Rev. |
Description of Modification |
Date |
1. |
First Issue |
13/06/2024 |
2. |
Revised According to Comments |
03/09/2024 |
3. |
Revised According to Comments |
18/11/2024 |
Appendix A |
Master Programme |
Appendix B |
Overview of Desalination Plant in Tseung Kwan O |
Appendix C |
Summary of Implementation Status of Environmental Mitigation |
Appendix D |
Water Quality Graphical Presentation |
Appendix E |
Site Inspection Proforma |
Appendix F |
Waste Flow Table |
Appendix G |
Summary of Exceedances |
Appendix H |
Complaint Log |
Appendix I |
Event/Action Plan for Noise and Water Quality Monitoring Exceedance |
Introduction
A1. The Project, Design, Build and Operate First Stage of Tseung Kwan O Desalination Plant (TKODP), is a Designated Project under the Environmental Impact Assessment Ordinance (Cap. 499) (EIAO) and is currently governed by a Further Environmental Permit (EP No. FEP - 01/503/2015/A and EP No. FEP - 01/503/2015/B) for the construction and operation of the Contract.
A2. In accordance with the Environmental Monitoring and Audit (EM&A) Manual for the Contract, EM&A works for marine water quality, noise, waste management and ecology should be carried out by Environmental Team (ET), Acuity Sustainability Consulting Limited (ASCL), during the construction phase of the Contract.
A3. This is the 4th Annual EM&A Review Report, prepared by ASCL, for the Contract summarizing the monitoring results and audit findings of the EM&A programme at and around Tseung Kwan O Area 137 (TKO 137) during the reporting period from 1 May 2023 to 30 April 2024.
A4. The EM&A programme for this contract has covered environmental monitoring on water quality, construction noise level at selected noise sensitive receivers, and Contractor¡¦s environmental performance auditing in the aspects of construction dust, construction noise, water quality, waste management, landscape and visual and ecology.
Summary of environmental monitoring and audit
works
A5. A summary of the environmental monitoring and audit works undertaken in the reporting period are summarized in Table I.
A6. No construction noise monitoring was conducted during the reporting period since there are no Contract -related construction activities undertaken within a radius of 300m from the monitoring locations. No Action Level exceedance was recorded during the reporting period.
A7. Construction Phase Impact Water Quality Monitoring was conducted as schedule in the reporting period. One hundred and fourteen (114) action level exceedances and ninety- two (92) limit level exceedances of Suspended Solid were recorded in the reporting period. Pre-operation Phase Impact Water Quality Monitoring was conducted as schedule in the reporting period. One hundred and fifty-seven (157) action level exceedances and one hundred and nine (109) limit level exceedances of Suspended Solid were recorded in the reporting period. Summary of exceedances could be referring to Appendix G.
A8. All Action and Limit Level exceedance was concluded to be unrelated to the Project. Details of the exceedance could be referring to Appendix L of the corresponding Monthly EM&A Report.
A9. Total eleven (11) of dechlorinated effluent sample were taken during the discharge of dechlorinated effluent by contractor. No TRC exceedance of action or limit levels was obtained during the discharge of dechlorinated effluent.
A10. Nine hundred and seventy-three (973) times of landfill gas monitoring were conducted in the reporting period. No action or limit level exceedance was recorded in the reporting period.
A11. Pre-operation phase coral monitoring was commenced in December 2023. There were no AL/LL exceedances observed during the reporting period.
A12. Pre-operation phase fishery monitoring for dry season 2024 was carried out on 17 and 24 February 2024. There is no AL/LL exceedance during the reporting period.
Table I Summary of Environmental Monitoring Works
Environmental Monitoring works |
Frequency |
Noise Monitoring |
N/A |
Construction Phase Water Quality Monitoring |
52 |
Pre-operation Phase Water Quality Monitoring |
61 |
Pre-operation Phase Coral Monitoring |
5 |
Pre-operation Phase Fishery Monitoring |
2 |
Landfill Gas Monitoring |
973 |
Environmental Site Inspection |
53 |
Complaint Handling and Prosecution
A13. One environmental complaint was received from the EPD in the reporting period, no notifications of summons and prosecution was received during the reporting period.
Reporting Change
A14. There was no change to be reported that may affect the on-going EM&A programme.
The Jardine Engineering Corporation, Limited, China State Construction Engineering (Hong Kong) Limited and Acciona Agua, S.A. Trading as AJC Joint Venture (AJCJV) is contracted to carry out the Design, Build and Operate First Stage of Tseung Kwan O Desalination Plant (TKODP) under Contract No. 13/WSD/17 (the Contract).
