12/2023 |
Mid-flood |
Sunny |
Moderate |
M |
4 |
9:23:00 AM |
9.2 |
7.4 |
33.2 |
21.8 |
1.6 |
5.0 |
<0.10 |
<0.01 |
WSR04 |
14/12/2023 |
Mid-flood |
Sunny |
Moderate |
M |
4 |
9:23:00 AM |
9.2 |
7.3 |
33.3 |
21.7 |
1.6 |
3.0 |
<0.10 |
<0.01 |
WSR04 |
14/12/2023 |
Mid-flood |
Sunny |
Moderate |
B |
6 |
9:24:00 AM |
9.2 |
7.3 |
33.3 |
21.8 |
1.6 |
4.0 |
<0.10 |
<0.01 |
WSR04 |
14/12/2023 |
Mid-flood |
Sunny |
Moderate |
B |
6 |
9:24:00 AM |
9.1 |
7.3 |
33.2 |
21.8 |
1.6 |
3.0 |
<0.10 |
<0.01 |
WSR16 |
14/12/2023 |
Mid-flood |
Sunny |
Moderate |
S |
1 |
10:58:00 AM |
9.1 |
7.1 |
33.7 |
21.7 |
1.2 |
4.0 |
<0.10 |
<0.01 |
WSR16 |
14/12/2023 |
Mid-flood |
Sunny |
Moderate |
S |
1 |
10:58:00 AM |
9.2 |
7.0 |
33.7 |
21.7 |
1.2 |
5.0 |
<0.10 |
<0.01 |
WSR16 |
14/12/2023 |
Mid-flood |
Sunny |
Moderate |
M |
8 |
10:59:00 AM |
9.2 |
7.1 |
33.7 |
21.7 |
1.2 |
4.0 |
<0.10 |
<0.01 |
WSR16 |
14/12/2023 |
Mid-flood |
Sunny |
Moderate |
M |
8 |
10:59:00 AM |
9.2 |
7.0 |
33.7 |
21.7 |
1.1 |
3.0 |
<0.10 |
<0.01 |
WSR16 |
14/12/2023 |
Mid-flood |
Sunny |
Moderate |
B |
14 |
11:00:00 AM |
9.3 |
7.1 |
33.7 |
21.7 |
1.1 |
4.0 |
<0.10 |
<0.01 |
WSR16 |
14/12/2023 |
Mid-flood |
Sunny |
Moderate |
B |
14 |
11:00:00 AM |
9.1 |
7.1 |
33.7 |
21.6 |
1.3 |
4.0 |
<0.10 |
<0.01 |
WSR33 |
14/12/2023 |
Mid-flood |
Sunny |
Moderate |
S |
1 |
9:39:00 AM |
9.2 |
7.3 |
32.4 |
21.5 |
1.9 |
4.0 |
<0.10 |
<0.01 |
WSR33 |
14/12/2023 |
Mid-flood |
Sunny |
Moderate |
S |
1 |
9:39:00 AM |
9.2 |
7.3 |
32.4 |
21.5 |
2.0 |
5.0 |
<0.10 |
<0.01 |
WSR33 |
14/12/2023 |
Mid-flood |
Sunny |
Moderate |
M |
4 |
9:40:00 AM |
9.1 |
7.3 |
32.4 |
21.5 |
1.9 |
3.0 |
<0.10 |
<0.01 |
WSR33 |
14/12/2023 |
Mid-flood |
Sunny |
Moderate |
M |
4 |
9:40:00 AM |
9.0 |
7.3 |
32.4 |
21.5 |
2.0 |
3.0 |
<0.10 |
<0.01 |
WSR33 |
14/12/2023 |
Mid-flood |
Sunny |
Moderate |
B |
7 |
9:41:00 AM |
9.2 |
7.3 |
32.3 |
21.5 |
2.0 |
3.0 |
<0.10 |
<0.01 |
WSR33 |
14/12/2023 |
Mid-flood |
Sunny |
Moderate |
B |
7 |
9:41:00 AM |
9.1 |
7.3 |
32.4 |
21.5 |
1.9 |
3.0 |
<0.10 |
<0.01 |
WSR36 |
14/12/2023 |
Mid-flood |
Sunny |
Moderate |
S |
1 |
9:56:00 AM |
8.7 |
7.2 |
33.6 |
22.0 |
2.2 |
5.0 |
<0.10 |
<0.01 |
WSR36 |
14/12/2023 |
Mid-flood |
Sunny |
Moderate |
S |
1 |
9:56:00 AM |
8.7 |
7.3 |
33.7 |
22.0 |
2.3 |
4.0 |
<0.10 |
<0.01 |
WSR36 |
14/12/2023 |
Mid-flood |
Sunny |
Moderate |
M |
3 |
9:57:00 AM |
8.7 |
7.3 |
33.6 |
22.0 |
2.4 |
5.0 |
<0.10 |
<0.01 |
WSR36 |
14/12/2023 |
Mid-flood |
Sunny |
Moderate |
M |
3 |
9:57:00 AM |
8.5 |
7.3 |
33.8 |
21.9 |
2.5 |
4.0 |
<0.10 |
<0.01 |
WSR36 |
14/12/2023 |
Mid-flood |
Sunny |
Moderate |
B |
6 |
9:57:00 AM |
8.7 |
7.3 |
33.7 |
21.9 |
2.5 |
4.0 |
<0.10 |
<0.01 |
WSR36 |
14/12/2023 |
Mid-flood |
Sunny |
Moderate |
B |
6 |
9:57:00 AM |
8.5 |
7.2 |
33.7 |
22.0 |
2.5 |
5.0 |
<0.10 |
<0.01 |
WSR37 |
14/12/2023 |
Mid-flood |
Sunny |
Moderate |
S |
1 |
10:13:00 AM |
9.4 |
7.2 |
32.9 |
21.7 |
2.3 |
4.0 |
<0.10 |
<0.01 |
WSR37 |
14/12/2023 |
Mid-flood |
Sunny |
Moderate |
S |
1 |
10:13:00 AM |
9.4 |
7.3 |
32.8 |
21.8 |
2.4 |
5.0 |
<0.10 |
<0.01 |
WSR37 |
14/12/2023 |
Mid-flood |
Sunny |
Moderate |
M |
4 |
10:14:00 AM |
9.5 |
7.3 |
32.9 |
21.8 |
2.4 |
3.0 |
<0.10 |
<0.01 |
WSR37 |
14/12/2023 |
Mid-flood |
Sunny |
Moderate |
M |
4 |
10:14:00 AM |
9.4 |
7.3 |
32.8 |
21.8 |
2.5 |
5.0 |
<0.10 |
<0.01 |
WSR37 |
14/12/2023 |
Mid-flood |
Sunny |
Moderate |
B |
8 |
10:15:00 AM |
9.4 |
7.2 |
32.9 |
21.8 |
2.5 |
3.0 |
<0.10 |
<0.01 |
WSR37 |
14/12/2023 |
Mid-flood |
Sunny |
Moderate |
B |
8 |
10:15:00 AM |
9.4 |
7.2 |
32.8 |
21.7 |
2.4 |
3.0 |
<0.10 |
<0.01 |
NF1 |
14/12/2023 |
Mid-flood |
Sunny |
Moderate |
S |
1 |
10:51:00 AM |
8.6 |
7.2 |
33.1 |
21.8 |
1.6 |
4.0 |
<0.10 |
<0.01 |
NF1 |
14/12/2023 |
Mid-flood |
Sunny |
Moderate |
S |
1 |
10:51:00 AM |
8.7 |
7.3 |
33.2 |
21.6 |
1.6 |
5.0 |
<0.10 |
<0.01 |
NF1 |
14/12/2023 |
Mid-flood |
Sunny |
Moderate |
M |
7 |
10:52:00 AM |
8.8 |
7.2 |
33.2 |
21.7 |
1.7 |
4.0 |
<0.10 |
<0.01 |
NF1 |
14/12/2023 |
Mid-flood |
Sunny |
Moderate |
M |
7 |
10:52:00 AM |
8.6 |
7.2 |
33.1 |
21.7 |
1.7 |
3.0 |
<0.10 |
<0.01 |
NF1 |
14/12/2023 |
Mid-flood |
Sunny |
Moderate |
B |
12 |
10:53:00 AM |
8.7 |
7.3 |
33.2 |
21.7 |
1.8 |
4.0 |
<0.10 |
<0.01 |
NF1 |
14/12/2023 |
Mid-flood |
Sunny |
Moderate |
B |
12 |
10:53:00 AM |
8.6 |
7.2 |
33.3 |
21.7 |
1.7 |
3.0 |
<0.10 |
<0.01 |
Location Date Tidal Weather Sea Condition Water Level Depth (m) Time DO (mg/L) pH Sal (ppt) Temp (°C) Turbidty (NTU) SS (mg/L) Iron (mg/L) Total Chlorine
NF2 |
14/12/2023 |
Mid-flood |
Sunny |
Moderate |
S |
1 |
10:44:00 AM |
8.9 |
7.1 |
32.8 |
21.8 |
1.9 |
3.0 |
<0.10 |
<0.01 |
NF2 |
14/12/2023 |
Mid-flood |
Sunny |
Moderate |
S |
1 |
10:44:00 AM |
9.0 |
7.2 |
32.7 |
21.8 |
1.8 |
4.0 |
<0.10 |
<0.01 |
NF2 |
14/12/2023 |
Mid-flood |
Sunny |
Moderate |
M |
5 |
10:45:00 AM |
8.9 |
7.2 |
32.8 |
21.8 |
2.1 |
5.0 |
<0.10 |
<0.01 |
NF2 |
14/12/2023 |
Mid-flood |
Sunny |
Moderate |
M |
5 |
10:45:00 AM |
9.1 |
7.2 |
32.7 |
21.9 |
2.2 |
5.0 |
<0.10 |
<0.01 |
NF2 |
14/12/2023 |
Mid-flood |
Sunny |
Moderate |
B |
10 |
10:46:00 AM |
8.9 |
7.2 |
32.7 |
21.9 |
2.2 |
5.0 |
<0.10 |
<0.01 |
NF2 |
14/12/2023 |
Mid-flood |
Sunny |
Moderate |
B |
10 |
10:46:00 AM |
8.9 |
7.1 |
32.7 |
21.9 |
2.1 |
3.0 |
<0.10 |
<0.01 |
NF3 |
14/12/2023 |
Mid-flood |
Sunny |
Moderate |
S |
1 |
10:38:00 AM |
8.9 |
7.3 |
32.6 |
21.7 |
1.4 |
3.0 |
<0.10 |
<0.01 |
NF3 |
14/12/2023 |
Mid-flood |
Sunny |
Moderate |
S |
1 |
10:38:00 AM |
8.8 |
7.3 |
32.6 |
21.7 |
1.3 |
4.0 |
<0.10 |
<0.01 |
NF3 |
14/12/2023 |
Mid-flood |
Sunny |
Moderate |
M |
6 |
10:39:00 AM |
8.9 |
7.4 |
32.5 |
21.7 |
1.4 |
4.0 |
<0.10 |
<0.01 |
NF3 |
14/12/2023 |
Mid-flood |
Sunny |
Moderate |
M |
6 |
10:39:00 AM |
8.9 |
7.3 |
32.5 |
21.7 |
1.4 |
4.0 |
<0.10 |
<0.01 |
NF3 |
14/12/2023 |
Mid-flood |
Sunny |
Moderate |
B |
11 |
10:40:00 AM |
8.9 |
7.3 |
32.6 |
21.7 |
1.4 |
5.0 |
<0.10 |
<0.01 |
NF3 |
14/12/2023 |
Mid-flood |
Sunny |
Moderate |
B |
11 |
10:40:00 AM |
8.7 |
7.3 |
32.6 |
21.7 |
1.5 |
4.0 |
<0.10 |
<0.01 |
CE |
16/12/2023 |
Mid-flood |
Sunny |
Moderate |
S |
1 |
11:30:00 AM |
9.4 |
7.2 |
33.0 |
21.8 |
2.8 |
3.0 |
<0.10 |
<0.01 |
CE |
16/12/2023 |
Mid-flood |
Sunny |
Moderate |
S |
1 |
11:30:00 AM |
9.3 |
7.2 |
33.0 |
21.8 |
2.7 |
4.0 |
<0.10 |
<0.01 |
CE |
16/12/2023 |
Mid-flood |
Sunny |
Moderate |
M |
10 |
11:31:00 AM |
9.4 |
7.2 |
32.9 |
21.8 |
2.7 |
4.0 |
<0.10 |
<0.01 |
CE |
16/12/2023 |
Mid-flood |
Sunny |
Moderate |
M |
10 |
11:31:00 AM |
9.2 |
7.2 |
33.0 |
21.7 |
2.8 |
4.0 |
<0.10 |
<0.01 |
CE |
16/12/2023 |
Mid-flood |
Sunny |
Moderate |
B |
19 |
11:32:00 AM |
9.3 |
7.2 |
33.0 |
21.8 |
2.7 |
4.0 |
<0.10 |
<0.01 |
CE |
16/12/2023 |
Mid-flood |
Sunny |
Moderate |
B |
19 |
11:32:00 AM |
9.5 |
7.2 |
33.0 |
21.7 |
2.7 |
3.0 |
<0.10 |
<0.01 |
CF |
16/12/2023 |
Mid-flood |
Sunny |
Moderate |
S |
1 |
8:05:00 AM |
9.8 |
7.1 |
34.2 |
21.7 |
3.3 |
3.0 |
<0.10 |
<0.01 |
CF |
16/12/2023 |
Mid-flood |
Sunny |
Moderate |
S |
1 |
8:05:00 AM |
9.8 |
7.1 |
34.1 |
21.7 |
3.1 |
3.0 |
<0.10 |
<0.01 |
CF |
16/12/2023 |
Mid-flood |
Sunny |
Moderate |
M |
11 |
8:06:00 AM |
9.5 |
7.2 |
34.2 |
21.8 |
3.2 |
3.0 |
<0.10 |
<0.01 |
CF |
16/12/2023 |
Mid-flood |
Sunny |
Moderate |
M |
11 |
8:06:00 AM |
9.4 |
7.1 |
34.0 |
21.7 |
3.2 |
3.0 |
<0.10 |
<0.01 |
CF |
16/12/2023 |
Mid-flood |
Sunny |
Moderate |
B |
20 |
8:07:00 AM |
9.8 |
7.1 |
34.1 |
21.8 |
3.2 |
3.0 |
<0.10 |
<0.01 |
CF |
16/12/2023 |
Mid-flood |
Sunny |
Moderate |
B |
20 |
8:07:00 AM |
9.7 |
7.1 |
34.2 |
21.7 |
3.0 |
2.5 |
<0.10 |
<0.01 |
WSR01 |
16/12/2023 |
Mid-flood |
Sunny |
Moderate |
S |
1 |
8:31:00 AM |
9.1 |
7.3 |
33.8 |
21.7 |
2.3 |
3.0 |
<0.10 |
<0.01 |
WSR01 |
16/12/2023 |
Mid-flood |
Sunny |
Moderate |
S |
1 |
8:31:00 AM |
9.0 |
7.2 |
33.7 |
21.7 |
2.2 |
4.0 |
<0.10 |
<0.01 |
WSR01 |
16/12/2023 |
Mid-flood |
Sunny |
Moderate |
M |
4 |
8:32:00 AM |
9.3 |
7.3 |
34.0 |
21.6 |
2.4 |
4.0 |
<0.10 |
<0.01 |
WSR01 |
16/12/2023 |
Mid-flood |
Sunny |
Moderate |
M |
4 |
8:32:00 AM |
9.3 |
7.2 |
33.7 |
21.6 |
2.4 |
4.0 |
<0.10 |
<0.01 |
WSR01 |
16/12/2023 |
Mid-flood |
Sunny |
Moderate |
B |
8 |
8:33:00 AM |
9.1 |
7.3 |
33.8 |
21.6 |
2.4 |
3.0 |
<0.10 |
<0.01 |
WSR01 |
16/12/2023 |
Mid-flood |
Sunny |
Moderate |
B |
8 |
8:33:00 AM |
9.2 |
7.2 |
33.8 |
21.6 |
2.5 |
3.0 |
<0.10 |
<0.01 |
WSR02 |
16/12/2023 |
Mid-flood |
Sunny |
Moderate |
S |
1 |
8:53:00 AM |
8.5 |
7.2 |
33.3 |
21.6 |
2.4 |
4.0 |
<0.10 |
<0.01 |
WSR02 |
16/12/2023 |
Mid-flood |
Sunny |
Moderate |
S |
1 |
8:53:00 AM |
8.7 |
7.2 |
33.5 |
21.6 |
2.3 |
6.0 |
<0.10 |
<0.01 |
WSR02 |
16/12/2023 |
Mid-flood |
Sunny |
Moderate |
M |
5 |
8:54:00 AM |
8.5 |
7.1 |
33.4 |
21.5 |
2.4 |
2.5 |
<0.10 |
<0.01 |
WSR02 |
16/12/2023 |
Mid-flood |
Sunny |
Moderate |
M |
5 |
8:54:00 AM |
8.8 |
7.2 |
33.3 |
21.6 |
2.3 |
2.5 |
<0.10 |
<0.01 |
WSR02 |
16/12/2023 |
Mid-flood |
Sunny |
Moderate |
B |
9 |
8:55:00 AM |
8.5 |
7.1 |
33.4 |
21.5 |
2.4 |
4.0 |
<0.10 |
<0.01 |
WSR02 |
16/12/2023 |
Mid-flood |
Sunny |
Moderate |
B |
9 |
8:55:00 AM |
8.6 |
7.2 |
33.5 |
21.6 |
2.5 |
2.5 |
<0.10 |
<0.01 |
Location Date Tidal Weather Sea Condition Water Level Depth (m) Time DO (mg/L) pH Sal (ppt) Temp (°C) Turbidty (NTU) SS (mg/L) Iron (mg/L) Total Chlorine
WSR03 |
16/12/2023 |
Mid-flood |
Sunny |
Moderate |
S |
1 |
9:09:00 AM |
9.3 |
7.1 |
33.1 |
21.8 |
1.4 |
3.0 |
<0.10 |
<0.01 |
WSR03 |
16/12/2023 |
Mid-flood |
Sunny |
Moderate |
S |
1 |
9:09:00 AM |
9.3 |
7.2 |
33.1 |
21.8 |
1.4 |
3.0 |
<0.10 |
<0.01 |
WSR03 |
16/12/2023 |
Mid-flood |
Sunny |
Moderate |
M |
4 |
9:10:00 AM |
9.4 |
7.2 |
33.0 |
21.8 |
1.5 |
3.0 |
<0.10 |
<0.01 |
WSR03 |
16/12/2023 |
Mid-flood |
Sunny |
Moderate |
M |
4 |
9:10:00 AM |
9.6 |
7.2 |
33.0 |
21.7 |
1.5 |
3.0 |
<0.10 |
<0.01 |
WSR03 |
16/12/2023 |
Mid-flood |
Sunny |
Moderate |
B |
7 |
9:11:00 AM |
9.5 |
7.1 |
32.9 |
21.7 |
1.4 |
3.0 |
<0.10 |
<0.01 |
WSR03 |
16/12/2023 |
Mid-flood |
Sunny |
Moderate |
B |
7 |
9:11:00 AM |
9.4 |
7.2 |
33.0 |
21.7 |
1.3 |
4.0 |
<0.10 |
<0.01 |
WSR04 |
16/12/2023 |
Mid-flood |
Sunny |
Moderate |
S |
1 |
9:27:00 AM |
9.5 |
7.1 |
33.1 |
21.6 |
1.7 |
3.0 |
<0.10 |
<0.01 |
WSR04 |
16/12/2023 |
Mid-flood |
Sunny |
Moderate |
S |
1 |
9:27:00 AM |
9.7 |
7.1 |
33.1 |
21.7 |
1.7 |
3.0 |
<0.10 |
<0.01 |
WSR04 |
16/12/2023 |
Mid-flood |
Sunny |
Moderate |
M |
4 |
9:28:00 AM |
9.4 |
7.2 |
32.8 |
21.6 |
1.8 |
2.5 |
<0.10 |
<0.01 |
WSR04 |
16/12/2023 |
Mid-flood |
Sunny |
Moderate |
M |
4 |
9:28:00 AM |
9.4 |
7.1 |
33.0 |
21.6 |
1.7 |
3.0 |
<0.10 |
<0.01 |
WSR04 |
16/12/2023 |
Mid-flood |
Sunny |
Moderate |
B |
7 |
9:29:00 AM |
9.6 |
7.1 |
32.8 |
21.7 |
1.8 |
4.0 |
<0.10 |
<0.01 |
WSR04 |
16/12/2023 |
Mid-flood |
Sunny |
Moderate |
B |
7 |
9:29:00 AM |
9.5 |
7.2 |
32.9 |
21.6 |
1.8 |
5.0 |
<0.10 |
<0.01 |
WSR16 |
16/12/2023 |
Mid-flood |
Sunny |
Moderate |
S |
1 |
11:07:00 AM |
9.5 |
7.2 |
34.0 |
21.8 |
2.2 |
2.5 |
<0.10 |
<0.01 |
WSR16 |
16/12/2023 |
Mid-flood |
Sunny |
Moderate |
S |
1 |
11:07:00 AM |
9.4 |
7.2 |
34.2 |
21.8 |
2.2 |
2.5 |
<0.10 |
<0.01 |
WSR16 |
16/12/2023 |
Mid-flood |
Sunny |
Moderate |
M |
8 |
11:08:00 AM |
9.5 |
7.2 |
34.0 |
21.9 |
2.4 |
2.5 |
<0.10 |
<0.01 |
WSR16 |
16/12/2023 |
Mid-flood |
Sunny |
Moderate |
M |
8 |
11:08:00 AM |
9.2 |
7.2 |
34.0 |
21.9 |
2.3 |
4.0 |
<0.10 |
<0.01 |
WSR16 |
16/12/2023 |
Mid-flood |
Sunny |
Moderate |
B |
15 |
11:09:00 AM |
9.5 |
7.2 |
34.0 |
21.8 |
2.3 |
3.0 |
<0.10 |
<0.01 |
WSR16 |
16/12/2023 |
Mid-flood |