Acuity Sustainability Consulting Limited (ASCL) is commissioned by AJCJV to undertake the Environmental Team (ET) services as required and/or implied, both explicitly and implicitly, in the Environmental Permit (EP), Environmental Impact Assessment Report (EIA Report) (Register No. AEIAR-192/2015) and Environmental Monitoring and Audit Manual (EM&A Manual) for the Contract; and to carry out the Environmental Monitoring and Audit (EM&A) programme in fulfillment of the EIA Report¡¦s EM&A requirements and Contract No. 13/WSD/17 Specification requirements.
Pursuant to the Environmental Impact Assessment Ordinance (EIAO), the Director of Environmental Protection granted the Environmental Permit (No. EP-01/503/2015) and Variation of Environmental Permit (No. EP-01/503/2015/A and No. EP-01/503/2015/B) to Water Supplies Department (WSD); and granted the Further Environmental Permit (No. FEP-01/503/2015/A and No. EP-01/503/2015/B) to AJCJV for the Contract.
This is the 4th Annual EM&A Review Report for the Project which summarizes the key findings of the EM&A programme during the reporting period from 1 May 2023 to 30 April 2024.
The Contract Organization structure for Construction Phase is presented in Figure 1.1 and contact details of the key personnel are presented in Table 1.1 below:
Figure 1.1 Contract Organization Chart
Table 1.1 Contact Details
of Key Personnel
Party |
Position |
Name |
Telephone no. |
Remark |
Project Proponent (WSD) |
SE/CM2 |
Milton Law |
2634-3573 |
- |
Supervising Officer (Binnies Hong Kong Limited) |
Project Manager |
Christina Ko |
2608-7302 |
- |
Chief Resident Engineer |
Roger Wu |
6343-1002 |
- |
|
The Jardine Engineering Corporation, Limited, China State Construction Engineering (Hong Kong) Limited and Acciona Agua, S.A. Trading |
Project Manager |
Stephen Yeung |
2807-4665 |
- |
Environmental Monitoring Manager |
Brian Kam |
9456-9541 |
- |
|
Environmental Monitoring Manager |
Joy Chan |
6468-1782 |
Until 24
March 2024 |
|
Environmental Monitoring Manager |
Tommy Law |
6468-1782 |
On the position from 25 April 2024 |
|
Acuity Sustainability Consulting Limited |
Environmental Team Leader
(ETL) |
Jacky Leung |
2698-6833 |
Until 21
April 2024 |
Toby Wan |
9719-5422 |
On the position from 22 April 2024 |
||
ANewR Consulting Limited |
Independent Environmental Checker (IEC) |
Louis Kwan |
2618-2831 |
Until 31 May 2023 |
Alex Chan |
Until 31
January 2024 |
|||
Lam Environmental Services Limited |
Independent Environmental Checker (IEC) |
Serena Shek |
6149-6683 |
On the position from 1 February 2024 |
The construction programme is presented in Appendix A. Detail of the major construction activities undertaken could be referred to Section 1.8 in each monthly EM&A Report.
The status for all environmental aspects is presented in Table 1.2.
Table 1.2 Summary of Status for Key Environmental Aspects under the EM&A Manual
Parameters |
Status |
Water Quality |
|
Baseline Monitoring under EM&A
Manual |
The baseline water quality monitoring was conducted
between 12 May 2020 to 6 June 2020 |
Parameters |
Status |
Construction Phase Marine Impact Monitoring |
Ceased from
1 September 2023 |
Pre-Operation Phase
Marine Impact Monitoring |
On-going from
12 December 2023 |
Impact
Monitoring of Effluent Discharge from Main Disinfection |
Complete in November 2023
and December 2024 |
Noise |
|
Baseline Monitoring |
The baseline noise monitoring result has been reported in Baseline Monitoring Report and submitted to EPD under EP Condition
3.4. |
Impact Monitoring |
Completed |
Ecology (Coral) |
|
Pre-operation phase Regular Coral Monitoring (Monthly) |
On-going (Started from December 2023) |
Ecology (Fishery) |
|
Pre-operation phase
Regular Fishery Monitoring
(Monthly) |
On-going (Started from December 2023) |
Ecology (Landscape) |
|
Pre-operation phase
Landscape and Visual Site
Inspection |
On-going |
Waste Management |
|
Mitigation Measures in Waste Management Plan |
On-going |
Landfill Gas |
|
Regular Monitoring when construction works are within the 250 m Consultation
Zone |
On-going |
Environmental Audit |
|
Site Inspection
covering Measures of Air Quality, Noise Impact, Water
Quality, Waste, Ecological Quality, Fisheries, Landscape and Visual |
On-going |
Other than the EM&A work by ET, environmental briefings, trainings and regular environmental management meetings were conducted, in order to enhance environmental awareness and closely monitor the environmental performance of the contractors.