Sunny |
Moderate |
B |
15 |
11:09:00 AM |
9.3 |
7.3 |
34.0 |
21.8 |
2.4 |
2.5 |
<0.10 |
<0.01 |
WSR33 |
16/12/2023 |
Mid-flood |
Sunny |
Moderate |
S |
1 |
9:44:00 AM |
8.9 |
7.2 |
33.3 |
21.5 |
1.9 |
3.0 |
<0.10 |
<0.01 |
WSR33 |
16/12/2023 |
Mid-flood |
Sunny |
Moderate |
S |
1 |
9:44:00 AM |
8.8 |
7.1 |
33.3 |
21.6 |
2.1 |
2.5 |
<0.10 |
<0.01 |
WSR33 |
16/12/2023 |
Mid-flood |
Sunny |
Moderate |
M |
4 |
9:45:00 AM |
8.9 |
7.2 |
33.3 |
21.6 |
2.0 |
3.0 |
<0.10 |
<0.01 |
WSR33 |
16/12/2023 |
Mid-flood |
Sunny |
Moderate |
M |
4 |
9:45:00 AM |
8.9 |
7.2 |
33.1 |
21.6 |
2.0 |
3.0 |
<0.10 |
<0.01 |
WSR33 |
16/12/2023 |
Mid-flood |
Sunny |
Moderate |
B |
7 |
9:46:00 AM |
9.1 |
7.1 |
33.2 |
21.6 |
2.1 |
3.0 |
<0.10 |
<0.01 |
WSR33 |
16/12/2023 |
Mid-flood |
Sunny |
Moderate |
B |
7 |
9:46:00 AM |
8.9 |
7.2 |
33.2 |
21.6 |
2.0 |
2.5 |
<0.10 |
<0.01 |
WSR36 |
16/12/2023 |
Mid-flood |
Sunny |
Moderate |
S |
1 |
10:01:00 AM |
9.7 |
7.2 |
33.3 |
21.6 |
2.4 |
3.0 |
<0.10 |
<0.01 |
WSR36 |
16/12/2023 |
Mid-flood |
Sunny |
Moderate |
S |
1 |
10:01:00 AM |
10.1 |
7.3 |
33.4 |
21.7 |
2.4 |
4.0 |
<0.10 |
<0.01 |
WSR36 |
16/12/2023 |
Mid-flood |
Sunny |
Moderate |
M |
3 |
10:02:00 AM |
9.8 |
7.2 |
33.4 |
21.7 |
2.5 |
3.0 |
<0.10 |
<0.01 |
WSR36 |
16/12/2023 |
Mid-flood |
Sunny |
Moderate |
M |
3 |
10:02:00 AM |
9.8 |
7.3 |
33.2 |
21.7 |
2.4 |
3.0 |
<0.10 |
<0.01 |
WSR36 |
16/12/2023 |
Mid-flood |
Sunny |
Moderate |
B |
6 |
10:02:00 AM |
9.9 |
7.2 |
33.1 |
21.7 |
2.4 |
4.0 |
<0.10 |
<0.01 |
WSR36 |
16/12/2023 |
Mid-flood |
Sunny |
Moderate |
B |
6 |
10:02:00 AM |
9.8 |
7.3 |
33.2 |
21.7 |
2.4 |
3.0 |
<0.10 |
<0.01 |
WSR37 |
16/12/2023 |
Mid-flood |
Sunny |
Moderate |
S |
1 |
10:18:00 AM |
8.8 |
7.2 |
33.4 |
21.7 |
2.2 |
2.5 |
<0.10 |
<0.01 |
WSR37 |
16/12/2023 |
Mid-flood |
Sunny |
Moderate |
S |
1 |
10:18:00 AM |
8.9 |
7.2 |
33.2 |
21.7 |
2.3 |
2.5 |
<0.10 |
<0.01 |
WSR37 |
16/12/2023 |
Mid-flood |
Sunny |
Moderate |
M |
4 |
10:19:00 AM |
9.1 |
7.1 |
33.3 |
21.7 |
2.2 |
3.0 |
<0.10 |
<0.01 |
WSR37 |
16/12/2023 |
Mid-flood |
Sunny |
Moderate |
M |
4 |
10:19:00 AM |
8.9 |
7.2 |
33.3 |
21.6 |
2.3 |
3.0 |
<0.10 |
<0.01 |
WSR37 |
16/12/2023 |
Mid-flood |
Sunny |
Moderate |
B |
8 |
10:20:00 AM |
8.7 |
7.2 |
33.2 |
21.7 |
2.2 |
3.0 |
<0.10 |
<0.01 |
WSR37 |
16/12/2023 |
Mid-flood |
Sunny |
Moderate |
B |
8 |
10:20:00 AM |
9.0 |
7.2 |
33.3 |
21.7 |
2.3 |
3.0 |
<0.10 |
<0.01 |
Location Date Tidal Weather Sea Condition Water Level Depth (m) Time DO (mg/L) pH Sal (ppt) Temp (°C) Turbidty (NTU) SS (mg/L) Iron (mg/L) Total Chlorine
NF1 |
16/12/2023 |
Mid-flood |
Sunny |
Moderate |
S |
1 |
11:00:00 AM |
9.7 |
7.1 |
33.1 |
21.5 |
2.4 |
2.5 |
<0.10 |
<0.01 |
NF1 |
16/12/2023 |
Mid-flood |
Sunny |
Moderate |
S |
1 |
11:00:00 AM |
9.8 |
7.2 |
33.1 |
21.5 |
2.5 |
4.0 |
<0.10 |
<0.01 |
NF1 |
16/12/2023 |
Mid-flood |
Sunny |
Moderate |
M |
7 |
11:01:00 AM |
10.0 |
7.1 |
33.1 |
21.4 |
2.3 |
3.0 |
<0.10 |
<0.01 |
NF1 |
16/12/2023 |
Mid-flood |
Sunny |
Moderate |
M |
7 |
11:01:00 AM |
10.0 |
7.1 |
33.1 |
21.5 |
2.4 |
3.0 |
<0.10 |
<0.01 |
NF1 |
16/12/2023 |
Mid-flood |
Sunny |
Moderate |
B |
13 |
11:02:00 AM |
10.1 |
7.1 |
33.0 |
21.4 |
2.5 |
4.0 |
<0.10 |
<0.01 |
NF1 |
16/12/2023 |
Mid-flood |
Sunny |
Moderate |
B |
13 |
11:02:00 AM |
10.0 |
7.2 |
33.0 |
21.4 |
2.4 |
3.0 |
<0.10 |
<0.01 |
NF2 |
16/12/2023 |
Mid-flood |
Sunny |
Moderate |
S |
1 |
10:51:00 AM |
9.6 |
7.3 |
33.0 |
21.7 |
2.4 |
4.0 |
<0.10 |
<0.01 |
NF2 |
16/12/2023 |
Mid-flood |
Sunny |
Moderate |
S |
1 |
10:51:00 AM |
9.4 |
7.3 |
32.9 |
21.7 |
2.4 |
3.0 |
<0.10 |
<0.01 |
NF2 |
16/12/2023 |
Mid-flood |
Sunny |
Moderate |
M |
5 |
10:52:00 AM |
9.5 |
7.2 |
32.9 |
21.7 |
2.3 |
3.0 |
<0.10 |
<0.01 |
NF2 |
16/12/2023 |
Mid-flood |
Sunny |
Moderate |
M |
5 |
10:52:00 AM |
9.3 |
7.3 |
33.0 |
21.8 |
2.5 |
2.5 |
<0.10 |
<0.01 |
NF2 |
16/12/2023 |
Mid-flood |
Sunny |
Moderate |
B |
10 |
10:53:00 AM |
9.6 |
7.3 |
33.0 |
21.7 |
2.4 |
3.0 |
<0.10 |
<0.01 |
NF2 |
16/12/2023 |
Mid-flood |
Sunny |
Moderate |
B |
10 |
10:53:00 AM |
9.6 |
7.3 |
32.9 |
21.7 |
2.4 |
2.5 |
<0.10 |
<0.01 |
NF3 |
16/12/2023 |
Mid-flood |
Sunny |
Moderate |
S |
1 |
10:45:00 AM |
10.1 |
7.2 |
33.8 |
21.5 |
2.3 |
2.5 |
<0.10 |
<0.01 |
NF3 |
16/12/2023 |
Mid-flood |
Sunny |
Moderate |
S |
1 |
10:45:00 AM |
10.0 |
7.2 |
33.8 |
21.4 |
2.4 |
2.5 |
<0.10 |
<0.01 |
NF3 |
16/12/2023 |
Mid-flood |
Sunny |
Moderate |
M |
6 |
10:46:00 AM |
10.0 |
7.3 |
34.0 |
21.5 |
2.4 |
4.0 |
<0.10 |
<0.01 |
NF3 |
16/12/2023 |
Mid-flood |
Sunny |
Moderate |
M |
6 |
10:46:00 AM |
10.1 |
7.3 |
33.9 |
21.5 |
2.4 |
2.5 |
<0.10 |
<0.01 |
NF3 |
16/12/2023 |
Mid-flood |
Sunny |
Moderate |
B |
11 |
10:47:00 AM |
9.8 |
7.3 |
33.8 |
21.5 |
2.4 |
2.5 |
<0.10 |
<0.01 |
NF3 |
16/12/2023 |
Mid-flood |
Sunny |
Moderate |
B |
11 |
10:47:00 AM |
10.0 |
7.3 |
33.8 |
21.5 |
2.5 |
3.0 |
<0.10 |
<0.01 |
CE |
19/12/2023 |
Mid-flood |
Cloudy |
Moderate |
S |
1 |
1:46:00 PM |
8.6 |
7.2 |
32.9 |
22.0 |
3.2 |
3.0 |
<0.10 |
<0.01 |
CE |
19/12/2023 |
Mid-flood |
Cloudy |
Moderate |
S |
1 |
1:46:00 PM |
8.6 |
7.2 |
32.7 |
22.0 |
3.2 |
4.0 |
<0.10 |
<0.01 |
CE |
19/12/2023 |
Mid-flood |
Cloudy |
Moderate |
M |
11 |
1:47:00 PM |
8.6 |
7.3 |
32.8 |
22.1 |
3.1 |
4.0 |
<0.10 |
<0.01 |
CE |
19/12/2023 |
Mid-flood |
Cloudy |
Moderate |
M |
11 |
1:47:00 PM |
8.4 |
7.2 |
32.9 |
22.0 |
3.1 |
3.0 |
<0.10 |
<0.01 |
CE |
19/12/2023 |
Mid-flood |
Cloudy |
Moderate |
B |
22 |
1:48:00 PM |
8.6 |
7.2 |
32.7 |
22.0 |
3.1 |
4.0 |
<0.10 |
<0.01 |
CE |
19/12/2023 |
Mid-flood |
Cloudy |
Moderate |
B |
22 |
1:48:00 PM |
8.5 |
7.2 |
32.9 |
22.0 |
3.1 |
4.0 |
<0.10 |
<0.01 |
CF |
19/12/2023 |
Mid-flood |
Cloudy |
Moderate |
S |
1 |
10:29:00 AM |
8.0 |
7.3 |
32.4 |
22.0 |
3.7 |
3.0 |
<0.10 |
<0.01 |
CF |
19/12/2023 |
Mid-flood |
Cloudy |
Moderate |
S |
1 |
10:29:00 AM |
7.9 |
7.3 |
32.4 |
21.9 |
3.6 |
3.0 |
<0.10 |
<0.01 |
CF |
19/12/2023 |
Mid-flood |
Cloudy |
Moderate |
M |
10 |
10:30:00 AM |
7.8 |
7.3 |
32.3 |
22.0 |
3.9 |
3.0 |
<0.10 |
<0.01 |
CF |
19/12/2023 |
Mid-flood |
Cloudy |
Moderate |
M |
10 |
10:30:00 AM |
7.9 |
7.3 |
32.3 |
22.0 |
3.8 |
5.0 |
<0.10 |
<0.01 |
CF |
19/12/2023 |
Mid-flood |
Cloudy |
Moderate |
B |
19 |
10:31:00 AM |
7.8 |
7.3 |
32.5 |
22.0 |
4.0 |
5.0 |
<0.10 |
<0.01 |
CF |
19/12/2023 |
Mid-flood |
Cloudy |
Moderate |
B |
19 |
10:31:00 AM |
8.0 |
7.3 |
32.6 |
21.9 |
3.9 |
3.0 |
<0.10 |
<0.01 |
WSR01 |
19/12/2023 |
Mid-flood |
Cloudy |
Moderate |
S |
1 |
10:54:00 AM |
7.8 |
7.4 |
33.3 |
22.0 |
2.2 |
4.0 |
<0.10 |
<0.01 |
WSR01 |
19/12/2023 |
Mid-flood |
Cloudy |
Moderate |
S |
1 |
10:54:00 AM |
7.8 |
7.3 |
33.5 |
22.0 |
2.2 |
5.0 |
<0.10 |
<0.01 |
WSR01 |
19/12/2023 |
Mid-flood |
Cloudy |
Moderate |
M |
4 |
10:55:00 AM |
7.8 |
7.3 |
33.4 |
22.1 |
2.1 |
3.0 |
<0.10 |
<0.01 |
WSR01 |
19/12/2023 |
Mid-flood |
Cloudy |
Moderate |
M |
4 |
10:55:00 AM |
8.0 |
7.3 |
33.4 |
22.0 |
2.2 |
4.0 |
<0.10 |
<0.01 |
WSR01 |
19/12/2023 |
Mid-flood |
Cloudy |
Moderate |
B |
8 |
10:56:00 AM |
7.9 |
7.4 |
33.3 |
22.0 |
2.1 |
6.0 |
<0.10 |
<0.01 |
WSR01 |
19/12/2023 |
Mid-flood |
Cloudy |
Moderate |
B |
8 |
10:56:00 AM |
8.0 |
7.3 |
33.3 |
22.0 |
2.1 |
3.0 |
<0.10 |
<0.01 |
Location Date Tidal Weather Sea Condition Water Level Depth (m) Time DO (mg/L) pH Sal (ppt) Temp (°C) Turbidty (NTU) SS (mg/L) Iron (mg/L) Total Chlorine
WSR02 |
19/12/2023 |
Mid-flood |
Cloudy |
Moderate |
S |
1 |
11:15:00 AM |
7.8 |
7.4 |
33.0 |
22.1 |
2.1 |
6.0 |
<0.10 |
<0.01 |
WSR02 |
19/12/2023 |
Mid-flood |
Cloudy |
Moderate |
S |
1 |
11:15:00 AM |
7.7 |
7.4 |
33.2 |
22.1 |
2.1 |
3.0 |
<0.10 |
<0.01 |
WSR02 |
19/12/2023 |
Mid-flood |
Cloudy |
Moderate |
M |
5 |
11:16:00 AM |
7.6 |
7.4 |
33.1 |
22.1 |
2.5 |
3.0 |
<0.10 |
<0.01 |
WSR02 |
19/12/2023 |
Mid-flood |
Cloudy |
Moderate |
M |
5 |
11:16:00 AM |
7.8 |
7.3 |
33.0 |
22.1 |
2.6 |
4.0 |
<0.10 |
<0.01 |
WSR02 |
19/12/2023 |
Mid-flood |
Cloudy |
Moderate |
B |
8 |
11:17:00 AM |
7.6 |
7.3 |
33.1 |
22.0 |
2.5 |
2.5 |
<0.10 |
<0.01 |
WSR02 |
19/12/2023 |
Mid-flood |
Cloudy |
Moderate |
B |
8 |
11:17:00 AM |
7.8 |
7.4 |
33.2 |
22.1 |
2.5 |
3.0 |
<0.10 |
<0.01 |
WSR03 |
19/12/2023 |
Mid-flood |
Cloudy |
Moderate |
S |
1 |
11:31:00 AM |
8.0 |
7.3 |
32.9 |
22.2 |
2.1 |
3.0 |
<0.10 |
<0.01 |
WSR03 |
19/12/2023 |
Mid-flood |
Cloudy |
Moderate |
S |
1 |
11:31:00 AM |
7.8 |
7.3 |
33.0 |
22.1 |
2.2 |
2.5 |
<0.10 |
<0.01 |
WSR03 |
19/12/2023 |
Mid-flood |
Cloudy |
Moderate |
M |
4 |
11:32:00 AM |
7.8 |
7.3 |
33.1 |
22.2 |
2.1 |
6.0 |
<0.10 |
<0.01 |
WSR03 |
19/12/2023 |
Mid-flood |
Cloudy |
Moderate |
M |
4 |
11:32:00 AM |
8.0 |
7.3 |
33.0 |
22.1 |
2.1 |
5.0 |
<0.10 |
<0.01 |
WSR03 |
19/12/2023 |
Mid-flood |
Cloudy |
Moderate |
B |
7 |
11:33:00 AM |
8.0 |
7.4 |
33.1 |
22.1 |
2.2 |
3.0 |
<0.10 |
<0.01 |
WSR03 |
19/12/2023 |
Mid-flood |
Cloudy |
Moderate |
B |
7 |
11:33:00 AM |
7.9 |
7.3 |
33.2 |
22.1 |
2.1 |
6.0 |
<0.10 |
<0.01 |
WSR04 |
19/12/2023 |
Mid-flood |
Cloudy |
Moderate |
S |
1 |
11:47:00 AM |
8.2 |
7.2 |
32.4 |
22.0 |
2.4 |
4.0 |
<0.10 |
<0.01 |
WSR04 |
19/12/2023 |
Mid-flood |
Cloudy |
Moderate |
S |
1 |
11:47:00 AM |
8.2 |
7.3 |
32.6 |
22.0 |
2.5 |
7.0 |
<0.10 |
<0.01 |
WSR04 |
19/12/2023 |
Mid-flood |
Cloudy |
Moderate |
M |
3 |
11:48:00 AM |
8.1 |
7.3 |
32.6 |
22.0 |
2.2 |
2.5 |
<0.10 |
<0.01 |
WSR04 |
19/12/2023 |
Mid-flood |
Cloudy |
Moderate |
M |
3 |
11:48:00 AM |
8.1 |
7.3 |
32.6 |
22.0 |
2.2 |
4.0 |
<0.10 |
<0.01 |
WSR04 |
19/12/2023 |
Mid-flood |
Cloudy |
Moderate |
B |
6 |
11:49:00 AM |
8.1 |
7.2 |
32.5 |
22.0 |
2.3 |
6.0 |
<0.10 |
<0.01 |
WSR04 |
19/12/2023 |
Mid-flood |
Cloudy |
Moderate |
B |
6 |
11:49:00 AM |
8.3 |
7.3 |
32.4 |
22.0 |
2.2 |
4.0 |
<0.10 |
<0.01 |
WSR16 |
19/12/2023 |
Mid-flood |
Cloudy |
Moderate |
S |
1 |
1:23:00 PM |
8.4 |
7.2 |
33.3 |
22.3 |
2.3 |
3.0 |
<0.10 |
<0.01 |
WSR16 |
19/12/2023 |
Mid-flood |
Cloudy |
Moderate |
S |
1 |
1:23:00 PM |
8.4 |
7.3 |
33.4 |
22.2 |
2.0 |
2.5 |
<0.10 |
<0.01 |
WSR16 |
19/12/2023 |
Mid-flood |
Cloudy |
Moderate |
M |
8 |
1:24:00 PM |
8.4 |
7.2 |
33.4 |
22.2 |
2.6 |
4.0 |
<0.10 |
<0.01 |
WSR16 |
19/12/2023 |
Mid-flood |
Cloudy |
Moderate |
M |
8 |
1:24:00 PM |
8.6 |
7.2 |
33.5 |
22.2 |
2.4 |
5.0 |
<0.10 |
<0.01 |
WSR16 |
19/12/2023 |
Mid-flood |
Cloudy |
Moderate |
B |
16 |
1:25:00 PM |
8.4 |
7.2 |
33.5 |
22.2 |
2.6 |
5.0 |
<0.10 |
<0.01 |
WSR16 |
19/12/2023 |
Mid-flood |
Cloudy |
Moderate |
B |
16 |
1:25:00 PM |
8.5 |
7.2 |
33.5 |
22.2 |
2.4 |
6.0 |
<0.10 |
<0.01 |
WSR33 |
19/12/2023 |
Mid-flood |
Cloudy |
Moderate |
S |
1 |
12:02:00 PM |
8.2 |
7.3 |
33.4 |
22.0 |
2.8 |
2.5 |
<0.10 |
<0.01 |
WSR33 |
19/12/2023 |
Mid-flood |
Cloudy |
Moderate |
S |
1 |
12:02:00 PM |
8.2 |
7.3 |
33.6 |
22.0 |
2.7 |
3.0 |
<0.10 |
<0.01 |
WSR33 |
19/12/2023 |
Mid-flood |
Cloudy |
Moderate |
M |
4 |
12:03:00 PM |
8.4 |
7.3 |
33.3 |
22.0 |
2.4 |
5.0 |
<0.10 |
<0.01 |
WSR33 |
19/12/2023 |
Mid-flood |
Cloudy |
Moderate |
M |
4 |
12:03:00 PM |
8.3 |
7.3 |
33.3 |
22.0 |
2.2 |
5.0 |
<0.10 |
<0.01 |
WSR33 |
19/12/2023 |
Mid-flood |
Cloudy |
Moderate |
B |
6 |
12:04:00 PM |
8.2 |
7.3 |
33.4 |
22.1 |
2.1 |
3.0 |
<0.10 |
<0.01 |
WSR33 |
19/12/2023 |
Mid-flood |
Cloudy |
Moderate |
B |
6 |
12:04:00 PM |
8.2 |
7.3 |
33.3 |
22.1 |
2.2 |
5.0 |
<0.10 |
<0.01 |
WSR36 |
19/12/2023 |
Mid-flood |
Cloudy |
Moderate |
S |
1 |
12:19:00 PM |
8.4 |
7.2 |
33.4 |
22.2 |
2.3 |
5.0 |
<0.10 |
<0.01 |
WSR36 |
19/12/2023 |
Mid-flood |
Cloudy |
Moderate |
S |
1 |
12:19:00 PM |
8.4 |
7.2 |
33.7 |
22.2 |
2.3 |
5.0 |
<0.10 |
<0.01 |
WSR36 |
19/12/2023 |
Mid-flood |
Cloudy |
Moderate |
M |
4 |
12:20:00 PM |
8.5 |
7.2 |
33.5 |
22.2 |
2.4 |
4.0 |
<0.10 |
<0.01 |
WSR36 |
19/12/2023 |
Mid-flood |
Cloudy |
Moderate |
M |
4 |
12:20:00 PM |
8.4 |
7.2 |
33.7 |
22.2 |
2.3 |
5.0 |
<0.10 |
<0.01 |
WSR36 |
19/12/2023 |
Mid-flood |
Cloudy |
Moderate |
B |
6 |
12:20:00 PM |
8.4 |
7.2 |
33.7 |
22.2 |
2.2 |
3.0 |
<0.10 |
<0.01 |
WSR36 |
19/12/2023 |
Mid-flood |
Cloudy |
Moderate |
B |
6 |
12:20:00 PM |
8.5 |
7.2 |
33.4 |
22.2 |
2.3 |
4.0 |
<0.10 |
<0.01 |
Location Date Tidal Weather Sea Condition Water Level Depth (m) Time DO (mg/L) pH Sal (ppt) Temp (°C) Turbidty (NTU) SS (mg/L) Iron (mg/L) Total Chlorine
WSR37 |
19/12/2023 |
Mid-flood |
Cloudy |
Moderate |
S |
1 |
12:36:00 PM |
7.5 |
7.2 |
33.5 |
22.2 |
2.2 |
6.0 |
<0.10 |
<0.01 |
WSR37 |
19/12/2023 |
Mid-flood |
Cloudy |
Moderate |
S |
1 |
12:36:00 PM |
7.5 |
7.2 |
33.4 |
22.2 |
2.3 |
5.0 |
<0.10 |
<0.01 |
WSR37 |
19/12/2023 |
Mid-flood |
Cloudy |
Moderate |
M |
4 |
12:37:00 PM |
7.6 |
7.3 |
33.3 |
22.2 |
2.5 |
6.0 |
<0.10 |
<0.01 |
WSR37 |
19/12/2023 |
Mid-flood |
Cloudy |
Moderate |
M |
4 |
12:37:00 PM |
7.5 |
7.2 |
33.2 |
22.2 |
2.5 |
5.0 |
<0.10 |
<0.01 |
WSR37 |
19/12/2023 |
Mid-flood |
Cloudy |
Moderate |
B |
7 |
12:38:00 PM |
7.6 |
7.2 |
33.4 |
22.2 |
2.4 |
5.0 |
<0.10 |
<0.01 |
WSR37 |
19/12/2023 |
Mid-flood |
Cloudy |
Moderate |
B |
7 |
12:38:00 PM |
7.5 |
7.2 |
33.3 |
22.1 |
2.4 |
8.0 |
<0.10 |
<0.01 |
NF1 |
19/12/2023 |
Mid-flood |
Cloudy |
Moderate |
S |
1 |
1:15:00 PM |
8.3 |
7.3 |
33.0 |
22.1 |
2.0 |
3.0 |
<0.10 |
<0.01 |
NF1 |
19/12/2023 |
Mid-flood |
Cloudy |
Moderate |
S |
1 |
1:15:00 PM |
8.4 |
7.3 |
33.0 |
22.1 |
2.1 |
2.5 |
<0.10 |
<0.01 |
NF1 |
19/12/2023 |
Mid-flood |
Cloudy |
Moderate |
M |
7 |
1:16:00 PM |
8.2 |
7.3 |
32.9 |
22.1 |
2.1 |
3.0 |
<0.10 |
<0.01 |
NF1 |
19/12/2023 |
Mid-flood |
Cloudy |
Moderate |
M |
7 |
1:16:00 PM |
8.4 |
7.3 |
33.0 |
22.0 |
2.0 |
4.0 |
<0.10 |
<0.01 |
NF1 |
19/12/2023 |
Mid-flood |
Cloudy |
Moderate |
B |
12 |
1:17:00 PM |
8.4 |
7.3 |
32.9 |
22.1 |
2.1 |
3.0 |
<0.10 |
<0.01 |
NF1 |
19/12/2023 |
Mid-flood |
Cloudy |
Moderate |
B |
12 |
1:17:00 PM |
8.4 |
7.3 |
32.9 |
22.1 |
2.1 |
3.0 |
<0.10 |
<0.01 |
NF2 |
19/12/2023 |
Mid-flood |
Cloudy |
Moderate |
S |
1 |
1:08:00 PM |
7.4 |
7.3 |
32.6 |
22.1 |
2.0 |
6.0 |
<0.10 |
<0.01 |
NF2 |
19/12/2023 |
Mid-flood |
Cloudy |
Moderate |
S |
1 |
1:08:00 PM |
7.5 |
7.3 |
32.4 |
22.1 |
2.1 |
7.0 |
<0.10 |
<0.01 |
NF2 |
19/12/2023 |
Mid-flood |
Cloudy |
Moderate |
M |
5 |
1:09:00 PM |
7.4 |
7.3 |
32.4 |
22.1 |
2.1 |
4.0 |
<0.10 |
<0.01 |
NF2 |
19/12/2023 |
Mid-flood |
Cloudy |
Moderate |
M |
5 |
1:09:00 PM |
7.4 |
7.4 |
32.4 |
22.0 |
2.0 |
2.5 |
<0.10 |
<0.01 |
NF2 |
19/12/2023 |
Mid-flood |
Cloudy |
Moderate |
B |
10 |
1:10:00 PM |
7.4 |
7.4 |
32.3 |
22.0 |
2.0 |
4.0 |
<0.10 |
<0.01 |
NF2 |
19/12/2023 |
Mid-flood |
Cloudy |
Moderate |
B |
10 |
1:10:00 PM |
7.5 |
7.3 |
32.3 |
22.1 |
2.2 |
4.0 |
<0.10 |
<0.01 |
NF3 |
19/12/2023 |
Mid-flood |
Cloudy |
Moderate |
S |
1 |
1:01:00 PM |
7.7 |
7.3 |
32.5 |
22.0 |
2.3 |
3.0 |
<0.10 |
<0.01 |
NF3 |
19/12/2023 |
Mid-flood |
Cloudy |
Moderate |
S |
1 |
1:01:00 PM |
7.8 |
7.3 |
32.6 |
22.0 |
2.4 |
2.5 |
<0.10 |
<0.01 |
NF3 |
19/12/2023 |
Mid-flood |
Cloudy |
Moderate |
M |
6 |
1:02:00 PM |
7.9 |
7.3 |
32.5 |
22.1 |
2.3 |
5.0 |
<0.10 |
<0.01 |
NF3 |
19/12/2023 |
Mid-flood |
Cloudy |
Moderate |
M |
6 |
1:02:00 PM |
7.8 |
7.3 |
32.6 |
22.0 |
2.4 |
4.0 |
<0.10 |
<0.01 |
NF3 |
19/12/2023 |
Mid-flood |
Cloudy |
Moderate |
B |
11 |
1:03:00 PM |
7.6 |
7.3 |
32.6 |
22.1 |
2.4 |
2.5 |
<0.10 |
<0.01 |
NF3 |
19/12/2023 |
Mid-flood |
Cloudy |
Moderate |
B |
11 |
1:03:00 PM |
7.9 |
7.3 |
32.3 |
22.1 |
2.4 |
4.0 |
<0.10 |
<0.01 |
CE |
21/12/2023 |
Mid-ebb |
Cloudy |
Moderate |
S |
1 |
8:00:00 AM |
7.4 |
7.6 |
34.3 |
21.9 |
3.2 |
3.0 |
<0.10 |
<0.01 |
CE |
21/12/2023 |
Mid-ebb |
Cloudy |
Moderate |
S |
1 |
8:00:00 AM |
7.5 |
7.6 |
34.2 |
21.9 |
3.1 |
3.0 |
<0.10 |
<0.01 |
CE |
21/12/2023 |
Mid-ebb |
Cloudy |
Moderate |
M |
11 |
8:01:00 AM |
7.5 |
7.5 |
34.4 |
21.9 |
3.0 |
4.0 |
<0.10 |
<0.01 |
CE |
21/12/2023 |
Mid-ebb |
Cloudy |
Moderate |
M |
11 |
8:01:00 AM |
7.4 |
7.6 |
34.5 |
21.9 |
3.0 |
3.0 |
<0.10 |
<0.01 |
CE |
21/12/2023 |
Mid-ebb |
Cloudy |
Moderate |
B |
20 |
8:02:00 AM |
7.4 |
7.6 |
34.4 |
22.0 |
2.9 |
5.0 |
<0.10 |
<0.01 |
CE |
21/12/2023 |
Mid-ebb |
Cloudy |
Moderate |
B |
20 |
8:02:00 AM |
7.4 |
7.6 |
34.2 |
22.0 |
2.8 |
6.0 |
<0.10 |
<0.01 |
CF |
21/12/2023 |
Mid-ebb |
Cloudy |
Moderate |
S |
1 |
11:11:00 AM |
8.3 |
7.1 |
32.9 |
22.1 |
2.5 |
4.0 |
<0.10 |
<0.01 |
CF |
21/12/2023 |
Mid-ebb |
Cloudy |
Moderate |
S |
1 |
11:11:00 AM |
8.3 |
7.2 |
33.1 |
22.2 |
2.6 |
3.0 |
<0.10 |
<0.01 |
CF |
21/12/2023 |
Mid-ebb |
Cloudy |
Moderate |
M |
10 |
11:12:00 AM |
8.2 |
7.2 |
32.9 |
22.2 |
2.7 |
4.0 |
<0.10 |
<0.01 |
CF |
21/12/2023 |
Mid-ebb |
Cloudy |
Moderate |
M |
10 |
11:12:00 AM |
8.4 |
7.1 |
33.0 |
22.2 |
2.8 |
4.0 |
<0.10 |
<0.01 |
CF |
21/12/2023 |
Mid-ebb |
Cloudy |
Moderate |
B |
19 |
11:13:00 AM |
8.4 |
7.2 |
33.0 |
22.2 |
2.9 |
4.0 |
<0.10 |
<0.01 |
CF |
21/12/2023 |
Mid-ebb |
Cloudy |
Moderate |
B |
19 |
11:13:00 AM |
8.5 |
7.2 |
33.1 |
22.1 |
2.8 |
3.0 |
<0.10 |
<0.01 |
Location Date Tidal Weather Sea Condition Water Level Depth (m) Time DO (mg/L) pH Sal (ppt) Temp (°C) Turbidty (NTU) SS (mg/L) Iron (mg/L) Total Chlorine
WSR01 |
21/12/2023 |
Mid-ebb |
Cloudy |
Moderate |
S |
1 |
10:47:00 AM |
7.8 |
7.4 |
34.3 |
22.0 |
2.2 |
4.0 |
<0.10 |
<0.01 |
WSR01 |
21/12/2023 |
Mid-ebb |
Cloudy |
Moderate |
S |
1 |
10:47:00 AM |
8.1 |
7.4 |
34.4 |
21.9 |
2.4 |
5.0 |
<0.10 |
<0.01 |
WSR01 |
21/12/2023 |
Mid-ebb |
Cloudy |
Moderate |
M |
4 |
10:48:00 AM |
8.0 |
7.4 |
34.4 |
22.0 |
2.4 |
4.0 |
<0.10 |
<0.01 |
WSR01 |
21/12/2023 |
Mid-ebb |
Cloudy |
Moderate |
M |
4 |
10:48:00 AM |
8.1 |
7.4 |
34.2 |
22.0 |
2.3 |
4.0 |
<0.10 |
<0.01 |
WSR01 |
21/12/2023 |
Mid-ebb |
Cloudy |
Moderate |
B |
8 |
10:49:00 AM |
8.1 |
7.4 |
34.2 |
22.0 |
2.4 |
6.0 |
<0.10 |
<0.01 |
WSR01 |
21/12/2023 |
Mid-ebb |
Cloudy |
Moderate |
B |
8 |
10:49:00 AM |
7.9 |
7.4 |
34.4 |
21.9 |
2.3 |
4.0 |
<0.10 |
<0.01 |
WSR02 |
21/12/2023 |
Mid-ebb |
Cloudy |
Moderate |
S |
1 |
10:26:00 AM |
9.2 |
7.3 |
32.9 |
22.0 |
2.2 |
3.0 |
<0.10 |
<0.01 |
WSR02 |
21/12/2023 |
Mid-ebb |
Cloudy |
Moderate |
S |
1 |
10:26:00 AM |
9.0 |
7.3 |
32.6 |
22.1 |
2.3 |
4.0 |
<0.10 |
<0.01 |
WSR02 |
21/12/2023 |
Mid-ebb |
Cloudy |
Moderate |
M |
5 |
10:27:00 AM |
8.9 |
7.3 |
32.8 |
22.1 |
2.2 |
4.0 |
<0.10 |
<0.01 |
WSR02 |
21/12/2023 |
Mid-ebb |
Cloudy |
Moderate |
M |
5 |
10:27:00 AM |
8.9 |
7.3 |
32.8 |
22.1 |
2.2 |
4.0 |
<0.10 |
<0.01 |
WSR02 |
21/12/2023 |
Mid-ebb |
Cloudy |
Moderate |
B |
9 |
10:28:00 AM |
9.0 |
7.3 |
32.9 |
22.0 |
2.3 |
4.0 |
<0.10 |
<0.01 |
WSR02 |
21/12/2023 |
Mid-ebb |
Cloudy |
Moderate |
B |
9 |
10:28:00 AM |
9.1 |
7.3 |
32.7 |
22.1 |
2.3 |
5.0 |
<0.10 |
<0.01 |
WSR03 |
21/12/2023 |
Mid-ebb |
Cloudy |
Moderate |
S |
1 |
10:10:00 AM |
8.0 |
7.4 |
32.5 |
21.9 |
1.7 |
6.0 |
<0.10 |
<0.01 |
WSR03 |
21/12/2023 |
Mid-ebb |
Cloudy |
Moderate |
S |
1 |
10:10:00 AM |
7.8 |
7.4 |
32.5 |
21.9 |
1.7 |
6.0 |
<0.10 |
<0.01 |
WSR03 |
21/12/2023 |
Mid-ebb |
Cloudy |
Moderate |
M |
4 |
10:11:00 AM |
8.0 |
7.4 |
32.8 |
21.9 |
1.6 |
5.0 |
<0.10 |
<0.01 |
WSR03 |
21/12/2023 |
Mid-ebb |
Cloudy |
Moderate |
M |
4 |
10:11:00 AM |
8.1 |
7.4 |
32.7 |
22.0 |
1.7 |
5.0 |
<0.10 |
<0.01 |
WSR03 |
21/12/2023 |
Mid-ebb |
Cloudy |
Moderate |
B |
7 |
10:12:00 AM |
8.1 |
7.4 |
32.5 |
21.9 |
1.7 |
4.0 |
<0.10 |
<0.01 |
WSR03 |
21/12/2023 |
Mid-ebb |
Cloudy |
Moderate |
B |
7 |
10:12:00 AM |
7.9 |
7.4 |
32.7 |
21.9 |
1.6 |
4.0 |
<0.10 |
<0.01 |
WSR04 |
21/12/2023 |
Mid-ebb |
Cloudy |
Moderate |
S |
1 |
9:55:00 AM |
7.3 |
7.5 |
34.1 |
22.2 |
1.2 |
4.0 |
<0.10 |
<0.01 |
WSR04 |
21/12/2023 |
Mid-ebb |
Cloudy |
Moderate |
S |
1 |
9:55:00 AM |
7.5 |
7.5 |
34.2 |
22.2 |
1.3 |
3.0 |
<0.10 |
<0.01 |
WSR04 |
21/12/2023 |
Mid-ebb |
Cloudy |
Moderate |
M |
4 |
9:56:00 AM |
7.3 |
7.4 |
34.2 |
22.2 |
1.3 |
4.0 |
<0.10 |
<0.01 |
WSR04 |
21/12/2023 |
Mid-ebb |
Cloudy |
Moderate |
M |
4 |
9:56:00 AM |
7.3 |
7.5 |
33.9 |
22.2 |
1.4 |
4.0 |
<0.10 |
<0.01 |
WSR04 |
21/12/2023 |
Mid-ebb |
Cloudy |
Moderate |
B |
6 |
9:57:00 AM |
7.4 |
7.5 |
34.2 |
22.1 |
1.2 |
5.0 |
<0.10 |
<0.01 |
WSR04 |
21/12/2023 |
Mid-ebb |
Cloudy |
Moderate |
B |
6 |
9:57:00 AM |
7.3 |
7.5 |
33.9 |
22.2 |
1.4 |
5.0 |
<0.10 |
<0.01 |
WSR16 |
21/12/2023 |
Mid-ebb |
Cloudy |
Moderate |
S |
1 |
8:24:00 AM |
8.5 |
7.4 |
32.7 |
22.1 |
1.6 |
5.0 |
<0.10 |
<0.01 |
WSR16 |
21/12/2023 |
Mid-ebb |
Cloudy |
Moderate |
S |
1 |
8:24:00 AM |
8.4 |
7.4 |
32.7 |
22.2 |
1.7 |
4.0 |
<0.10 |
<0.01 |
WSR16 |
21/12/2023 |
Mid-ebb |
Cloudy |
Moderate |
M |
8 |
8:25:00 AM |
8.5 |
7.4 |
32.5 |
22.2 |
1.6 |
5.0 |
<0.10 |
<0.01 |
WSR16 |
21/12/2023 |
Mid-ebb |
Cloudy |
Moderate |
M |
8 |
8:25:00 AM |
8.4 |
7.4 |
32.8 |
22.1 |
1.6 |
6.0 |
<0.10 |
<0.01 |
WSR16 |
21/12/2023 |
Mid-ebb |
Cloudy |
Moderate |
B |
15 |
8:26:00 AM |
8.5 |
7.4 |
32.6 |
22.2 |
1.6 |
4.0 |
<0.10 |
<0.01 |
WSR16 |
21/12/2023 |
Mid-ebb |
Cloudy |
Moderate |
B |
15 |
8:26:00 AM |
8.6 |
7.4 |
32.6 |
22.2 |
1.6 |
5.0 |
<0.10 |
<0.01 |
WSR33 |
21/12/2023 |
Mid-ebb |
Cloudy |
Moderate |
S |
1 |
9:38:00 AM |
8.4 |
7.4 |
33.4 |
22.1 |
2.2 |
4.0 |
<0.10 |
<0.01 |
WSR33 |
21/12/2023 |
Mid-ebb |
Cloudy |
Moderate |
S |
1 |
9:38:00 AM |
8.3 |
7.4 |
33.6 |
22.2 |
2.3 |
7.0 |
<0.10 |
<0.01 |
WSR33 |
21/12/2023 |
Mid-ebb |
Cloudy |
Moderate |
M |
4 |
9:39:00 AM |
8.1 |
7.4 |
33.4 |
22.1 |
2.2 |
5.0 |
<0.10 |
<0.01 |
WSR33 |
21/12/2023 |
Mid-ebb |
Cloudy |
Moderate |
M |
4 |
9:39:00 AM |
8.2 |
7.4 |
33.5 |
22.2 |
2.3 |
6.0 |
<0.10 |
<0.01 |
WSR33 |
21/12/2023 |
Mid-ebb |
Cloudy |
Moderate |
B |
7 |
9:40:00 AM |
8.3 |
7.4 |
33.3 |
22.2 |
2.3 |
7.0 |
<0.10 |
<0.01 |
WSR33 |
21/12/2023 |
Mid-ebb |
Cloudy |
Moderate |
B |
7 |
9:40:00 AM |
8.3 |
7.4 |
33.4 |
22.2 |
2.2 |
6.0 |
<0.10 |
<0.01 |
Location Date Tidal Weather Sea Condition Water Level Depth (m) Time DO (mg/L) pH Sal (ppt) Temp (°C) Turbidty (NTU) SS (mg/L) Iron (mg/L) Total Chlorine
WSR36 |
21/12/2023 |
Mid-ebb |
Cloudy |
Moderate |
S |
1 |
9:24:00 AM |
8.2 |
7.3 |
34.6 |
22.1 |
2.4 |
5.0 |
<0.10 |
<0.01 |
WSR36 |
21/12/2023 |
Mid-ebb |
Cloudy |
Moderate |
S |
1 |
9:24:00 AM |
8.3 |
7.3 |
34.3 |
22.1 |
2.3 |
6.0 |
<0.10 |
<0.01 |
WSR36 |
21/12/2023 |
Mid-ebb |
Cloudy |
Moderate |
M |
4 |
9:25:00 AM |
8.3 |
7.3 |
34.5 |
22.0 |
2.5 |
4.0 |
<0.10 |
<0.01 |
WSR36 |
21/12/2023 |
Mid-ebb |
Cloudy |
Moderate |
M |
4 |
9:25:00 AM |
8.3 |
7.3 |
34.3 |
22.1 |
2.4 |
5.0 |
<0.10 |
<0.01 |
WSR36 |
21/12/2023 |
Mid-ebb |
Cloudy |
Moderate |
B |
7 |
9:25:00 AM |
8.2 |
7.3 |
34.6 |
22.0 |
2.4 |
5.0 |
<0.10 |
<0.01 |
WSR36 |
21/12/2023 |
Mid-ebb |
Cloudy |
Moderate |
B |
7 |
9:25:00 AM |
8.3 |
7.3 |
34.4 |
22.0 |
2.5 |
4.0 |
<0.10 |
<0.01 |
WSR37 |
21/12/2023 |
Mid-ebb |
Cloudy |
Moderate |
S |
1 |
9:18:00 AM |
8.1 |
7.3 |
33.5 |
21.9 |
2.1 |
5.0 |
<0.10 |
<0.01 |
WSR37 |
21/12/2023 |
Mid-ebb |
Cloudy |
Moderate |
S |
1 |
9:18:00 AM |
8.1 |
7.4 |
33.7 |
21.9 |
2.1 |
4.0 |
<0.10 |
<0.01 |
WSR37 |
21/12/2023 |
Mid-ebb |
Cloudy |
Moderate |
M |
4 |
9:19:00 AM |
8.0 |
7.4 |
33.4 |
21.9 |
2.2 |
8.0 |
<0.10 |
<0.01 |
WSR37 |
21/12/2023 |
Mid-ebb |
Cloudy |
Moderate |
M |
4 |
9:19:00 AM |
8.2 |
7.3 |
33.6 |
21.9 |
2.1 |
6.0 |
<0.10 |
<0.01 |
WSR37 |