The EM&A programme has been implemented in accordance with the recommendations presented in the approved EIA Report and the EM&A Manual. A summary of implementation status of the environmental mitigation measures for the construction phase and pre-operation phase of the Contract during the reporting period is provided in Appendix C.
To ensure no adverse noise impact, noise monitoring is recommended to be carried out within 300m radius from the nearby noise sensitive receivers (NSRs), during construction phase. The NSRs selected as monitoring station are (i) NSR4 - Creative Secondary School, (ii) NSR24 - PLK Laws Foundation College, and (iii) NSR31 - School of Continuing and Professional Studies - CUHK respectively.
The monitoring locations were normally made at a point 1m from the exterior of the NSRs building façade and be at a position 1.2m above the ground. A correction of +3dB(A) was made to the free-field measurements.
According to the environmental findings detailed in the EIA report and Baseline Monitoring Report, the designated locations for the construction noise monitoring are listed in Table 2.1 below.
Table 2.1 Noise Sensitive Receivers
NSR ID |
Noise Sensitive Receivers |
Monitoring Location |
Position |
NSR 4 |
Creative Secondary School |
Roof Floor |
1 m from facade |
NSR 24 |
PLK Laws Foundation College |
Pedestrian Road on Ground Floor |
Free field |
NSR 31 |
School of Continuing and Professional Studies - CUHK |
Roof Floor |
1 m from facade |
Three noise monitoring locations for impact monitoring at the nearby sensitive receivers are shown in Figure 2.1-2.3.
|
Figure 2.1 NSR4
Creative Secondary School |
|
Figure 2.2 NSR24 PLK Laws Foundation College |
|
Figure 2.3 NSR31
School of Continuing and Professional Studies - CUHK |
Construction noise level were measured in terms of the A-weighted equivalent continuous sound pressure level (LAeq). Leq 30min was used as the monitoring parameter for the time period between 0700 and 1900 on normal weekdays. Table 2.2 summarizes the monitoring parameters, frequency, and duration of the impact noise monitoring.
Table 2.2 Noise Monitoring Parameters, Time, Frequency
and Duration
Time |
Duration |
Interval |
Parameters |
Daytime: 0700-1900 |
Day time: 0700-1900 (during normal weekdays) |
Continuously in Leq 5min/Leq 30min (Average of 6 consecutive Leq 5min) |
Leq 30min L10 30min
& L90 30min |
The monitoring methodology and QA/QC procedure could be referring to Section 2.3 of the Monthly EM&A Report.
The Action/Limit Levels are in line with the criteria of Practice Note for Professional Persons (ProPECC PN 2/93) ¡§Noise from Construction Activities - Non-statutory Controls¡¨ and Technical Memorandum on Environmental Impact Assessment Process issued by HKSAR Environmental Protection Department [¡§EPD¡¨] under the Environmental Impact
Assessment Ordinance, Cap 499, S.16 are presented in Table 2.3.
Table 2.3 Action and Limit Levels for Noise per EM&A Manual
Time Period |
Action |
Limit (dB(A)) |
0700-1900 on normal weekdays |
When one documented complaint is received from any one of the noise sensitive receivers |
- 70 dB(A) for school and - 65 dB(A) during examination period |
Notes: Limits specified in the GW-TM
and IND-TM for construction and operation noise,
respectively.
If exceedances were found during noise monitoring, the actions in accordance with the Event and Action Plan shall be carried out according to Appendix G.
Referring to EM&A manual Section 4.1.2, the impact noise monitoring should be carried out when there are Contract-related construction activities undertaken within a radius of 300m from the monitoring stations. No monitoring station was located within a radius of 300m of the Contract site as shown in Figure 2.4, no impact monitoring for noise impact was conducted in the reporting period.
Figure 2.4 Site Layout Plan with Noise Sensitive Receivers and Desalination Plant
In accordance with the recommendations of the EIA, water quality EM&A is required during dredging for the submarine pipelines and, during operation phase. In addition, baseline water quality monitoring was prior to the commencement of marine construction activities.
The following Section provides details of the water quality monitoring to be undertaken by the Environmental Team (ET) to verify the distance of sediment and brine plume dispersion and to identify whether the potential exists for any indirect impacts to occur to ecological sensitive receivers.
Water quality monitoring for the Contract can be divided into the following stages:
- Dredging activities during construction phase;
- Discharge of effluent from main disinfection during construction phase;
- Pre-operation - before operation phase
- Operation phase - first year upon commissioning; and,
- Continuous monitoring of effluent quality (Operation phase)
In addition, the marine works contractor is required to complete a silt curtain efficiency test for the combined use of floating silt curtain type and cage type silt curtain for dredging at seawater intake to confirm the silt curtain reduction efficiency assumptions of the assessment. The details of testing plan together with the silt curtain deployment plan shall be submitted by the ET to seek approval from the IEC and EPD.