21/12/2023 |
Mid-ebb |
Cloudy |
Moderate |
B |
7 |
9:20:00 AM |
8.0 |
7.4 |
33.6 |
21.9 |
2.1 |
5.0 |
<0.10 |
<0.01 |
WSR37 |
21/12/2023 |
Mid-ebb |
Cloudy |
Moderate |
B |
7 |
9:20:00 AM |
8.0 |
7.3 |
33.5 |
21.8 |
2.1 |
4.0 |
<0.10 |
<0.01 |
NF1 |
21/12/2023 |
Mid-ebb |
Cloudy |
Moderate |
S |
1 |
8:48:00 AM |
8.4 |
7.3 |
33.0 |
22.0 |
2.2 |
3.0 |
<0.10 |
<0.01 |
NF1 |
21/12/2023 |
Mid-ebb |
Cloudy |
Moderate |
S |
1 |
8:48:00 AM |
8.2 |
7.3 |
33.0 |
22.0 |
2.3 |
5.0 |
<0.10 |
<0.01 |
NF1 |
21/12/2023 |
Mid-ebb |
Cloudy |
Moderate |
M |
7 |
8:49:00 AM |
8.2 |
7.3 |
32.9 |
22.1 |
2.3 |
4.0 |
<0.10 |
<0.01 |
NF1 |
21/12/2023 |
Mid-ebb |
Cloudy |
Moderate |
M |
7 |
8:49:00 AM |
8.3 |
7.3 |
32.9 |
22.0 |
2.4 |
5.0 |
<0.10 |
<0.01 |
NF1 |
21/12/2023 |
Mid-ebb |
Cloudy |
Moderate |
B |
13 |
8:50:00 AM |
8.4 |
7.3 |
32.9 |
22.0 |
2.3 |
5.0 |
<0.10 |
<0.01 |
NF1 |
21/12/2023 |
Mid-ebb |
Cloudy |
Moderate |
B |
13 |
8:50:00 AM |
8.2 |
7.2 |
32.9 |
22.0 |
2.3 |
4.0 |
<0.10 |
<0.01 |
NF2 |
21/12/2023 |
Mid-ebb |
Cloudy |
Moderate |
S |
1 |
9:05:00 AM |
8.3 |
7.1 |
32.8 |
21.8 |
1.8 |
4.0 |
<0.10 |
<0.01 |
NF2 |
21/12/2023 |
Mid-ebb |
Cloudy |
Moderate |
S |
1 |
9:05:00 AM |
8.3 |
7.2 |
32.5 |
21.9 |
1.8 |
3.0 |
<0.10 |
<0.01 |
NF2 |
21/12/2023 |
Mid-ebb |
Cloudy |
Moderate |
M |
5 |
9:06:00 AM |
8.4 |
7.2 |
32.8 |
21.8 |
1.8 |
3.0 |
<0.10 |
<0.01 |
NF2 |
21/12/2023 |
Mid-ebb |
Cloudy |
Moderate |
M |
5 |
9:06:00 AM |
8.4 |
7.2 |
32.7 |
21.9 |
1.7 |
3.0 |
<0.10 |
<0.01 |
NF2 |
21/12/2023 |
Mid-ebb |
Cloudy |
Moderate |
B |
10 |
9:07:00 AM |
8.3 |
7.2 |
32.8 |
21.9 |
1.8 |
4.0 |
<0.10 |
<0.01 |
NF2 |
21/12/2023 |
Mid-ebb |
Cloudy |
Moderate |
B |
10 |
9:07:00 AM |
8.5 |
7.2 |
32.6 |
21.9 |
1.7 |
4.0 |
<0.10 |
<0.01 |
NF3 |
21/12/2023 |
Mid-ebb |
Cloudy |
Moderate |
S |
1 |
9:11:00 AM |
7.6 |
7.5 |
32.6 |
22.0 |
1.9 |
5.0 |
<0.10 |
<0.01 |
NF3 |
21/12/2023 |
Mid-ebb |
Cloudy |
Moderate |
S |
1 |
9:11:00 AM |
7.7 |
7.5 |
32.6 |
22.1 |
2.0 |
4.0 |
<0.10 |
<0.01 |
NF3 |
21/12/2023 |
Mid-ebb |
Cloudy |
Moderate |
M |
6 |
9:12:00 AM |
7.6 |
7.5 |
32.9 |
22.1 |
1.9 |
3.0 |
<0.10 |
<0.01 |
NF3 |
21/12/2023 |
Mid-ebb |
Cloudy |
Moderate |
M |
6 |
9:12:00 AM |
7.8 |
7.5 |
32.7 |
22.0 |
2.0 |
3.0 |
<0.10 |
<0.01 |
NF3 |
21/12/2023 |
Mid-ebb |
Cloudy |
Moderate |
B |
11 |
9:13:00 AM |
7.8 |
7.5 |
32.8 |
22.1 |
2.0 |
4.0 |
<0.10 |
<0.01 |
NF3 |
21/12/2023 |
Mid-ebb |
Cloudy |
Moderate |
B |
11 |
9:13:00 AM |
7.7 |
7.5 |
32.9 |
22.0 |
2.0 |
7.0 |
<0.10 |
<0.01 |
CE |
23/12/2023 |
Mid-ebb |
Cloudy |
Moderate |
S |
1 |
8:00:00 AM |
8.9 |
7.4 |
33.2 |
21.1 |
3.5 |
4.0 |
<0.10 |
<0.01 |
CE |
23/12/2023 |
Mid-ebb |
Cloudy |
Moderate |
S |
1 |
8:00:00 AM |
9.6 |
7.4 |
33.2 |
21.1 |
3.4 |
5.0 |
<0.10 |
<0.01 |
CE |
23/12/2023 |
Mid-ebb |
Cloudy |
Moderate |
M |
12 |
8:01:00 AM |
8.4 |
7.3 |
33.2 |
21.1 |
3.5 |
3.0 |
<0.10 |
<0.01 |
CE |
23/12/2023 |
Mid-ebb |
Cloudy |
Moderate |
M |
12 |
8:01:00 AM |
9.6 |
7.4 |
33.2 |
21.0 |
3.7 |
4.0 |
<0.10 |
<0.01 |
CE |
23/12/2023 |
Mid-ebb |
Cloudy |
Moderate |
B |
23 |
8:02:00 AM |
8.3 |
7.4 |
33.2 |
21.1 |
3.8 |
6.0 |
<0.10 |
<0.01 |
CE |
23/12/2023 |
Mid-ebb |
Cloudy |
Moderate |
B |
23 |
8:02:00 AM |
8.9 |
7.3 |
33.2 |
21.1 |
3.7 |
4.0 |
<0.10 |
<0.01 |
Location Date Tidal Weather Sea Condition Water Level Depth (m) Time DO (mg/L) pH Sal (ppt) Temp (°C) Turbidty (NTU) SS (mg/L) Iron (mg/L) Total Chlorine
CF |
23/12/2023 |
Mid-ebb |
Cloudy |
Moderate |
S |
1 |
11:12:00 AM |
9.2 |
7.4 |
33.6 |
21.0 |
3.2 |
5.0 |
<0.10 |
<0.01 |
CF |
23/12/2023 |
Mid-ebb |
Cloudy |
Moderate |
S |
1 |
11:12:00 AM |
8.7 |
7.4 |
33.7 |
21.0 |
3.2 |
5.0 |
<0.10 |
<0.01 |
CF |
23/12/2023 |
Mid-ebb |
Cloudy |
Moderate |
M |
10 |
11:13:00 AM |
9.8 |
7.3 |
33.7 |
21.0 |
2.9 |
6.0 |
<0.10 |
<0.01 |
CF |
23/12/2023 |
Mid-ebb |
Cloudy |
Moderate |
M |
10 |
11:13:00 AM |
9.1 |
7.3 |
33.7 |
21.0 |
2.8 |
6.0 |
<0.10 |
<0.01 |
CF |
23/12/2023 |
Mid-ebb |
Cloudy |
Moderate |
B |
19 |
11:14:00 AM |
9.0 |
7.4 |
33.7 |
21.0 |
2.8 |
7.0 |
<0.10 |
<0.01 |
CF |
23/12/2023 |
Mid-ebb |
Cloudy |
Moderate |
B |
19 |
11:14:00 AM |
9.9 |
7.4 |
33.7 |
20.9 |
3.0 |
5.0 |
<0.10 |
<0.01 |
WSR01 |
23/12/2023 |
Mid-ebb |
Cloudy |
Moderate |
S |
1 |
10:47:00 AM |
9.3 |
7.4 |
33.4 |
21.2 |
2.0 |
5.0 |
<0.10 |
<0.01 |
WSR01 |
23/12/2023 |
Mid-ebb |
Cloudy |
Moderate |
S |
1 |
10:47:00 AM |
9.1 |
7.3 |
33.4 |
21.3 |
1.8 |
5.0 |
<0.10 |
<0.01 |
WSR01 |
23/12/2023 |
Mid-ebb |
Cloudy |
Moderate |
M |
5 |
10:48:00 AM |
10.0 |
7.3 |
33.5 |
21.2 |
2.0 |
5.0 |
<0.10 |
<0.01 |
WSR01 |
23/12/2023 |
Mid-ebb |
Cloudy |
Moderate |
M |
5 |
10:48:00 AM |
9.9 |
7.3 |
33.4 |
21.3 |
2.0 |
6.0 |
<0.10 |
<0.01 |
WSR01 |
23/12/2023 |
Mid-ebb |
Cloudy |
Moderate |
B |
9 |
10:49:00 AM |
9.2 |
7.4 |
33.3 |
21.3 |
2.0 |
5.0 |
<0.10 |
<0.01 |
WSR01 |
23/12/2023 |
Mid-ebb |
Cloudy |
Moderate |
B |
9 |
10:49:00 AM |
10.0 |
7.3 |
33.4 |
21.2 |
1.9 |
3.0 |
<0.10 |
<0.01 |
WSR02 |
23/12/2023 |
Mid-ebb |
Cloudy |
Moderate |
S |
1 |
10:27:00 AM |
9.3 |
7.2 |
33.0 |
21.1 |
2.3 |
4.0 |
<0.10 |
<0.01 |
WSR02 |
23/12/2023 |
Mid-ebb |
Cloudy |
Moderate |
S |
1 |
10:27:00 AM |
8.4 |
7.1 |
33.0 |
21.1 |
2.4 |
4.0 |
<0.10 |
<0.01 |
WSR02 |
23/12/2023 |
Mid-ebb |
Cloudy |
Moderate |
M |
5 |
10:28:00 AM |
9.2 |
7.1 |
33.0 |
21.1 |
2.4 |
4.0 |
<0.10 |
<0.01 |
WSR02 |
23/12/2023 |
Mid-ebb |
Cloudy |
Moderate |
M |
5 |
10:28:00 AM |
9.2 |
7.1 |
32.9 |
21.1 |
2.4 |
2.5 |
<0.10 |
<0.01 |
WSR02 |
23/12/2023 |
Mid-ebb |
Cloudy |
Moderate |
B |
9 |
10:29:00 AM |
8.3 |
7.1 |
32.9 |
21.1 |
2.4 |
5.0 |
<0.10 |
<0.01 |
WSR02 |
23/12/2023 |
Mid-ebb |
Cloudy |
Moderate |
B |
9 |
10:29:00 AM |
9.0 |
7.1 |
33.0 |
21.1 |
2.5 |
5.0 |
<0.10 |
<0.01 |
WSR03 |
23/12/2023 |
Mid-ebb |
Cloudy |
Moderate |
S |
1 |
10:09:00 AM |
10.0 |
7.3 |
33.4 |
21.2 |
2.2 |
5.0 |
<0.10 |
<0.01 |
WSR03 |
23/12/2023 |
Mid-ebb |
Cloudy |
Moderate |
S |
1 |
10:09:00 AM |
9.0 |
7.4 |
33.5 |
21.2 |
2.3 |
3.0 |
<0.10 |
<0.01 |
WSR03 |
23/12/2023 |
Mid-ebb |
Cloudy |
Moderate |
M |
4 |
10:10:00 AM |
9.7 |
7.4 |
33.4 |
21.1 |
2.4 |
4.0 |
<0.10 |
<0.01 |
WSR03 |
23/12/2023 |
Mid-ebb |
Cloudy |
Moderate |
M |
4 |
10:10:00 AM |
9.9 |
7.4 |
33.4 |
21.1 |
2.4 |
4.0 |
<0.10 |
<0.01 |
WSR03 |
23/12/2023 |
Mid-ebb |
Cloudy |
Moderate |
B |
7 |
10:11:00 AM |
9.9 |
7.3 |
33.4 |
21.1 |
2.6 |
4.0 |
<0.10 |
<0.01 |
WSR03 |
23/12/2023 |
Mid-ebb |
Cloudy |
Moderate |
B |
7 |
10:11:00 AM |
9.1 |
7.4 |
33.5 |
21.1 |
2.5 |
5.0 |
<0.10 |
<0.01 |
WSR04 |
23/12/2023 |
Mid-ebb |
Cloudy |
Moderate |
S |
1 |
9:54:00 AM |
9.2 |
7.3 |
32.9 |
21.2 |
2.4 |
5.0 |
<0.10 |
<0.01 |
WSR04 |
23/12/2023 |
Mid-ebb |
Cloudy |
Moderate |
S |
1 |
9:54:00 AM |
9.3 |
7.3 |
32.9 |
21.2 |
2.4 |
6.0 |
<0.10 |
<0.01 |
WSR04 |
23/12/2023 |
Mid-ebb |
Cloudy |
Moderate |
M |
4 |
9:55:00 AM |
8.7 |
7.3 |
33.0 |
21.3 |
2.4 |
3.0 |
<0.10 |
<0.01 |
WSR04 |
23/12/2023 |
Mid-ebb |
Cloudy |
Moderate |
M |
4 |
9:55:00 AM |
9.3 |
7.3 |
32.8 |
21.3 |
2.4 |
5.0 |
<0.10 |
<0.01 |
WSR04 |
23/12/2023 |
Mid-ebb |
Cloudy |
Moderate |
B |
6 |
9:56:00 AM |
9.4 |
7.3 |
33.0 |
21.2 |
2.3 |
2.5 |
<0.10 |
<0.01 |
WSR04 |
23/12/2023 |
Mid-ebb |
Cloudy |
Moderate |
B |
6 |
9:56:00 AM |
9.3 |
7.3 |
32.9 |
21.3 |
2.5 |
3.0 |
<0.10 |
<0.01 |
WSR16 |
23/12/2023 |
Mid-ebb |
Cloudy |
Moderate |
S |
1 |
8:23:00 AM |
8.4 |
7.2 |
32.5 |
21.2 |
2.3 |
4.0 |
<0.10 |
<0.01 |
WSR16 |
23/12/2023 |
Mid-ebb |
Cloudy |
Moderate |
S |
1 |
8:23:00 AM |
8.6 |
7.2 |
32.5 |
21.2 |
2.4 |
2.5 |
<0.10 |
<0.01 |
WSR16 |
23/12/2023 |
Mid-ebb |
Cloudy |
Moderate |
M |
8 |
8:24:00 AM |
9.1 |
7.2 |
32.4 |
21.1 |
2.4 |
2.5 |
<0.10 |
<0.01 |
WSR16 |
23/12/2023 |
Mid-ebb |
Cloudy |
Moderate |
M |
8 |
8:24:00 AM |
9.2 |
7.2 |
32.4 |
21.2 |
2.4 |
3.0 |
<0.10 |
<0.01 |
WSR16 |
23/12/2023 |
Mid-ebb |
Cloudy |
Moderate |
B |
16 |
8:25:00 AM |
8.5 |
7.2 |
32.4 |
21.1 |
2.6 |
5.0 |
<0.10 |
<0.01 |
WSR16 |
23/12/2023 |
Mid-ebb |
Cloudy |
Moderate |
B |
16 |
8:25:00 AM |
8.9 |
7.2 |
32.3 |
21.2 |
2.4 |
3.0 |
<0.10 |
<0.01 |
Location Date Tidal Weather Sea Condition Water Level Depth (m) Time DO (mg/L) pH Sal (ppt) Temp (°C) Turbidty (NTU) SS (mg/L) Iron (mg/L) Total Chlorine
WSR33 |
23/12/2023 |
Mid-ebb |
Cloudy |
Moderate |
S |
1 |
9:37:00 AM |
8.5 |
7.4 |
33.7 |
21.2 |
2.3 |
3.0 |
<0.10 |
<0.01 |
WSR33 |
23/12/2023 |
Mid-ebb |
Cloudy |
Moderate |
S |
1 |
9:37:00 AM |
8.9 |
7.4 |
33.7 |
21.2 |
2.2 |
3.0 |
<0.10 |
<0.01 |
WSR33 |
23/12/2023 |
Mid-ebb |
Cloudy |
Moderate |
M |
4 |
9:38:00 AM |
9.3 |
7.3 |
33.6 |
21.2 |
2.3 |
4.0 |
<0.10 |
<0.01 |
WSR33 |
23/12/2023 |
Mid-ebb |
Cloudy |
Moderate |
M |
4 |
9:38:00 AM |
7.9 |
7.3 |
33.6 |
21.3 |
2.3 |
2.5 |
<0.10 |
<0.01 |
WSR33 |
23/12/2023 |
Mid-ebb |
Cloudy |
Moderate |
B |
6 |
9:39:00 AM |
8.5 |
7.3 |
33.6 |
21.3 |
2.3 |
4.0 |
<0.10 |
<0.01 |
WSR33 |
23/12/2023 |
Mid-ebb |
Cloudy |
Moderate |
B |
6 |
9:39:00 AM |
8.6 |
7.3 |
33.7 |
21.2 |
2.3 |
2.5 |
<0.10 |
<0.01 |
WSR36 |
23/12/2023 |
Mid-ebb |
Cloudy |
Moderate |
S |
1 |
9:21:00 AM |
8.9 |
7.2 |
33.2 |
21.2 |
2.1 |
3.0 |
<0.10 |
<0.01 |
WSR36 |
23/12/2023 |
Mid-ebb |
Cloudy |
Moderate |
S |
1 |
9:21:00 AM |
9.3 |
7.2 |
33.1 |
21.2 |
2.3 |
2.5 |
<0.10 |
<0.01 |
WSR36 |
23/12/2023 |
Mid-ebb |
Cloudy |
Moderate |
M |
4 |
9:22:00 AM |
9.0 |
7.2 |
33.1 |
21.2 |
2.2 |
2.5 |
<0.10 |
<0.01 |
WSR36 |
23/12/2023 |
Mid-ebb |
Cloudy |
Moderate |
M |
4 |
9:22:00 AM |
9.5 |
7.2 |
33.0 |
21.2 |
2.3 |
3.0 |
<0.10 |
<0.01 |
WSR36 |
23/12/2023 |
Mid-ebb |
Cloudy |
Moderate |
B |
6 |
9:22:00 AM |
9.3 |
7.1 |
33.0 |
21.1 |
2.6 |
3.0 |
<0.10 |
<0.01 |
WSR36 |
23/12/2023 |
Mid-ebb |
Cloudy |
Moderate |
B |
6 |
9:22:00 AM |
9.5 |
7.2 |
33.1 |
21.2 |
2.6 |
4.0 |
<0.10 |
<0.01 |
WSR37 |
23/12/2023 |
Mid-ebb |
Cloudy |
Moderate |
S |
1 |
9:15:00 AM |
9.1 |
7.3 |
32.4 |
21.2 |
2.4 |
4.0 |
<0.10 |
<0.01 |
WSR37 |
23/12/2023 |
Mid-ebb |
Cloudy |
Moderate |
S |
1 |
9:15:00 AM |
8.9 |
7.4 |
32.5 |
21.1 |
2.3 |
4.0 |
<0.10 |
<0.01 |
WSR37 |
23/12/2023 |
Mid-ebb |
Cloudy |
Moderate |
M |
4 |
9:16:00 AM |
9.9 |
7.3 |
32.5 |
21.2 |
2.4 |
6.0 |
<0.10 |
<0.01 |
WSR37 |
23/12/2023 |
Mid-ebb |
Cloudy |
Moderate |
M |
4 |
9:16:00 AM |
8.7 |
7.3 |
32.5 |
21.2 |
2.4 |
5.0 |
<0.10 |
<0.01 |
WSR37 |
23/12/2023 |
Mid-ebb |
Cloudy |
Moderate |
B |
8 |
9:17:00 AM |
9.7 |
7.3 |
32.6 |
21.1 |
2.4 |
4.0 |
<0.10 |
<0.01 |
WSR37 |
23/12/2023 |
Mid-ebb |
Cloudy |
Moderate |
B |
8 |
9:17:00 AM |
8.8 |
7.4 |
32.4 |
21.2 |
2.5 |
3.0 |
<0.10 |
<0.01 |
NF1 |
23/12/2023 |
Mid-ebb |
Cloudy |
Moderate |
S |
1 |
8:47:00 AM |
8.3 |
7.3 |
32.5 |
20.9 |
2.2 |
3.0 |
<0.10 |
<0.01 |
NF1 |
23/12/2023 |
Mid-ebb |
Cloudy |
Moderate |
S |
1 |
8:47:00 AM |
8.8 |
7.3 |
32.5 |
20.9 |
2.3 |
3.0 |
<0.10 |
<0.01 |
NF1 |
23/12/2023 |
Mid-ebb |
Cloudy |
Moderate |
M |
7 |
8:48:00 AM |
7.8 |
7.4 |
32.5 |
21.0 |
2.2 |
3.0 |
<0.10 |
<0.01 |
NF1 |
23/12/2023 |
Mid-ebb |
Cloudy |
Moderate |
M |
7 |
8:48:00 AM |
8.1 |
7.3 |
32.6 |
21.0 |
2.2 |
3.0 |
<0.10 |
<0.01 |
NF1 |
23/12/2023 |
Mid-ebb |
Cloudy |
Moderate |
B |
13 |
8:49:00 AM |
8.7 |
7.3 |
32.5 |
21.0 |
2.2 |
3.0 |
<0.10 |
<0.01 |
NF1 |
23/12/2023 |
Mid-ebb |
Cloudy |
Moderate |
B |
13 |
8:49:00 AM |
8.3 |
7.4 |
32.6 |
21.0 |
2.2 |
3.0 |
<0.10 |
<0.01 |
NF2 |
23/12/2023 |
Mid-ebb |
Cloudy |
Moderate |
S |
1 |
9:02:00 AM |
8.9 |
7.3 |
32.6 |
21.0 |
1.6 |
3.0 |
<0.10 |
<0.01 |
NF2 |
23/12/2023 |
Mid-ebb |
Cloudy |
Moderate |
S |
1 |
9:02:00 AM |
9.1 |
7.2 |
32.6 |
21.0 |
1.7 |
3.0 |
<0.10 |
<0.01 |
NF2 |
23/12/2023 |
Mid-ebb |
Cloudy |
Moderate |
M |
5 |
9:03:00 AM |
9.3 |
7.2 |
32.7 |
20.9 |
1.6 |
3.0 |
<0.10 |
<0.01 |
NF2 |
23/12/2023 |
Mid-ebb |
Cloudy |
Moderate |
M |
5 |
9:03:00 AM |
8.6 |
7.3 |
32.7 |
21.0 |
1.7 |
2.5 |
<0.10 |
<0.01 |
NF2 |
23/12/2023 |
Mid-ebb |
Cloudy |
Moderate |
B |
10 |
9:04:00 AM |
9.1 |
7.2 |
32.7 |
21.0 |
1.6 |
6.0 |
<0.10 |
<0.01 |
NF2 |
23/12/2023 |
Mid-ebb |
Cloudy |
Moderate |
B |
10 |
9:04:00 AM |
9.1 |
7.3 |
32.7 |
20.9 |
1.6 |
6.0 |
<0.10 |
<0.01 |
NF3 |
23/12/2023 |
Mid-ebb |
Cloudy |
Moderate |
S |
1 |
9:10:00 AM |
9.8 |
7.4 |
33.4 |
20.9 |
2.2 |
5.0 |
<0.10 |
<0.01 |
NF3 |
23/12/2023 |
Mid-ebb |
Cloudy |
Moderate |
S |
1 |
9:10:00 AM |
9.7 |
7.3 |
33.5 |
20.9 |
2.4 |
5.0 |
<0.10 |
<0.01 |
NF3 |
23/12/2023 |
Mid-ebb |
Cloudy |
Moderate |
M |
6 |
9:11:00 AM |
9.5 |
7.3 |
33.6 |
20.9 |
2.4 |
5.0 |
<0.10 |
<0.01 |
NF3 |
23/12/2023 |
Mid-ebb |
Cloudy |
Moderate |
M |
6 |
9:11:00 AM |
8.7 |
7.3 |
33.6 |
20.9 |
2.4 |
6.0 |
<0.10 |
<0.01 |
NF3 |
23/12/2023 |
Mid-ebb |
Cloudy |
Moderate |
B |
11 |
9:12:00 AM |
8.8 |
7.3 |
33.4 |
20.9 |
2.5 |
6.0 |
<0.10 |
<0.01 |
NF3 |
23/12/2023 |
Mid-ebb |
Cloudy |
Moderate |
B |
11 |
9:12:00 AM |
8.9 |
7.3 |
33.4 |
20.9 |
2.6 |
7.0 |
<0.10 |
<0.01 |
Location Date Tidal Weather Sea Condition Water Level Depth (m) Time DO (mg/L) pH Sal (ppt) Temp (°C) Turbidty (NTU) SS (mg/L) Iron (mg/L) Total Chlorine
CE |
26/12/2023 |
Mid-flood |
Sunny |
Moderate |
S |
1 |
10:30:00 AM |
9.9 |
6.6 |
33.4 |
21.9 |
3.1 |
3.0 |
<0.10 |
<0.01 |
CE |
26/12/2023 |
Mid-flood |
Sunny |
Moderate |
S |
1 |
10:30:00 AM |
10.0 |
6.7 |
33.7 |
22.0 |
3.0 |
3.0 |
<0.10 |
<0.01 |
CE |
26/12/2023 |
Mid-flood |
Sunny |
Moderate |
M |
11 |
10:31:00 AM |
9.9 |
6.6 |
33.7 |
22.0 |
3.1 |
5.0 |
<0.10 |
<0.01 |
CE |
26/12/2023 |
Mid-flood |
Sunny |
Moderate |
M |
11 |
10:31:00 AM |
10.0 |
6.7 |
33.7 |
21.9 |
3.1 |
4.0 |
<0.10 |
<0.01 |
CE |
26/12/2023 |
Mid-flood |
Sunny |
Moderate |
B |
21 |
10:32:00 AM |
9.9 |
6.6 |
33.6 |
21.9 |
3.0 |
5.0 |
<0.10 |
<0.01 |
CE |
26/12/2023 |
Mid-flood |
Sunny |
Moderate |
B |
21 |
10:32:00 AM |
10.0 |
6.6 |
33.4 |
21.9 |
3.0 |
4.0 |
<0.10 |
<0.01 |
CF |
26/12/2023 |
Mid-flood |
Sunny |
Moderate |
S |
1 |
1:49:00 PM |
10.0 |
6.8 |
32.6 |
21.9 |
2.7 |
2.5 |
<0.10 |
<0.01 |
CF |
26/12/2023 |
Mid-flood |
Sunny |
Moderate |
S |
1 |
1:49:00 PM |
10.0 |
6.8 |
32.6 |
21.9 |
2.7 |
4.0 |
<0.10 |
<0.01 |
CF |
26/12/2023 |
Mid-flood |
Sunny |
Moderate |
M |
10 |
1:50:00 PM |
9.7 |
6.8 |
32.7 |
21.9 |
2.7 |
3.0 |
<0.10 |
<0.01 |
CF |
26/12/2023 |
Mid-flood |
Sunny |
Moderate |
M |
10 |
1:50:00 PM |
9.9 |
6.8 |
32.5 |
21.9 |
2.8 |
2.5 |
<0.10 |
<0.01 |
CF |
26/12/2023 |
Mid-flood |
Sunny |
Moderate |
B |
19 |
1:51:00 PM |
9.9 |
6.8 |
32.4 |
21.9 |
2.7 |
4.0 |
<0.10 |
<0.01 |
CF |
26/12/2023 |
Mid-flood |
Sunny |
Moderate |
B |
19 |
1:51:00 PM |
9.8 |
6.8 |
32.5 |
21.9 |
2.7 |
2.5 |
<0.10 |
<0.01 |
WSR01 |
26/12/2023 |
Mid-flood |
Sunny |
Moderate |
S |
1 |
1:23:00 PM |
10.1 |
6.9 |
32.7 |
21.9 |
2.0 |
3.0 |
<0.10 |
<0.01 |
WSR01 |
26/12/2023 |
Mid-flood |
Sunny |
Moderate |
S |
1 |
1:23:00 PM |
10.1 |
6.8 |
32.5 |
21.9 |
2.1 |
4.0 |
<0.10 |
<0.01 |
WSR01 |
26/12/2023 |
Mid-flood |
Sunny |
Moderate |
M |
4 |
1:24:00 PM |
10.3 |
6.8 |
32.8 |
21.8 |
2.0 |
4.0 |
<0.10 |
<0.01 |
WSR01 |
26/12/2023 |
Mid-flood |
Sunny |
Moderate |
M |
4 |
1:24:00 PM |
10.3 |
6.8 |
32.7 |
21.8 |
2.1 |
5.0 |
<0.10 |
<0.01 |
WSR01 |
26/12/2023 |
Mid-flood |
Sunny |
Moderate |
B |
8 |
1:25:00 PM |
10.1 |
6.8 |
32.6 |
21.9 |
2.0 |
4.0 |
<0.10 |
<0.01 |
WSR01 |
26/12/2023 |
Mid-flood |
Sunny |
Moderate |
B |
8 |
1:25:00 PM |
10.2 |
6.9 |
32.6 |
21.8 |
2.0 |
4.0 |
<0.10 |
<0.01 |
WSR02 |
26/12/2023 |
Mid-flood |
Sunny |
Moderate |
S |
1 |
12:01:00 PM |
9.9 |
6.8 |
33.1 |
21.9 |
2.4 |
5.0 |
<0.10 |
<0.01 |
WSR02 |
26/12/2023 |
Mid-flood |
Sunny |
Moderate |
S |
1 |
12:01:00 PM |
9.9 |
6.7 |
32.7 |
21.8 |
2.4 |
5.0 |
<0.10 |
<0.01 |
WSR02 |
26/12/2023 |
Mid-flood |
Sunny |
Moderate |
M |
5 |
12:02:00 PM |
9.8 |
6.8 |
32.8 |
21.8 |
2.4 |
4.0 |
<0.10 |
<0.01 |
WSR02 |
26/12/2023 |
Mid-flood |
Sunny |
Moderate |
M |
5 |
12:02:00 PM |
9.9 |
6.7 |
32.8 |
21.8 |
2.3 |
3.0 |
<0.10 |
<0.01 |
WSR02 |
26/12/2023 |
Mid-flood |
Sunny |
Moderate |
B |
9 |
12:03:00 PM |
9.9 |
6.7 |
32.7 |
21.8 |
2.4 |
6.0 |
<0.10 |
<0.01 |
WSR02 |
26/12/2023 |
Mid-flood |
Sunny |
Moderate |
B |
9 |
12:03:00 PM |
9.9 |
6.9 |
32.9 |
21.8 |
2.5 |
5.0 |
<0.10 |
<0.01 |
WSR03 |
26/12/2023 |
Mid-flood |
Sunny |
Moderate |
S |
1 |
12:43:00 PM |
10.0 |
6.8 |
33.3 |
22.0 |
2.3 |
6.0 |
<0.10 |
<0.01 |
WSR03 |
26/12/2023 |
Mid-flood |
Sunny |
Moderate |
S |
1 |
12:43:00 PM |
10.1 |
6.7 |
33.1 |
22.0 |
2.2 |
3.0 |
<0.10 |
<0.01 |
WSR03 |
26/12/2023 |
Mid-flood |
Sunny |
Moderate |
M |
4 |
12:44:00 PM |
10.1 |
6.7 |
33.1 |
22.0 |
2.4 |
4.0 |
<0.10 |
<0.01 |
WSR03 |
26/12/2023 |
Mid-flood |
Sunny |
Moderate |
M |
4 |
12:44:00 PM |
10.1 |
6.8 |
32.9 |
22.0 |
2.5 |
5.0 |
<0.10 |
<0.01 |
WSR03 |
26/12/2023 |
Mid-flood |
Sunny |
Moderate |
B |
7 |
12:45:00 PM |
10.0 |
6.7 |
33.0 |
22.0 |
2.6 |
7.0 |
<0.10 |
<0.01 |
WSR03 |
26/12/2023 |
Mid-flood |
Sunny |
Moderate |
B |
7 |
12:45:00 PM |
10.1 |
6.8 |
33.1 |
22.0 |
2.5 |
4.0 |
<0.10 |
<0.01 |
WSR04 |
26/12/2023 |
Mid-flood |
Sunny |
Moderate |
S |
1 |
11:40:00 AM |
9.5 |
6.6 |
32.7 |
22.1 |
2.4 |
4.0 |
<0.10 |
<0.01 |
WSR04 |
26/12/2023 |
Mid-flood |
Sunny |
Moderate |
S |
1 |
11:40:00 AM |
9.5 |
6.7 |
32.5 |
22.2 |
2.3 |
6.0 |
<0.10 |
<0.01 |
WSR04 |
26/12/2023 |
Mid-flood |
Sunny |
Moderate |
M |
4 |
11:41:00 AM |
9.4 |
6.6 |
32.5 |
22.2 |
2.3 |
4.0 |
<0.10 |
<0.01 |
WSR04 |
26/12/2023 |
Mid-flood |
Sunny |
Moderate |
M |
4 |
11:41:00 AM |
9.3 |
6.6 |
32.8 |
22.2 |
2.4 |
4.0 |
<0.10 |
<0.01 |
WSR04 |
26/12/2023 |
Mid-flood |
Sunny |
Moderate |
B |
6 |
11:42:00 AM |
9.2 |
6.7 |
32.8 |
22.2 |
2.5 |
4.0 |
<0.10 |
<0.01 |
WSR04 |
26/12/2023 |
Mid-flood |
Sunny |
Moderate |
B |
6 |
11:42:00 AM |
9.3 |
6.7 |
32.7 |
22.2 |
2.5 |
4.0 |
<0.10 |
<0.01 |
Location Date Tidal Weather Sea Condition Water Level Depth (m) Time DO (mg/L) pH Sal (ppt) Temp (°C) Turbidty (NTU) SS (mg/L) Iron (mg/L) Total Chlorine
WSR16 |
26/12/2023 |
Mid-flood |
Sunny |
Moderate |
S |
1 |
10:53:00 AM |
10.4 |
6.6 |
33.2 |
22.0 |
2.1 |
5.0 |
<0.10 |
<0.01 |
WSR16 |
26/12/2023 |
Mid-flood |
Sunny |
Moderate |
S |
1 |
10:53:00 AM |
10.3 |
6.8 |
32.9 |
22.1 |
2.1 |
5.0 |
<0.10 |
<0.01 |
WSR16 |
26/12/2023 |
Mid-flood |
Sunny |
Moderate |
M |
8 |
10:54:00 AM |
10.2 |
6.7 |
33.0 |
22.1 |
2.2 |
4.0 |
<0.10 |
<0.01 |
WSR16 |
26/12/2023 |
Mid-flood |
Sunny |
Moderate |
M |
8 |
10:54:00 AM |
10.3 |
6.7 |
33.0 |
22.0 |
2.2 |
4.0 |
<0.10 |
<0.01 |
WSR16 |
26/12/2023 |
Mid-flood |
Sunny |
Moderate |
B |
14 |
10:55:00 AM |
10.4 |
6.7 |
33.1 |
22.1 |
2.1 |
4.0 |
<0.10 |
<0.01 |
WSR16 |
26/12/2023 |
Mid-flood |
Sunny |
Moderate |
B |
14 |
10:55:00 AM |
10.4 |
6.7 |
33.1 |
22.1 |
2.2 |
3.0 |
<0.10 |
<0.01 |
WSR33 |
26/12/2023 |
Mid-flood |
Sunny |
Moderate |
S |
1 |
12:11:00 PM |
9.1 |
6.8 |
32.3 |
22.1 |
2.1 |
4.0 |
<0.10 |
<0.01 |
WSR33 |
26/12/2023 |
Mid-flood |
Sunny |
Moderate |
S |
1 |
12:11:00 PM |
9.2 |
6.8 |
32.4 |
22.2 |
2.0 |
5.0 |
<0.10 |
<0.01 |
WSR33 |
26/12/2023 |
Mid-flood |
Sunny |
Moderate |
M |
4 |
12:12:00 PM |
9.1 |
6.8 |
32.4 |
22.2 |
2.1 |
3.0 |
<0.10 |
<0.01 |
WSR33 |
26/12/2023 |
Mid-flood |
Sunny |
Moderate |
M |
4 |
12:12:00 PM |
8.9 |
6.9 |
32.4 |
22.1 |
2.2 |
5.0 |
<0.10 |
<0.01 |
WSR33 |
26/12/2023 |
Mid-flood |
Sunny |
Moderate |
B |
7 |
12:13:00 PM |
9.1 |
6.8 |
32.6 |
22.2 |
2.0 |
5.0 |
<0.10 |
<0.01 |
WSR33 |
26/12/2023 |
Mid-flood |
Sunny |
Moderate |
B |
7 |
12:13:00 PM |
9.2 |
6.8 |
32.6 |
22.2 |
2.1 |
3.0 |
<0.10 |
<0.01 |
WSR36 |
26/12/2023 |
Mid-flood |
Sunny |
Moderate |
S |
1 |
11:53:00 AM |
9.6 |
6.8 |
32.9 |
21.9 |
2.3 |
4.0 |
<0.10 |
<0.01 |
WSR36 |
26/12/2023 |
Mid-flood |
Sunny |
Moderate |
S |
1 |
11:53:00 AM |
9.5 |
6.8 |
33.0 |
21.8 |
2.5 |
3.0 |
<0.10 |
<0.01 |
WSR36 |
26/12/2023 |
Mid-flood |
Sunny |
Moderate |
M |
4 |
11:54:00 AM |
9.5 |
6.8 |
33.0 |
21.8 |
2.4 |
3.0 |
<0.10 |
<0.01 |
WSR36 |
26/12/2023 |
Mid-flood |
Sunny |
Moderate |
M |
4 |
11:54:00 AM |
9.4 |
6.7 |
33.1 |
21.9 |
2.3 |
3.0 |
<0.10 |
<0.01 |
WSR36 |
26/12/2023 |
Mid-flood |
Sunny |
Moderate |
B |
7 |
11:54:00 AM |
9.5 |
6.7 |
33.0 |
21.8 |
2.4 |
4.0 |
<0.10 |
<0.01 |
WSR36 |
26/12/2023 |
Mid-flood |
Sunny |
Moderate |
B |
7 |
11:54:00 AM |
9.6 |
6.8 |
32.7 |
21.8 |
2.4 |
3.0 |
<0.10 |
<0.01 |
WSR37 |
26/12/2023 |
Mid-flood |
Sunny |
Moderate |
S |
1 |
11:47:00 AM |
9.3 |
6.8 |
32.1 |
22.1 |
1.8 |
3.0 |
<0.10 |
<0.01 |
WSR37 |
26/12/2023 |
Mid-flood |
Sunny |
Moderate |
S |
1 |
11:47:00 AM |
9.2 |
6.7 |
32.3 |
22.0 |
1.8 |
3.0 |
<0.10 |
<0.01 |
WSR37 |
26/12/2023 |
Mid-flood |
Sunny |
Moderate |
M |
4 |
11:48:00 AM |
9.3 |
6.8 |
32.4 |
22.1 |
1.8 |
2.5 |
<0.10 |
<0.01 |
WSR37 |
26/12/2023 |
Mid-flood |
Sunny |
Moderate |
M |
4 |
11:48:00 AM |
9.3 |
6.7 |
32.1 |
22.1 |
1.8 |
3.0 |
<0.10 |
<0.01 |
WSR37 |
26/12/2023 |
Mid-flood |
Sunny |
Moderate |
B |
8 |
11:49:00 AM |
9.2 |
6.7 |
32.1 |
22.1 |
1.8 |
3.0 |
<0.10 |
<0.01 |
WSR37 |
26/12/2023 |
Mid-flood |
Sunny |
Moderate |
B |
8 |
11:49:00 AM |
9.1 |
6.7 |
32.2 |
22.1 |
1.9 |
4.0 |
<0.10 |
<0.01 |
NF1 |
26/12/2023 |
Mid-flood |
Sunny |
Moderate |
S |
1 |
11:17:00 AM |
9.1 |
6.7 |
33.6 |
21.9 |
2.2 |
4.0 |
<0.10 |
<0.01 |
NF1 |
26/12/2023 |
Mid-flood |
Sunny |
Moderate |
S |
1 |
11:17:00 AM |
9.0 |
6.8 |
33.5 |
21.8 |
2.3 |
6.0 |
<0.10 |
<0.01 |
NF1 |
26/12/2023 |
Mid-flood |
Sunny |
Moderate |
M |
7 |
11:18:00 AM |
9.2 |
6.7 |
33.3 |
21.9 |
2.1 |
4.0 |
<0.10 |
<0.01 |
NF1 |
26/12/2023 |
Mid-flood |
Sunny |
Moderate |
M |
7 |
11:18:00 AM |
9.2 |
6.7 |
33.5 |
21.9 |
2.2 |
6.0 |
<0.10 |
<0.01 |
NF1 |
26/12/2023 |
Mid-flood |
Sunny |
Moderate |
B |
12 |
11:19:00 AM |
9.0 |
6.7 |
33.4 |
21.9 |
2.2 |
4.0 |
<0.10 |
<0.01 |
NF1 |
26/12/2023 |
Mid-flood |
Sunny |
Moderate |
B |
12 |
11:19:00 AM |
9.0 |
6.7 |
33.6 |
21.9 |
2.1 |
5.0 |
<0.10 |
<0.01 |
NF2 |
26/12/2023 |
Mid-flood |
Sunny |
Moderate |
S |
1 |
11:34:00 AM |
9.8 |
6.7 |
33.5 |
22.0 |
2.1 |
4.0 |
<0.10 |
<0.01 |
NF2 |
26/12/2023 |
Mid-flood |
Sunny |
Moderate |
S |
1 |
11:34:00 AM |
10.0 |
6.8 |
33.5 |
22.0 |
2.2 |
4.0 |
<0.10 |
<0.01 |
NF2 |
26/12/2023 |
Mid-flood |
Sunny |
Moderate |
M |
5 |
11:35:00 AM |
9.9 |
6.8 |
33.4 |
22.0 |
2.2 |
4.0 |
<0.10 |
<0.01 |
NF2 |
26/12/2023 |
Mid-flood |
Sunny |
Moderate |
M |
5 |
11:35:00 AM |
10.1 |
6.7 |
33.4 |
22.0 |
2.2 |
4.0 |
<0.10 |
<0.01 |
NF2 |
26/12/2023 |
Mid-flood |
Sunny |
Moderate |
B |
10 |
11:36:00 AM |
10.1 |
6.8 |
33.3 |
22.0 |
2.3 |
4.0 |
<0.10 |
<0.01 |
NF2 |
26/12/2023 |
Mid-flood |
Sunny |
Moderate |
B |
10 |
11:36:00 AM |
10.1 |
6.8 |
33.2 |
22.1 |
2.1 |
7.0 |
<0.10 |
<0.01 |
Location Date Tidal Weather Sea Condition Water Level Depth (m) Time DO (mg/L) pH Sal (ppt) Temp (°C) Turbidty (NTU) SS (mg/L) Iron (mg/L) Total Chlorine
NF3 |
26/12/2023 |
Mid-flood |
Sunny |
Moderate |
S |
1 |
11:40:00 AM |
9.1 |
6.7 |
33.2 |
22.1 |
2.4 |
5.0 |
<0.10 |
<0.01 |
NF3 |
26/12/2023 |
Mid-flood |
Sunny |
Moderate |
S |
1 |
11:40:00 AM |
9.2 |
6.8 |
33.5 |
22.1 |
2.3 |
5.0 |
<0.10 |
<0.01 |
NF3 |
26/12/2023 |
Mid-flood |
Sunny |
Moderate |
M |
6 |
11:41:00 AM |
9.3 |
6.8 |
33.3 |
22.2 |
2.3 |
5.0 |
<0.10 |
<0.01 |
NF3 |
26/12/2023 |
Mid-flood |
Sunny |
Moderate |
M |
6 |
11:41:00 AM |
9.2 |
6.7 |
33.2 |
22.1 |
2.4 |
3.0 |
<0.10 |
<0.01 |
NF3 |
26/12/2023 |
Mid-flood |
Sunny |
Moderate |
B |
11 |
11:42:00 AM |
9.2 |
6.8 |
33.3 |
22.2 |
2.3 |
4.0 |
<0.10 |
<0.01 |
NF3 |
26/12/2023 |
Mid-flood |
Sunny |
Moderate |
B |
11 |
11:42:00 AM |
9.2 |
6.8 |
33.2 |
22.1 |
2.3 |
4.0 |
<0.10 |
<0.01 |
CE |
28/12/2023 |
Mid-flood |
Sunny |
Moderate |
S |
1 |
11:11:00 AM |
10.1 |
7.5 |
32.3 |
21.9 |
2.5 |
4.0 |
<0.10 |
<0.01 |
CE |
28/12/2023 |
Mid-flood |
Sunny |
Moderate |
S |
1 |
11:11:00 AM |
9.9 |
7.5 |
32.1 |
22.0 |
2.6 |
3.0 |
<0.10 |
<0.01 |
CE |
28/12/2023 |
Mid-flood |
Sunny |
Moderate |
M |
10 |
11:12:00 AM |
9.9 |
7.5 |
32.5 |
21.9 |
2.5 |
3.0 |
<0.10 |
<0.01 |
CE |
28/12/2023 |
Mid-flood |
Sunny |
Moderate |
M |
10 |
11:12:00 AM |
9.8 |
7.4 |
32.3 |
21.9 |
2.6 |
5.0 |
<0.10 |
<0.01 |
CE |
28/12/2023 |
Mid-flood |
Sunny |
Moderate |
B |
19 |
11:13:00 AM |
10.0 |
7.5 |
32.2 |
22.0 |
2.5 |
5.0 |
<0.10 |
<0.01 |
CE |
28/12/2023 |
Mid-flood |
Sunny |
Moderate |
B |
19 |
11:13:00 AM |
10.1 |
7.4 |
32.4 |
21.9 |
2.6 |
5.0 |
<0.10 |
<0.01 |
CF |
28/12/2023 |
Mid-flood |
Sunny |
Moderate |
S |
1 |
8:00:00 AM |
9.6 |
7.3 |
32.4 |
22.0 |
3.5 |
4.0 |
<0.10 |
<0.01 |
CF |
28/12/2023 |
Mid-flood |
Sunny |
Moderate |
S |
1 |
8:00:00 AM |
9.3 |
7.2 |
32.5 |
22.0 |
3.5 |
5.0 |
<0.10 |
<0.01 |
CF |
28/12/2023 |
Mid-flood |
Sunny |
Moderate |
M |
10 |
8:01:00 AM |
9.5 |
7.3 |
32.5 |
22.0 |
3.5 |
4.0 |
<0.10 |
<0.01 |
CF |
28/12/2023 |
Mid-flood |
Sunny |
Moderate |
M |
10 |
8:01:00 AM |
9.6 |
7.2 |
32.4 |
22.0 |
3.4 |
3.0 |
<0.10 |
<0.01 |
CF |
28/12/2023 |
Mid-flood |
Sunny |
Moderate |
B |
19 |
8:02:00 AM |
9.6 |
7.3 |
32.7 |
22.1 |
2.6 |
4.0 |
<0.10 |
<0.01 |
CF |
28/12/2023 |
Mid-flood |
Sunny |
Moderate |
B |
19 |
8:02:00 AM |
9.3 |
7.3 |
32.4 |
22.1 |
2.5 |
4.0 |
<0.10 |
<0.01 |
WSR01 |
28/12/2023 |
Mid-flood |
Sunny |
Moderate |
S |
1 |
8:24:00 AM |
10.3 |
7.3 |
32.4 |
22.2 |
1.7 |
5.0 |
<0.10 |
<0.01 |
WSR01 |
28/12/2023 |
Mid-flood |
Sunny |
Moderate |
S |
1 |
8:24:00 AM |
10.2 |
7.4 |
32.3 |
22.1 |
1.8 |
4.0 |
<0.10 |
<0.01 |
WSR01 |
28/12/2023 |
Mid-flood |
Sunny |
Moderate |
M |
5 |
8:25:00 AM |
10.2 |
7.3 |
32.3 |
22.1 |
1.8 |
5.0 |
<0.10 |
<0.01 |
WSR01 |
28/12/2023 |
Mid-flood |
Sunny |
Moderate |
M |
5 |
8:25:00 AM |
10.3 |
7.3 |
32.6 |
22.1 |
1.9 |
4.0 |
<0.10 |
<0.01 |
WSR01 |
28/12/2023 |
Mid-flood |
Sunny |
Moderate |
B |
8 |
8:26:00 AM |
10.3 |
7.4 |
32.4 |
22.1 |
1.7 |
3.0 |
<0.10 |
<0.01 |
WSR01 |
28/12/2023 |
Mid-flood |
Sunny |
Moderate |
B |
8 |
8:26:00 AM |
10.3 |
7.3 |
32.3 |
22.1 |
1.8 |
4.0 |
<0.10 |
<0.01 |
WSR02 |
28/12/2023 |
Mid-flood |
Sunny |
Moderate |
S |
1 |
8:45:00 AM |
9.7 |
7.3 |
33.5 |
22.1 |
2.4 |
4.0 |
<0.10 |
<0.01 |
WSR02 |
28/12/2023 |
Mid-flood |
Sunny |
Moderate |
S |
1 |
8:45:00 AM |
9.6 |
7.3 |
33.3 |
22.0 |
2.4 |
4.0 |
<0.10 |
<0.01 |
WSR02 |
28/12/2023 |
Mid-flood |
Sunny |
Moderate |
M |
5 |
8:46:00 AM |
9.8 |
7.3 |
33.3 |
22.0 |
2.4 |
5.0 |
<0.10 |
<0.01 |
WSR02 |
28/12/2023 |
Mid-flood |
Sunny |
Moderate |
M |
5 |
8:46:00 AM |
9.6 |
7.3 |
33.2 |
22.0 |
2.4 |
7.0 |
<0.10 |
<0.01 |
WSR02 |
28/12/2023 |
Mid-flood |
Sunny |
Moderate |
B |
8 |
8:47:00 AM |
9.7 |
7.3 |
33.3 |
22.0 |
2.4 |
4.0 |
<0.10 |
<0.01 |
WSR02 |
28/12/2023 |
Mid-flood |
Sunny |
Moderate |
B |
8 |
8:47:00 AM |
9.7 |
7.3 |
33.2 |
22.0 |
2.4 |
3.0 |
<0.10 |
<0.01 |
WSR03 |
28/12/2023 |
Mid-flood |
Sunny |
Moderate |
S |
1 |
9:01:00 AM |
9.7 |
7.4 |
33.1 |
22.1 |
2.2 |
6.0 |
<0.10 |
<0.01 |
WSR03 |
28/12/2023 |
Mid-flood |
Sunny |
Moderate |
S |
1 |
9:01:00 AM |
9.8 |
7.3 |
33.0 |
22.2 |
2.4 |
5.0 |
<0.10 |
<0.01 |
WSR03 |
28/12/2023 |
Mid-flood |
Sunny |
Moderate |
M |
4 |
9:02:00 AM |
9.6 |
7.3 |
33.1 |
22.2 |
2.4 |
6.0 |
<0.10 |
<0.01 |
WSR03 |
28/12/2023 |
Mid-flood |
Sunny |
Moderate |
M |
4 |
9:02:00 AM |
9.7 |
7.3 |
33.3 |
22.2 |
2.4 |
4.0 |
<0.10 |
<0.01 |
WSR03 |
28/12/2023 |
Mid-flood |
Sunny |
Moderate |
B |
8 |
9:03:00 AM |
9.7 |
7.4 |
33.1 |
22.2 |
2.5 |
3.0 |
<0.10 |
<0.01 |
WSR03 |
28/12/2023 |
Mid-flood |
Sunny |
Moderate |
B |
8 |
9:03:00 AM |
9.6 |
7.4 |
33.0 |
22.2 |
2.5 |
5.0 |
<0.10 |
<0.01 |
Location Date Tidal Weather Sea Condition Water Level Depth (m) Time DO (mg/L) pH Sal (ppt) Temp (°C) Turbidty (NTU) SS (mg/L) Iron (mg/L) Total Chlorine
WSR04 |
28/12/2023 |
Mid-flood |
Sunny |
Moderate |
S |
1 |
9:15:00 AM |
10.4 |
7.3 |
33.3 |
22.0 |
2.2 |
4.0 |
<0.10 |
<0.01 |
WSR04 |
28/12/2023 |
Mid-flood |
Sunny |
Moderate |
S |
1 |
9:15:00 AM |
10.5 |
7.2 |
33.2 |
22.0 |
2.0 |
5.0 |
<0.10 |
<0.01 |
WSR04 |
28/12/2023 |
Mid-flood |
Sunny |
Moderate |
M |
4 |
9:16:00 AM |
10.3 |
7.3 |
33.1 |
22.1 |
2.0 |
4.0 |
<0.10 |
<0.01 |
WSR04 |
28/12/2023 |
Mid-flood |
Sunny |
Moderate |
M |
4 |
9:16:00 AM |
10.3 |
7.3 |
33.0 |
22.0 |
2.0 |
4.0 |
<0.10 |
<0.01 |
WSR04 |
28/12/2023 |
Mid-flood |
Sunny |
Moderate |
B |
6 |
9:17:00 AM |
10.4 |
7.3 |
33.3 |
22.0 |
2.1 |
4.0 |
<0.10 |
<0.01 |
WSR04 |
28/12/2023 |
Mid-flood |
Sunny |
Moderate |
B |
6 |
9:17:00 AM |
10.2 |
7.3 |
33.3 |
22.0 |
2.0 |
4.0 |
<0.10 |
<0.01 |
WSR16 |
28/12/2023 |
Mid-flood |
Sunny |
Moderate |
S |
1 |
10:50:00 AM |
9.7 |
7.4 |
33.4 |
22.2 |
2.3 |
3.0 |
<0.10 |
<0.01 |
WSR16 |
28/12/2023 |
Mid-flood |
Sunny |
Moderate |
S |
1 |
10:50:00 AM |
10.0 |
7.4 |
33.1 |
22.2 |
2.4 |
5.0 |
<0.10 |
<0.01 |
WSR16 |
28/12/2023 |
Mid-flood |
Sunny |
Moderate |
M |
8 |
10:51:00 AM |
9.8 |
7.4 |
33.1 |
22.2 |
2.4 |
7.0 |
<0.10 |
<0.01 |
WSR16 |
28/12/2023 |
Mid-flood |
Sunny |
Moderate |
M |
8 |
10:51:00 AM |
9.9 |
7.4 |
33.2 |
22.2 |
2.4 |
4.0 |
<0.10 |
<0.01 |
WSR16 |
28/12/2023 |
Mid-flood |
Sunny |
Moderate |
B |
15 |
10:52:00 AM |
9.7 |
7.4 |
33.3 |
22.2 |
2.5 |
8.0 |
<0.10 |
<0.01 |
WSR16 |
28/12/2023 |
Mid-flood |
Sunny |
Moderate |
B |
15 |
10:52:00 AM |
9.9 |
7.4 |
33.4 |
22.2 |
2.5 |
4.0 |
<0.10 |
<0.01 |
WSR33 |
28/12/2023 |
Mid-flood |
Sunny |
Moderate |
S |
1 |
9:32:00 AM |
10.0 |
7.3 |
32.8 |
22.1 |
2.2 |
4.0 |
<0.10 |
<0.01 |
WSR33 |
28/12/2023 |
Mid-flood |
Sunny |
Moderate |
S |
1 |
9:32:00 AM |
9.9 |
7.3 |
32.7 |
22.1 |
2.2 |
4.0 |
<0.10 |
<0.01 |
WSR33 |
28/12/2023 |
Mid-flood |
Sunny |
Moderate |
M |
4 |
9:33:00 AM |
10.0 |
7.3 |
32.7 |
22.1 |
2.3 |
4.0 |
<0.10 |
<0.01 |
WSR33 |
28/12/2023 |
Mid-flood |
Sunny |
Moderate |
M |
4 |
9:33:00 AM |
9.8 |
7.3 |
33.0 |
22.0 |
2.3 |
4.0 |
<0.10 |
<0.01 |
WSR33 |
28/12/2023 |
Mid-flood |
Sunny |
Moderate |
B |
6 |
9:34:00 AM |
9.8 |
7.3 |
33.0 |
22.1 |
2.4 |
3.0 |
<0.10 |
<0.01 |
WSR33 |
28/12/2023 |
Mid-flood |
Sunny |
Moderate |
B |
6 |
9:34:00 AM |
9.8 |
7.3 |
32.7 |
22.1 |
2.5 |
5.0 |
<0.10 |
<0.01 |
WSR36 |
28/12/2023 |
Mid-flood |
Sunny |
Moderate |
S |
1 |
9:37:00 AM |
9.9 |
7.4 |
33.5 |
22.1 |
2.4 |
4.0 |
<0.10 |
<0.01 |
WSR36 |
28/12/2023 |
Mid-flood |
Sunny |
Moderate |
S |
1 |
9:37:00 AM |
9.8 |
7.5 |
33.2 |
22.1 |
2.4 |
6.0 |
<0.10 |
<0.01 |
WSR36 |
28/12/2023 |
Mid-flood |
Sunny |
Moderate |
M |
3 |
9:38:00 AM |
9.9 |
7.4 |
33.3 |
22.1 |
2.3 |
4.0 |
<0.10 |
<0.01 |
WSR36 |
28/12/2023 |
Mid-flood |
Sunny |
Moderate |
M |
3 |
9:38:00 AM |
9.9 |
7.4 |
33.2 |
22.1 |
2.5 |
4.0 |
<0.10 |
<0.01 |
WSR36 |
28/12/2023 |
Mid-flood |
Sunny |
Moderate |
B |
6 |
9:38:00 AM |
9.9 |
7.4 |
33.3 |
22.0 |
2.4 |
5.0 |
<0.10 |
<0.01 |
WSR36 |
28/12/2023 |
Mid-flood |
Sunny |
Moderate |
B |
6 |
9:38:00 AM |
9.9 |
7.4 |
33.2 |
22.0 |
2.4 |
5.0 |
<0.10 |
<0.01 |
WSR37 |
28/12/2023 |
Mid-flood |
Sunny |
Moderate |
S |
1 |
11:11:00 AM |
10.3 |
7.2 |
33.5 |
22.0 |
2.3 |
4.0 |
<0.10 |
<0.01 |
WSR37 |
28/12/2023 |
Mid-flood |
Sunny |
Moderate |
S |
1 |
11:11:00 AM |
10.3 |
7.2 |
33.5 |
22.0 |
2.3 |
4.0 |
<0.10 |
<0.01 |
WSR37 |
28/12/2023 |
Mid-flood |
Sunny |
Moderate |
M |
4 |
11:12:00 AM |
10.3 |
7.3 |
33.6 |
22.0 |
2.5 |
4.0 |
<0.10 |
<0.01 |
WSR37 |
28/12/2023 |
Mid-flood |
Sunny |
Moderate |
M |
4 |
11:12:00 AM |
10.1 |
7.3 |
33.5 |
22.0 |
2.4 |
4.0 |
<0.10 |
<0.01 |
WSR37 |
28/12/2023 |
Mid-flood |
Sunny |
Moderate |
B |
8 |
11:13:00 AM |
10.2 |
7.2 |
33.7 |
22.0 |
2.5 |
4.0 |
<0.10 |
<0.01 |
WSR37 |
28/12/2023 |
Mid-flood |
Sunny |
Moderate |
B |
8 |
11:13:00 AM |
10.2 |
7.2 |
33.8 |
22.1 |
2.5 |
5.0 |
<0.10 |
<0.01 |
NF1 |
28/12/2023 |
Mid-flood |
Sunny |
Moderate |
S |
1 |
8:24:00 AM |
9.8 |
7.2 |
33.5 |
22.1 |
2.4 |
8.0 |
<0.10 |
<0.01 |
NF1 |
28/12/2023 |
Mid-flood |
Sunny |
Moderate |
S |
1 |
8:24:00 AM |
9.6 |
7.3 |
33.2 |
22.2 |
2.3 |
7.0 |
<0.10 |
<0.01 |
NF1 |
28/12/2023 |
Mid-flood |
Sunny |
Moderate |
M |
7 |
8:25:00 AM |
9.8 |
7.3 |
33.3 |
22.1 |
2.3 |
7.0 |
<0.10 |
<0.01 |
NF1 |
28/12/2023 |
Mid-flood |
Sunny |
Moderate |
M |
7 |
8:25:00 AM |
9.7 |
7.2 |
33.4 |
22.1 |
2.4 |
6.0 |
<0.10 |
<0.01 |
NF1 |
28/12/2023 |
Mid-flood |
Sunny |
Moderate |
B |
13 |
8:26:00 AM |
9.8 |
7.3 |
33.4 |
22.1 |
2.4 |
4.0 |
<0.10 |
<0.01 |
NF1 |
28/12/2023 |
Mid-flood |
Sunny |
Moderate |
B |
13 |
8:26:00 AM |
9.7 |
7.2 |
33.3 |
22.1 |
2.4 |
5.0 |
<0.10 |
<0.01 |
Location Date Tidal Weather Sea Condition Water Level Depth (m) Time DO (mg/L) pH Sal (ppt) Temp (°C) Turbidty (NTU) SS (mg/L) Iron (mg/L) Total Chlorine
NF2 |
28/12/2023 |
Mid-flood |
Sunny |
Moderate |
S |
1 |
8:45:00 AM |
9.9 |
7.3 |
33.1 |
21.8 |
1.4 |
5.0 |
<0.10 |
<0.01 |
NF2 |
28/12/2023 |
Mid-flood |
Sunny |
Moderate |
S |
1 |
8:45:00 AM |
10.1 |
7.3 |
32.9 |
21.8 |
1.3 |
5.0 |
<0.10 |
<0.01 |
NF2 |
28/12/2023 |
Mid-flood |
Sunny |
Moderate |
M |
5 |
8:46:00 AM |
10.1 |
7.3 |
33.0 |
21.9 |
1.5 |
5.0 |
<0.10 |
<0.01 |
NF2 |
28/12/2023 |
Mid-flood |
Sunny |
Moderate |
M |
5 |
8:46:00 AM |
9.9 |
7.3 |
32.9 |
21.8 |
1.4 |
6.0 |
<0.10 |
<0.01 |
NF2 |
28/12/2023 |
Mid-flood |
Sunny |
Moderate |
B |
10 |
8:47:00 AM |
10.0 |
7.3 |
32.9 |
21.9 |
1.4 |
6.0 |
<0.10 |
<0.01 |
NF2 |
28/12/2023 |
Mid-flood |
Sunny |
Moderate |
B |
10 |
8:47:00 AM |
10.0 |
7.3 |
32.9 |
21.8 |
1.5 |
4.0 |
<0.10 |
<0.01 |
NF3 |
28/12/2023 |
Mid-flood |
Sunny |
Moderate |
S |
1 |
10:31:00 AM |
9.2 |
7.4 |
32.4 |
22.0 |
1.4 |
5.0 |
<0.10 |
<0.01 |
NF3 |
28/12/2023 |
Mid-flood |
Sunny |
Moderate |
S |
1 |
10:31:00 AM |
9.2 |
7.4 |
32.8 |
21.9 |
1.4 |
5.0 |
<0.10 |
<0.01 |
NF3 |
28/12/2023 |
Mid-flood |
Sunny |
Moderate |
M |
6 |
10:32:00 AM |
9.1 |
7.4 |
32.5 |
21.9 |
1.4 |
4.0 |
<0.10 |
<0.01 |
NF3 |
28/12/2023 |
Mid-flood |
Sunny |
Moderate |
M |
6 |
10:32:00 AM |
9.2 |
7.4 |
32.5 |
21.9 |
1.3 |
4.0 |
<0.10 |
<0.01 |
NF3 |
28/12/2023 |
Mid-flood |
Sunny |
Moderate |
B |
11 |
10:33:00 AM |
9.1 |
7.4 |
32.6 |
22.0 |
1.3 |
6.0 |
<0.10 |
<0.01 |
NF3 |
28/12/2023 |
Mid-flood |
Sunny |
Moderate |
B |
11 |
10:33:00 AM |
8.9 |
7.4 |
32.4 |
21.9 |
1.4 |
8.0 |
<0.10 |
<0.01 |
CE |
30/12/2023 |
Mid-flood |
Sunny |
Moderate |
S |
1 |
11:19:00 AM |
8.5 |
7.2 |
33.8 |
22.4 |
2.3 |
3.0 |
<0.10 |
<0.01 |
CE |
30/12/2023 |
Mid-flood |
Sunny |
Moderate |
S |
1 |
11:19:00 AM |
8.6 |
7.3 |
33.8 |
22.4 |
2.2 |
4.0 |
<0.10 |
<0.01 |
CE |
30/12/2023 |
Mid-flood |
Sunny |
Moderate |
M |
12 |
11:20:00 AM |
8.6 |
7.1 |
33.7 |
22.3 |
2.3 |
3.0 |
<0.10 |
<0.01 |
CE |
30/12/2023 |
Mid-flood |
Sunny |
Moderate |
M |
12 |
11:20:00 AM |
8.5 |
7.2 |
33.8 |
22.4 |
2.2 |
3.0 |
<0.10 |
<0.01 |
CE |
30/12/2023 |
Mid-flood |
Sunny |
Moderate |
B |
24 |
11:21:00 AM |
8.4 |
7.1 |
33.8 |
22.4 |
2.3 |
4.0 |
<0.10 |
<0.01 |
CE |
30/12/2023 |
Mid-flood |
Sunny |
Moderate |
B |
24 |
11:21:00 AM |
8.6 |
7.2 |
33.7 |
22.3 |
2.2 |
4.0 |
<0.10 |
<0.01 |
CF |
30/12/2023 |
Mid-flood |
Sunny |
Moderate |
S |
1 |
8:08:00 AM |
9.6 |
7.2 |
33.6 |
22.5 |
3.5 |
4.0 |
<0.10 |
<0.01 |
CF |
30/12/2023 |
Mid-flood |
Sunny |
Moderate |
S |
1 |
8:08:00 AM |
9.5 |
7.2 |
33.6 |
22.5 |
3.5 |
3.0 |
<0.10 |
<0.01 |
CF |
30/12/2023 |
Mid-flood |
Sunny |
Moderate |
M |
11 |
8:09:00 AM |
9.4 |
7.3 |
33.5 |
22.5 |
3.5 |
3.0 |
<0.10 |
<0.01 |
CF |
30/12/2023 |
Mid-flood |
Sunny |
Moderate |
M |
11 |
8:09:00 AM |
9.5 |
7.2 |
33.6 |
22.5 |
3.5 |
3.0 |
<0.10 |
<0.01 |
CF |
30/12/2023 |
Mid-flood |
Sunny |
Moderate |
B |
20 |
8:10:00 AM |
9.5 |
7.2 |
33.6 |
22.6 |
3.4 |
5.0 |
<0.10 |
<0.01 |
CF |
30/12/2023 |
Mid-flood |
Sunny |
Moderate |
B |
20 |
8:10:00 AM |
9.6 |
7.2 |
33.6 |
22.5 |
3.5 |
4.0 |
<0.10 |
<0.01 |
WSR01 |
30/12/2023 |
Mid-flood |
Sunny |
Moderate |
S |
1 |
8:34:00 AM |
8.4 |
7.4 |
33.1 |
22.7 |
2.4 |
3.0 |
<0.10 |
<0.01 |
WSR01 |
30/12/2023 |
Mid-flood |
Sunny |
Moderate |
S |
1 |
8:34:00 AM |
8.5 |
7.4 |
33.0 |
22.8 |
2.3 |
3.0 |
<0.10 |
<0.01 |
WSR01 |
30/12/2023 |
Mid-flood |
Sunny |
Moderate |
M |
4 |
8:35:00 AM |
8.4 |
7.4 |
33.1 |
22.8 |
2.4 |
5.0 |
<0.10 |
<0.01 |
WSR01 |
30/12/2023 |
Mid-flood |
Sunny |
Moderate |
M |
4 |
8:35:00 AM |
8.5 |
7.3 |
33.0 |
22.7 |
2.5 |
4.0 |
<0.10 |
<0.01 |
WSR01 |
30/12/2023 |
Mid-flood |
Sunny |
Moderate |
B |
8 |
8:36:00 AM |
8.4 |
7.3 |
33.1 |
22.7 |
2.5 |
3.0 |
<0.10 |
<0.01 |
WSR01 |
30/12/2023 |
Mid-flood |
Sunny |
Moderate |
B |
8 |
8:36:00 AM |
8.6 |
7.4 |
33.0 |
22.7 |
2.4 |
3.0 |
<0.10 |
<0.01 |
WSR02 |
30/12/2023 |
Mid-flood |
Sunny |
Moderate |
S |
1 |
8:54:00 AM |
8.7 |
7.3 |
33.6 |
22.8 |
2.3 |
5.0 |
<0.10 |
<0.01 |
WSR02 |
30/12/2023 |
Mid-flood |
Sunny |
Moderate |
S |
1 |
8:54:00 AM |
8.7 |
7.3 |
33.7 |
22.8 |
2.3 |
3.0 |
<0.10 |
<0.01 |
WSR02 |
30/12/2023 |
Mid-flood |
Sunny |
Moderate |
M |
5 |
8:55:00 AM |
8.6 |
7.3 |
33.7 |
22.7 |
2.3 |
2.5 |
<0.10 |
<0.01 |
WSR02 |
30/12/2023 |
Mid-flood |
Sunny |
Moderate |
M |
5 |
8:55:00 AM |
8.6 |
7.3 |
33.6 |
22.8 |
2.2 |
2.5 |
<0.10 |
<0.01 |
WSR02 |
30/12/2023 |
Mid-flood |
Sunny |
Moderate |
B |
9 |
8:56:00 AM |
8.6 |
7.3 |
33.7 |
22.8 |
2.2 |
5.0 |
<0.10 |
<0.01 |
WSR02 |
30/12/2023 |
Mid-flood |
Sunny |
Moderate |
B |
9 |
8:56:00 AM |
8.7 |
7.2 |
33.6 |
22.7 |
2.3 |
4.0 |
<0.10 |
<0.01 |
Location Date Tidal Weather Sea Condition Water Level Depth (m) Time DO (mg/L) pH Sal (ppt) Temp (°C) Turbidty (NTU) SS (mg/L) Iron (mg/L) Total Chlorine
WSR03 |
30/12/2023 |
Mid-flood |
Sunny |
Moderate |
S |
1 |
9:10:00 AM |
9.3 |
7.2 |
33.3 |
22.6 |
2.4 |
2.5 |
<0.10 |
<0.01 |
WSR03 |
30/12/2023 |
Mid-flood |
Sunny |
Moderate |
S |
1 |
9:10:00 AM |
9.3 |
7.1 |
33.2 |
22.6 |
2.3 |
3.0 |
<0.10 |
<0.01 |
WSR03 |
30/12/2023 |
Mid-flood |
Sunny |
Moderate |
M |
4 |
9:11:00 AM |
9.2 |
7.1 |
33.3 |
22.6 |
2.4 |
2.5 |
<0.10 |
<0.01 |
WSR03 |
30/12/2023 |
Mid-flood |
Sunny |
Moderate |
M |
4 |
9:11:00 AM |
9.2 |
7.2 |
33.3 |
22.5 |
2.4 |
3.0 |
<0.10 |
<0.01 |
WSR03 |
30/12/2023 |
Mid-flood |
Sunny |
Moderate |
B |
7 |
9:12:00 AM |
9.3 |
7.1 |
33.3 |
22.5 |
2.5 |
2.5 |
<0.10 |
<0.01 |
WSR03 |
30/12/2023 |
Mid-flood |
Sunny |
Moderate |
B |
7 |
9:12:00 AM |
9.4 |
7.2 |
33.2 |
22.5 |
2.4 |
2.5 |
<0.10 |
<0.01 |
WSR04 |
30/12/2023 |
Mid-flood |
Sunny |
Moderate |
S |
1 |
9:25:00 AM |
9.1 |
7.1 |
32.9 |
22.7 |
2.3 |
2.5 |
<0.10 |
<0.01 |
WSR04 |
30/12/2023 |
Mid-flood |
Sunny |
Moderate |
S |
1 |
9:25:00 AM |
9.2 |
7.1 |
32.9 |
22.7 |
2.2 |
2.5 |
<0.10 |
<0.01 |
WSR04 |
30/12/2023 |
Mid-flood |
Sunny |
Moderate |
M |
3 |
9:26:00 AM |
9.0 |
7.1 |
32.9 |
22.7 |
2.1 |
4.0 |
<0.10 |
<0.01 |
WSR04 |
30/12/2023 |
Mid-flood |
Sunny |
Moderate |
M |
3 |
9:26:00 AM |
9.1 |
7.1 |
32.9 |
22.7 |
2.1 |
2.5 |
<0.10 |
<0.01 |
WSR04 |
30/12/2023 |
Mid-flood |
Sunny |
Moderate |
B |
6 |
9:27:00 AM |
9.1 |
7.1 |
32.9 |
22.8 |
2.3 |
2.5 |
<0.10 |
<0.01 |
WSR04 |
30/12/2023 |
Mid-flood |
Sunny |
Moderate |
B |
6 |
9:27:00 AM |
9.0 |
7.2 |
32.9 |
22.8 |
2.2 |
3.0 |
<0.10 |
<0.01 |
WSR16 |
30/12/2023 |
Mid-flood |
Sunny |
Moderate |
S |
1 |
10:58:00 AM |
8.9 |
7.4 |
32.4 |
22.7 |
2.4 |
5.0 |
<0.10 |
<0.01 |
WSR16 |
30/12/2023 |
Mid-flood |
Sunny |
Moderate |
S |
1 |
10:58:00 AM |
8.8 |
7.4 |
32.4 |
22.6 |
2.4 |
5.0 |
<0.10 |
<0.01 |
WSR16 |
30/12/2023 |
Mid-flood |
Sunny |
Moderate |
M |
8 |
10:59:00 AM |
8.8 |
7.3 |
32.4 |
22.6 |
2.4 |
4.0 |
<0.10 |
<0.01 |
WSR16 |
30/12/2023 |
Mid-flood |
Sunny |
Moderate |
M |
8 |
10:59:00 AM |
8.8 |
7.3 |
32.5 |
22.6 |
2.3 |
4.0 |
<0.10 |
<0.01 |
WSR16 |
30/12/2023 |
Mid-flood |
Sunny |
Moderate |
B |
15 |
11:00:00 AM |
8.8 |
7.3 |
32.4 |
22.6 |
2.4 |
2.5 |
<0.10 |
<0.01 |
WSR16 |
30/12/2023 |
Mid-flood |
Sunny |
Moderate |
B |
15 |
11:00:00 AM |
8.7 |
7.4 |
32.4 |
22.7 |
2.4 |
2.5 |
<0.10 |
<0.01 |
WSR33 |
30/12/2023 |
Mid-flood |
Sunny |
Moderate |
S |
1 |
9:42:00 AM |
8.3 |
7.3 |
33.6 |
22.7 |
2.3 |
2.5 |
<0.10 |
<0.01 |
WSR33 |
30/12/2023 |
Mid-flood |
Sunny |
Moderate |
S |
1 |
9:42:00 AM |
8.3 |
7.2 |
33.6 |
22.6 |
2.3 |
3.0 |
<0.10 |
<0.01 |
WSR33 |
30/12/2023 |
Mid-flood |
Sunny |
Moderate |
M |
4 |
9:43:00 AM |
8.3 |
7.3 |
33.5 |
22.7 |
2.4 |
2.5 |
<0.10 |
<0.01 |
WSR33 |
30/12/2023 |
Mid-flood |
Sunny |
Moderate |
M |
4 |
9:43:00 AM |
8.4 |
7.3 |
33.5 |
22.6 |
2.3 |
2.5 |
<0.10 |
<0.01 |
WSR33 |
30/12/2023 |
Mid-flood |
Sunny |
Moderate |
B |
7 |
9:44:00 AM |
8.3 |
7.2 |
33.5 |
22.6 |
2.3 |
2.5 |
<0.10 |
<0.01 |
WSR33 |
30/12/2023 |
Mid-flood |
Sunny |
Moderate |
B |
7 |
9:44:00 AM |
8.4 |
7.3 |
33.5 |
22.7 |
2.5 |
2.5 |
<0.10 |
<0.01 |
WSR36 |
30/12/2023 |
Mid-flood |
Sunny |
Moderate |
S |
1 |
9:59:00 AM |
8.4 |
7.3 |
33.1 |
22.6 |
2.2 |
2.5 |
<0.10 |
<0.01 |
WSR36 |
30/12/2023 |
Mid-flood |
Sunny |
Moderate |
S |
1 |
9:59:00 AM |
8.5 |
7.2 |
33.2 |
22.5 |
2.2 |
2.5 |
<0.10 |
<0.01 |
WSR36 |
30/12/2023 |
Mid-flood |
Sunny |
Moderate |
M |
3 |
10:00:00 AM |
8.6 |
7.3 |
33.1 |
22.6 |
2.2 |
2.5 |
<0.10 |
<0.01 |
WSR36 |
30/12/2023 |
Mid-flood |
Sunny |
Moderate |
M |
3 |
10:00:00 AM |
8.5 |
7.2 |
33.2 |
22.5 |
2.3 |
2.5 |
<0.10 |
<0.01 |
WSR36 |
30/12/2023 |
Mid-flood |
Sunny |
Moderate |
B |
6 |
10:00:00 AM |
8.5 |
7.2 |
33.2 |
22.6 |
2.2 |
2.5 |
<0.10 |
<0.01 |
WSR36 |
30/12/2023 |
Mid-flood |
Sunny |
Moderate |
B |
6 |
10:00:00 AM |
8.6 |
7.2 |
33.2 |
22.6 |
2.3 |
2.5 |
<0.10 |
<0.01 |
WSR37 |
30/12/2023 |
Mid-flood |
Sunny |
Moderate |
S |
1 |
10:16:00 AM |
9.5 |
7.3 |
33.7 |
22.4 |
2.2 |
2.5 |
<0.10 |
<0.01 |
WSR37 |
30/12/2023 |
Mid-flood |
Sunny |
Moderate |
S |
1 |
10:16:00 AM |
9.6 |
7.3 |
33.6 |
22.5 |
2.1 |
2.5 |
<0.10 |
<0.01 |
WSR37 |
30/12/2023 |
Mid-flood |
Sunny |
Moderate |
M |
4 |
10:17:00 AM |
9.6 |
7.3 |
33.6 |
22.5 |
2.1 |
2.5 |
<0.10 |
<0.01 |
WSR37 |
30/12/2023 |
Mid-flood |
Sunny |
Moderate |
M |
4 |
10:17:00 AM |
9.5 |
7.2 |
33.6 |
22.5 |
2.1 |
2.5 |
<0.10 |
<0.01 |
WSR37 |
30/12/2023 |
Mid-flood |
Sunny |
Moderate |
B |
8 |
10:18:00 AM |
9.6 |
7.3 |
33.7 |
22.4 |
2.1 |
2.5 |
<0.10 |
<0.01 |
WSR37 |
30/12/2023 |
Mid-flood |
Sunny |
Moderate |
B |
8 |
10:18:00 AM |
9.6 |
7.3 |
33.7 |
22.4 |
2.1 |
2.5 |
<0.10 |
<0.01 |
Location Date Tidal Weather Sea Condition Water Level Depth (m) Time DO (mg/L) pH Sal (ppt) Temp (°C) Turbidty (NTU) SS (mg/L) Iron (mg/L) Total Chlorine
NF1 |
30/12/2023 |
Mid-flood |
Sunny |
Moderate |
S |
1 |
10:52:00 AM |
8.7 |
7.4 |
33.2 |
22.7 |
2.3 |
2.5 |
<0.10 |
<0.01 |
NF1 |
30/12/2023 |
Mid-flood |
Sunny |
Moderate |
S |
1 |
10:52:00 AM |
8.6 |
7.3 |
33.3 |
22.7 |
2.2 |
2.5 |
<0.10 |
<0.01 |
NF1 |
30/12/2023 |
Mid-flood |
Sunny |
Moderate |
M |
7 |
10:53:00 AM |
8.6 |
7.4 |
33.2 |
22.8 |
2.2 |
2.5 |
<0.10 |
<0.01 |
NF1 |
30/12/2023 |
Mid-flood |
Sunny |
Moderate |
M |
7 |
10:53:00 AM |
8.6 |
7.3 |
33.3 |
22.7 |
2.3 |
2.5 |
<0.10 |
<0.01 |
NF1 |
30/12/2023 |
Mid-flood |
Sunny |
Moderate |
B |
12 |
10:54:00 AM |
8.6 |
7.4 |
33.2 |
22.7 |
2.4 |
2.5 |
<0.10 |
<0.01 |
NF1 |
30/12/2023 |
Mid-flood |
Sunny |
Moderate |
B |
12 |
10:54:00 AM |
8.6 |
7.4 |
33.3 |
22.7 |
2.3 |
2.5 |
<0.10 |
<0.01 |
NF2 |
30/12/2023 |
Mid-flood |
Sunny |
Moderate |
S |
1 |
10:47:00 AM |
8.5 |
7.3 |
32.9 |
22.5 |
2.1 |
2.5 |
<0.10 |
<0.01 |
NF2 |
30/12/2023 |
Mid-flood |
Sunny |
Moderate |
S |
1 |
10:47:00 AM |
8.5 |
7.2 |
32.8 |
22.6 |
2.3 |
2.5 |
<0.10 |
<0.01 |
NF2 |
30/12/2023 |
Mid-flood |
Sunny |
Moderate |
M |
5 |
10:48:00 AM |
8.6 |
7.2 |
32.9 |
22.5 |
2.3 |
2.5 |
<0.10 |
<0.01 |
NF2 |
30/12/2023 |
Mid-flood |
Sunny |
Moderate |
M |
5 |
10:48:00 AM |
8.5 |
7.2 |
32.9 |
22.6 |
2.1 |
2.5 |
<0.10 |
<0.01 |
NF2 |
30/12/2023 |
Mid-flood |
Sunny |
Moderate |
B |
10 |
10:49:00 AM |
8.6 |
7.2 |
32.9 |
22.5 |
2.1 |
2.5 |
<0.10 |
<0.01 |
NF2 |
30/12/2023 |
Mid-flood |
Sunny |
Moderate |
B |
10 |
10:49:00 AM |
8.5 |
7.2 |
32.9 |
22.5 |
2.3 |
2.5 |
<0.10 |
<0.01 |
NF3 |
30/12/2023 |
Mid-flood |
Sunny |
Moderate |
S |
1 |
10:41:00 AM |
8.8 |
7.3 |
33.6 |
22.8 |
2.2 |
2.5 |
<0.10 |
<0.01 |
NF3 |
30/12/2023 |
Mid-flood |
Sunny |
Moderate |
S |
1 |
10:41:00 AM |
8.8 |
7.3 |
33.6 |
22.8 |
2.3 |
2.5 |
<0.10 |
<0.01 |
NF3 |
30/12/2023 |
Mid-flood |
Sunny |
Moderate |
M |
6 |
10:42:00 AM |
8.8 |
7.2 |
33.6 |
22.8 |
2.3 |
2.5 |
<0.10 |
<0.01 |
NF3 |
30/12/2023 |
Mid-flood |
Sunny |
Moderate |
M |
6 |
10:42:00 AM |
8.7 |
7.3 |
33.6 |
22.8 |
2.3 |
2.5 |
<0.10 |
<0.01 |
NF3 |
30/12/2023 |
Mid-flood |
Sunny |
Moderate |
B |
11 |
10:43:00 AM |
8.8 |
7.2 |
33.7 |
22.8 |
2.2 |
2.5 |
<0.10 |
<0.01 |
NF3 |
30/12/2023 |
Mid-flood |
Sunny |
Moderate |
B |
11 |
10:43:00 AM |
8.7 |
7.2 |
33.6 |
22.8 |
2.4 |
2.5 |
<0.10 |
<0.01 |
Appendix H
Waste Flow Table
Contract No. 13/WSD/17
Environmental Management Plan for Design, Build and Operate First Stage of Tseung Kwan O Desalination Plant
Appendix F - Monthly
Summary Waste Flow Table
Name of Department: WSD Contract No.: 13/WSD/17
Monthly Summary Waste Flow Table for 2023 (year)
Month Actual Quantities of Inert C&D Materials Generated Monthly Actual Quantities of C&D Wastes Generated Monthly Total Quantity Generated Hard Rock and Large Broken Concrete Reused in the Contract Reused in other Projects Disposed as Public Fill Imported Fill Metals Paper/ cardboard packaging Plastics (see Note 3) Chemical Waste Others, e.g. general refuse (in '000kg) (in '000kg) (in '000kg) (in '000kg) (in '000kg) (in '000kg) (in '000 kg) (in '000kg) (in '000kg) (in '000kg) (in '000kg) Jan 3383.820 0.000 0.000 0.000 3383.820 0.000 0.000 0.000 0.000 0.000 143.690 Feb 0.000 0.000 0.000 0.000 0.000 0.000 0.002 0.138 0.010 0.000 115.880 Mar 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 205.410 Apr 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 255.720 May 2088.990 0.000 0.000 0.000 2088.990 0.000 0.000 0.000 0.000 0.000 202.270 Jun 1955.240 0.000 0.000 0.000 1955.240 0.000 0.000 0.000 0.0017 0.000 189.680 Sub-total 7428.050 0.000 0.000 0.000 7428.050 0.000 0.002 0.138 0.012 0.000 1112.650 Jul 121.060 0.000 0.000 0.000 121.060 0.000 0.008 0.150 0.042 0.000 186.110 Aug 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 168.220 Sep 762.550 0.000 0.000 0.000 762.550 0.000 0.000 148.944 0.000 0.000 172.440 Oct 568.600 0.000 0.000 0.000 568.600 0.000 0.000 18.574 0.010 0.000 185.010 Nov 15.430 0.000 0.000 0.000 15.430 0.000 0.000 0.000 0.000 0.000 116.960 Dec 215.220 0.000 0.000 0.000 215.220 0.000 0.000 0.000 0.000 0.000 79.680 Total 9110.910 0.000 0.000 0.000 9110.910 0.000 0.010 167.806 0.064 0.000 2021.070
w
Notes: (1) The performance targets
are given in Section 1.69 of Specification B
(1) The waste flow table shall also include C&D
materials that are specified in the Contract
to be imported for use at the Site.
(2) Plastics refer to plastic
bottles/containers, plastic sheets/
foam from packaging material
Appendix I
Ecology (Coral) Survey
Report
Report
1
INTRODUCTION
Background
1.1. The Project,
Design, Build and Operate First Stage of Tseung Kwan O Desalination Plant (TKODP), is a Designated Project under the Environmental Impact
Assessment Ordinance (Cap. 499) (EIAO) and is
currently governed by a Further Environmental Permit (EP No. FEP - 01/503/2015/A) for the
pre-operation and operation of the Project.
1.2. The Jardine Engineering Corporation, Limited, China State Construction
Engineering (Hong Kong) Limited and Acciona Agua, S.A. Trading As AJC Joint Venture (AJCJV) is contracted to carry out the
Design, Build and Operate First Stage of Tseung Kwan O Desalination Plant (DPTKO) under
Contract No. 13/WSD/17 (the Project).
1.3. Acuity Sustainability Consulting Limited (ASCL)
is commissioned by AJCJV to undertake the
Environmental Team (ET) services as required and/or implied, both explicitly
and implicitly, in
the Environmental Permit (EP), Environmental Impact Assessment Report (EIA Report) (Register No.
AEIAR-192/2015) and Environmental Monitoring and Audit Manual (EM&A Manual) for the
Project; and to carry out the Environmental Monitoring and Audit (EM&A) programme
in fulfillment of the EIA Report’s EM&A requirements and Contract No. 13/WSD/17
Specification requirements.
1.4. The proposed Desalination Plant at Tseung Kwan O (DPTKO)
will produce potable water with an initial capacity of 135 million litres per day
(MLD), expandable to an ultimate capacity of 270 MLD in the future
to provide a secure and alternative fresh water resource complying with the World Health
Organization (WHO) standards. The plant will adopt the Seawater Reverse Osmosis (SWRO) technology, which
dominates the market due to its reliability and progressive reduction in cost as the
technology advances.
1.5. A baseline coral survey was conducted in 13 October 2023 to verify the
validity of the pervious EIA findings as well as to provide
updated coral data for impact
monitoring during the pre-operation and
operational phases. Two indirect impact sites and one control site were identified during the
baseline coral survey for impact monitoring.
2
Methodology
2.1.
All tagged coral colonies in C2, C3 and
C8 will be monitored monthly till the end of the first year of the plant
operation. The monitoring team will record
the following parameters (using the same methodology adopted during the
pre-construction phase survey): size, presence, survival, health conditions (percentage of mortality) and percentage of sediment
of each tagged coral
colonies. The general environmental conditions during the survey date will also be monitored.
2.2
Photographic records of the tagged
coral colonies will be taken as far as possible maintaining the same aspect and orientation as photographs taken for the pre-translocation
surveys. All the tags for marking coral colonies
will be removed / retrieved once the monitoring programme is completed.
2.3
The results of the pre-operation phase
monitoring surveys should be reviewed with reference to findings of the baseline survey.
2.4
If, during the pre-operation phase
monitoring, observations of any die-off / abnormal conditions of the tagged corals are made, the ET will
inform the Contractor, Independent Environmental Checker (IEC)/ Environmental Project Office
(ENPO), Agriculture, Fisheries and Conservation Department (AFCD) and in liaison with AFCD investigate any measures
needed.
2.5
Monitoring result will be reviewed and
be compared against the Action Level and Limit Level (AL/LL) as set out in Table 2-1. Actions
specified on Table 2-2 will be taken by ET, IEC, SOR and Contractor shall there be exceedance of
AL/LL
Table 2-1 Action and Limit Levels for Pre-Operation Phase Coral Monitoring
Parameter |
Action Level Definition |
Limit Level Definition |
Mortality |
If
during Impact Monitoring a 15% increase in the percentage of partial
mortality on the corals
occurs at more
than 20% of the tagged indirect impact site coral colonies that is not recorded on the tagged corals at the control site, then the Action Level is exceeded |
If
during Impact Monitoring a 25% increase in the percentage of partial
mortality on the corals
occurs at more
than 20% of the tagged indirect impact site coral colonies that is not recorded on the tagged corals at the control site, then the Limit Level is exceeded |
Note:
If the defined Action Level or Limit Level for coral monitoring is exceeded, the actions as set out in Table 5-4 will be
implemented.
Table 2-2 Event and Action Plan for Pre-Operation Phase Monitoring
Event |
Action |
|||
ET
Leader |
IEC |
SOR |
Contractor |
|
Action Level Exceedance |
1.
Check monitoring data 2.
Inform the IEC, SOR and
Contractor of the findings; 3.
Increase the monitoring to at least once a month
to confirm findings; 4.
Propose mitigation measures for consideration |
1.
Discuss monitoring with the ET and the Contractor; 2.
Review proposals for additional monitoring and any other measures submitted by the Contractor and advise the SOR accordingly. |
1.
Discuss with the IEC additional monitoring requirements and any other measures proposed by the ET; 2.
Make agreement on the measures to be implemented. |
1.
Inform the SOR and confirm notification of the non- compliance in writing; 2.
Discuss with
the ET and the IEC and propose measures to
the IEC and
the SOR; 3.
Implement the agreed measures. |
Remark: ** The “SOR”
is equivalent to the “ER” as defined
in the EM&A Manual of the Project
3. Result
3.1. The pre-operation phase monitoring for December 2023 pre-operation
phase monitoring were performed on 28th
December 2023 for both Indirect Impact Sites and Control Site (Figure 3 and 4); and the
weather conditions were summarized in Table 3.1.
Table 3.1 Weather Condition
for the December 2023 Pre-Operation Phase Monitoring
Date |
Condition |
Average Underwater Visibility |
28th December 2023 |
-
East force 4 to 5, -
Sunny period |
Less than 0.5 m |
3.2. Ten (10) hard coral colonies in C2, C3 and C8 were monitored at each site of Control
and Indirect Impact sites as
suggested in the Operation Phase Monitoring Plan. The general health conditions (size, mortality, bleaching and sediment) were recorded and summarized
in Table 3.2, Table 3.3
and Table 3.4. Photos of each tagged coral colonies were taken during the monitoring activities
and shown in Appendix A (Photo Plate A, B and C)..
3.3. All tagged coral colonies showed good health condition during the
December 2023 Monitoring. There was not
increased level of mortality, bleaching and sediment in other tagged coral colonies when
compared with the baseline results.
Table 3.2 Sizes, Condition, Mortality, Bleaching and Sediment
of 10 Natural Coral Colonies at Control Site C8
during December 2023 Coral Monitoring Survey
Tag # |
Species |
Size (cm)
- Max.
Diameter |
Condition |
Mortality (%) |
Bleaching (%) |
Sediment (%) |
|||
|
|
|
|
Baseline |
28-Dec |
Baseline |
28-Dec |
Baseline |
28-Dec |
1 |
Favites pentagona |
66 |
Good |
0 |
0 |
0 |
0 |
0 |
0 |
2 |
Porites lutea |
58 |
Good |
0 |
0 |
0 |
0 |
0 |
0 |
3 |
Plesiastrea versipora |
31 |
Good |
0 |
0 |
0 |
0 |
0 |
0 |
4 |
Platygyra carnosus |
30 |
Good |
0 |
0 |
0 |
0 |
0 |
0 |
5 |
Acropora solitaryensis |
32 |
Good |
0 |
0 |
0 |
0 |
0 |
0 |
6 |
Plesiastrea versipora |
27 |
Good |
0 |
0 |
0 |
0 |
0 |
0 |
7 |
Porites lutea |
39 |
Good |
0 |
0 |
0 |
0 |
0 |
0 |
8 |
Favites pentagona |
20 |
Good |
0 |
0 |
0 |
0 |
0 |
0 |
9 |
Platygyra carnosus |
26 |
Good |
0 |
0 |
0 |
0 |
0 |
0 |
10 |
Acropora solitaryensis |
28 |
Good |
0 |
0 |
0 |
0 |
0 |
0 |
4. Discussion and Conclusion
4.1
The
pre-operation coral monitoring for December 2023 survey were carried out in the indirect impact area (C2 and C3) and control site (C8) on 28th
December 2023. A
total of 30 tagged coral colonies (10 at control
site and 20 and two indirect impact
sites) were monitored. All coral colonies
were good in
general.
4.2
No sediment, bleaching or increased
mortality in the general condition of all other tagged coral colonies were observed during the pre-operation
phase monitoring period. No
deterioration of the coral community was observed in the ecological monitoring results when compared with the baseline ecological monitoring
results. There is no AL/LL exceedance during the monitoring period. Photos of each tagged corals colonies
were taken and shown in Appendix A (Photo Plates A, B and C).
Figure 1 Two Proposed
Indirect Impact Sites (C2 and C3) during
Pre-Operation Phase
Figure 2 Proposed Control
Site (C8) during
Pre-Operation Phase
Appendix J
Site Inspection Proforma
Appendix K
Complaint Log
Statistical Summary
of Environmental Complaints
Reporting Period |
Environmental Complaint Statistics |
||
Frequency |
Cumulative |
Complaint Nature |
|
1 - 31 December 2023 |
0 |
1 |
N/A |
Statistical Summary
of Environmental Summons
Reporting Period |
Environmental Summons Statistics |
||
Frequency |
Cumulative |
Details |
|
1 - 31 December 2023 |
0 |
0 |
N/A |
Statistical Summary
of Environmental Prosecution
Reporting Period |
Environmental Prosecution Statistics |
||
Frequency |
Cumulative |
Details |
|
1 - 31 December 2023 |
0 |
0 |
N/A |
Appendix L
Exceedance Report (s)
Bi-Weekly Incident
Report on Action
Level or Limit Level Non-Compliance
Date of exceedance |
Monitoring Station |
Tide |
Parameter |
Measurement Result (mg/L) |
Sampling depth |
Depth Average Result (mg/L) |
Action Level (mg/L) |
Limit Level (mg/L) |
Exceedance |
Marine construction activities with
contact with water (Y/N) |
Exceedance related
to Project (Y/N) |
Reasons of non-project related exceedance |
||||||||
95%- ile |
Control 120% |
99%- ile |
Control 130% |
(1) |
(2) |
(3) |
(4) |
(5) |
(6) |
(7) |
||||||||||
12/12/2023 |
WSR16 |
Ebb |
Suspended Solid
(SS) |
-- |
-- |
5.83 |
5.00 |
5.20 |
6.00 |
5.63 |
Limit Level |
N |
N |
|
ü |
|
ü |
ü |
ü |
ü |
WSR36 |
-- |
-- |
6.50 |
Limit Level |
N |
N |
|
ü |
|
|
ü |
ü |
ü |
|||||||
NF1 |
-- |
-- |
7.17 |
Limit Level |
N |
N |
|
ü |
|
ü |
ü |
ü |
ü |
|||||||
NF2 |
-- |
-- |
5.50 |
Action Level |
N |
N |
|
ü |
|
ü |
ü |
ü |
ü |
|||||||
14/12/2023 |
WSR36 |
Flood |
Suspended Solid
(SS) |
-- |
-- |
4.50 |
5.00 |
4.00 |
6.00 |
4.33 |
Limit Level |
N |
N |
|
ü |
|
|
ü |
ü |
ü |
NF2 |
-- |
-- |
4.17 |
Action Level |
N |
N |
|
ü |
|
ü |
ü |
ü |
ü |
1)
Control
station value already
exceed either the Action or Limit Level.
2)
No silt plume or pollution discharge from site area was observed.
3)
Rainfall
was recorded at Tseung Kwan O
during the monitoring period, rainfall
may lead to release of SS content
form the soil of the nearby lands (e.g., Country
Park, fill bank).
4)
No action and limit level exceedance observed
at WSR37 (Outfall
Shaft).
5)
Marine
construction activity was completed.
6)
No operation activities related to the release of SS in the reporting
period.
7)
Water
quality mitigation measures
were observed maintained / implemented properly
(double silt curtain).
Conclusion:
During water quality
monitoring on 12 December 2023 and 14 December 2023, four (4) Action Level exceedances and three (3) Limit Level exceedance were recorded during
mid-ebb tide, and two (2) Action Level and one (1) Limit Level exceedances of Suspended Solids were
recorded during mid-flood tide. Total six (6) Action Level and four (4) Limit
Level exceedances for SS of impact water quality monitoring were recorded between 1 December to 15
December 2023.
The marine construction works were completed on 1 September
2023. The operation activities were shown in the table below.
According to the record, most of
the operation activities were instrument
checking and adjustment, no operation activities might lead to the release
of SS during the reporting period. After investigation, all exceedances
were considered non-project related.
Operation Activities:
12 December 2023 |
14 December 2023 |
-
Production of desalinated water -
Goods receiving at the plant -
Instrumentation and Control Instrument checking -
Instrument adjustment at Dissolved Air
Flotation and Filtration (ActiDAFF) |
-
Production of desalinated water -
CCT and product water sampling and
analysis -
Instrumentation and Control Instrument checking and maintenance |
Supporting Photo:
Date of exceedance |
Monitoring station(s) |
|||
12/12/2023 |
|
|
|
|
WSR16 |
WSR36 |
NF1 |
NF2 |
|
14/12/2023 |
|
|
|
|
WSR36 |
NF2 |
|
|
Bi-Weekly Incident
Report on Action
Level or Limit Level Non-Compliance
Date of exceedance |
Monitoring Station |
Tide |
Parameter |
Measurement Result (mg/L) |
Sampling depth |
Depth Average Result (mg/L) |
Action Level (mg/L) |
Limit Level (mg/L) |
Exceedance |
Marine construction activities with contact with
water (Y/N) |
Exceedance related
to Project (Y/N) |
Reasons of non-project related exceedance |
||||||||
95%- ile |
Control 120% |
99%- ile |
Control 130% |
(1) |
(2) |
(3) |
(4) |
(5) |
(6) |
(7) |
||||||||||
16/12/2023 |
WSR1 |
Flood |
Suspended Solid
(SS) |
-- |
-- |
3.50 |
5.00 |
3.50 |
6.00 |
3.79 |
Action Level |
N |
N |
|
ü |
|
ü |
ü |
ü |
ü |
WSR2 |
-- |
-- |
3.58 |
Action Level |
N |
N |
|
ü |
|
ü |
ü |
ü |
ü |
|||||||
19/12/2023 |
WSR4 |
Flood |
Suspended Solid
(SS) |
-- |
-- |
4.58 |
5.00 |
4.40 |
6.00 |
4.77 |
Action Level |
N |
N |
|
ü |
|
|
ü |
ü |
ü |
WSR37 |
-- |
-- |
5.83 |
Limit Level |
N |
N |
|
ü |
|
|
ü |
ü |
ü |
|||||||
NF2 |
-- |
-- |
4.58 |
Action Level |
N |
N |
|
ü |
|
|
ü |
ü |
ü |
|||||||
21/12/2023 |
WSR1 |
Flood |
Suspended Solid
(SS) |
-- |
-- |
4.00 |
5.00 |
3.70 |
6.00 |
4.01 |
Action Level |
N |
N |
|
ü |
|
ü |
ü |
ü |
ü |
WSR2 |
-- |
-- |
4.67 |
Limit Level |
N |
N |
|
ü |
|
ü |
ü |
ü |
ü |
|||||||
WSR3 |
-- |
-- |
4.83 |
Limit Level |
N |
N |
|
ü |
|
ü |
ü |
ü |
ü |
|||||||
WSR4 |
-- |
-- |
4.33 |
Limit Level |
N |
N |
|
ü |
|
ü |
ü |
ü |
ü |
|||||||
WSR16 |
-- |
-- |
4.17 |
Limit Level |
N |
N |
|
ü |
|
ü |
ü |
ü |
ü |
|||||||
WSR33 |
-- |
-- |
4.17 |
Limit Level |
N |
N |
|
ü |
|
ü |
ü |
ü |
ü |
|||||||
NF1 |
-- |
-- |
4.83 |
Limit Level |
N |
N |
|
ü |
|
ü |
ü |
ü |
ü |
|||||||
NF2 |
-- |
-- |
4.50 |
Limit Level |
N |
N |
|
ü |
|
ü |
ü |
ü |
ü |
|||||||
NF3 |
-- |
-- |
4.33 |
Limit Level |
N |
N |
|
ü |
|
ü |
ü |
ü |
ü |
|||||||
23/12/2023 |
NF3 |
Ebb |
Suspended Solid (SS) |
-- |
-- |
5.67 |
5.00 |
5.20 |
6.00 |
5.63 |
Limit Level |
N |
N |
|
ü |
|
ü |
ü |
ü |
ü |
26/12/2023 |
WSR1 |
Flood |
Suspended Solid
(SS) |
-- |
-- |
4.00 |
5.00 |
3.70 |
6.00 |
4.01 |
Action Level |
N |
N |
|
ü |
|
ü |
ü |
ü |
ü |
WSR2 |
-- |
-- |
4.67 |
Limit Level |
N |
N |
|
ü |
|
ü |
ü |
ü |
ü |
|||||||
WSR3 |
-- |
-- |
4.83 |
Limit Level |
N |
N |
|
ü |
|
ü |
ü |
ü |
ü |
|||||||
WSR4 |
-- |
-- |
4.33 |
Limit Level |
N |
N |
|
ü |
|
ü |
ü |
ü |
ü |
|||||||
WSR16 |
-- |
-- |
4.17 |
Limit Level |
N |
N |
|
ü |
|
ü |
ü |
ü |
ü |
|||||||
WSR33 |
-- |
-- |
4.17 |
Limit Level |
N |
N |
|
ü |
|
ü |
ü |
ü |
ü |
|||||||
NF1 |
-- |
-- |
4.83 |
Limit Level |
N |
N |
|
ü |
|
ü |
ü |
ü |
ü |
|||||||
NF2 |
-- |
-- |
4.50 |
Limit Level |
N |
N |
|
ü |
|
ü |
ü |
ü |
ü |
|||||||
NF3 |
-- |
-- |
4.33 |
Limit Level |
N |
N |
|
ü |
|
ü |
ü |
ü |
ü |
|||||||
28/12/2023 |
WSR3 |
Flood |
Suspended Solid
(SS) |
-- |
-- |
4.83 |
5.00 |
4.80 |
6.00 |
5.20 |
Limit Level |
N |
N |
|
ü |
|
ü |
ü |
ü |
ü |
WSR16 |
-- |
-- |
5.17 |
Limit Level |
N |
N |
|
ü |
|
ü |
ü |
ü |
ü |
|||||||
NF1 |
-- |
-- |
6.17 |
Limit Level |
N |
N |
|
ü |
|
ü |
ü |
ü |
ü |
|||||||
NF2 |
-- |
-- |
5.17 |
Limit Level |
N |
N |
|
ü |
|
ü |
ü |
ü |
ü |
|||||||
NF3 |
-- |
-- |
5.33 |
Limit Level |
N |
N |
|
ü |
|
ü |
ü |
ü |
ü |
1)
Control
station value already
exceed either the Action or Limit Level.
2)
No silt plume or pollution discharge from site area was observed.
3)
Rainfall
was recorded at Tseung Kwan O during
the monitoring period,
rainfall may lead to release
of SS content form the soil of the nearby
lands (e.g., Country
Park, fill bank).
4)
No action and limit level exceedance observed
at WSR37 (Outfall
Shaft).
5)
Marine
construction activity was completed.
6)
No operation activities related to the release of SS in the reporting period.
7)
Water
quality mitigation measures
were observed maintained / implemented properly
(double silt curtain).
Conclusion:
During water quality monitoring on 16 December
2023, 19 December
2023, 21 December
2023, 23 December
2023, 26 December
2023 and 30 December 2023,
twenty-eight (28) Action
Level exceedances and twenty-two (22) Limit Level exceedance
were recorded during mid-flood tide, and one (1) Action Level and one (1) Limit
Level exceedances of Suspended Solids were recorded during mid-ebb tide. Total
twenty-nine (29) Action Level and twenty-three (23) Limit Level exceedances for
Suspended Solid of impact water quality monitoring were recorded between 16
December to 31 December 2023.
Marine construction works were completed
since 1 September 2023.
The operation
activities in the reporting period were shown in the table below. The no
discharge of SS during the backwashing of Dissolved Air Flotation and
Filtration (ActiDAFF). The major activities of the plant operation might not
lead to the release of SS during the reporting period.
After investigation, all exceedances were considered non-project related.
Operation Activities:
16 December 2023 |
19 December 2023 |
-
Production of desalinated water -
Instrument checking and maintenance |
-
Production of desalinated water -
Goods receiving at the plant -
Dissolved Air Flotation and Filtration (ActiDAFF) backwashing |
21 December 2023 |
23 December 2023 |
-
Production of desalinated water -
Instrument checking and maintenance -
Dissolved Air Flotation and Filtration (ActiDAFF) backwashing |
-
Production of desalinated water -
Dissolved Air Flotation and Filtration (ActiDAFF) backwashing -
CCT and product water sampling and
analysis |
26 December 2023 |
28 December 2023 |
-
Production of desalinated water -
Goods receiving at the plant |
-
Production of desalinated water -
CCT and product water sampling and
analysis -
Dissolved Air Flotation and Filtration (ActiDAFF) backwashing -
Instrument checking and maintenance |
Supporting Photo:
Date of exceedance |
Monitoring station(s) |
|||
16/12/2023 |
|
|
|
|
WSR1 |
WSR2 |
|
|
|
19/12/2023 |
|
|
|
|
WSR4 |
WSR37 |
NF2 |
|
|
21/12/2023 |
|
|
|
|
WSR1 |
WSR2 |
WSR3 |
WSR4 |
Date of exceedance |
Monitoring station(s) |
|||
|
|
|
|
|
WSR16 |
WSR33 |
NF1 |
NF2 |
|
|
|
|
|
|
|
NF3 |
|
|
|
23/12/2023 |
|
|
|
|
NF3 |
|
|
|
Date of exceedance |
Monitoring station(s) |
|||
26/12/2023 |
|
|
|
|
WSR1 |
WSR2 |
WSR3 |
WSR4 |
|
|
|
|
|
|
WSR16 |
WSR33 |
NF1 |
NF2 |
|
|
|
|
|
|
NF3 |
|
|
|
Date of exceedance |
Monitoring station(s) |
|||
28/12/2023 |
|
|
|
|
WSR3 |
WSR16 |
NF1 |
NF2 |
|
|
|
|
|
|
NF3 |
|
|
|