Marine Water Quality Monitoring
The parameters that have been selected for measurement in situ and in the laboratory are those that were either determined in the EIA to be those with the most potential to be affected by the construction works or are a standard check on water quality conditions. Parameters to be measured in the impact water quality monitoring are listed in Table 3.1.
Table 3.1 Parameters measured in the impact marine water quality monitoring
Parameters |
Unit |
Abbreviation |
Stage |
|
Construction |
Pre-operation |
|||
In-situ measurements |
||||
Dissolved oxygen |
mg/L |
DO |
🗸 |
🗸 |
Temperature |
oC |
- |
🗸 |
🗸 |
pH |
- |
- |
🗸 |
🗸 |
Turbidity |
NTU |
- |
🗸 |
🗸 |
Salinity |
0/00 |
- |
🗸 |
🗸 |
Total Residual Chlorine |
mg/L |
TRC |
- |
🗸 |
Parameters |
Unit |
Abbreviation |
Stage |
|
Construction |
Pre-operation |
|||
Laboratory measurements |
||||
Suspended Solids |
mg/L |
SS |
🗸 |
🗸 |
Iron |
mg/L |
Fe |
|
🗸 |
In addition to the water quality parameters, other relevant data was measured and recorded in Water Quality Monitoring Logs, including the location of the sampling stations, water depth, time, weather conditions, sea conditions, tidal stage, current direction and velocity, special phenomena and work activities undertaken around the monitoring and works area that may influence the monitoring results.
The monitoring methodology, monitoring equipment and QA/QC procedure could be referring to Section 3.1.2 - 3.1.4 of the Monthly EM&A Report.
Marine Water Quality Monitoring
The impact water quality monitoring locations are in accordance with the EM&A Manual and detailed in Table 3.2 and Figure 3.1 below.
Table 3.2 Location of Impact Water Quality Monitoring Station
Station |
Easting |
Northing |
Description |
CE |
843550 |
815243 |
Upstream control station at ebb tide |
CF |
846843 |
810193 |
Upstream control station at flood tide |
WSR1 |
846864 |
812014 |
Ecological sensitive receiver at Tung Lung Chau |
WSR2 |
847645 |
812993 |
Fisheries sensitive receiver at Tung Lung Chau |
WSR3 |
848023 |
813262 |
Ecological sensitive receiver at Tung Lung Chau |
WSR4 |
847886 |
814154 |
Ecological sensitive receiver at Tai Miu Wan |
WSR16 |
845039 |
815287 |
Ecological sensitive receiver at Fat Tong Chau |
WSR33 |
847159 |
814488 |
Ecological sensitive receiver at Tai Miu Wan |
WSR36 |
846878 |
814081 |
Ecological sensitive receiver at Kwun Tsai |
WSR37 |
846655 |
813810 |
Ecological sensitive receiver at Tit Cham Chau |
Station |
Easting |
Northing |
Description |
NF1* |
846542 |
813614 |
Edge of mixing zone, ~ 200m west of outfall diffuser |
NF2* |
846942 |
813614 |
Edge of mixing zone, ~ 200m east of outfall diffuser |
NF3* |
846742 |
813414 |
Edge of mixing zone, ~ 200m south of outfall diffuser |
Remark*: NF1 to NF3 are added for the operation phase of TKODP in accordance with Table 5.3 in the approved EM&A Manual.
WSR1 to WSR37 were identified in accordance with Annex 14 of the EIAO-TM as well as Clause 3.4.4.2 of the Environmental Impact Assessment Study Brief for Desalination Plant at Tseung Kwan O (No. ESB-266/2013). WSR1 to WSR3 are sited near the Tung Lung Chau Fish Culture Zone; WSR16 and WSR36 are sited near the coral assemblages along the coastlines of Fat Tong Chau and Kwun Tsai respectively; WSR 4 and WSR33 are sited near the Coastal Protection Area and coral assemblages in waters of Tai Miu Wan; WSR37 is sited near the fisheries resource including spawning and nursery grounds at the coastal water of Tit Cham Chau. NF1 to NF3 are the Edge of Mixing zone.
Figure 3.1 Impact water quality monitoring locations under EM&A Manual
Effluent Monitoring from Main Disinfection
According to the approved Flushing and Disinfection Procedure and Supplementary of the Disinfection Procedure for Desalination Plant at Tseung Kwan O, the sampling point of the dechlorinated effluent was located at Contact tank/Product Water Tank (PWT) and T1GKC01AA502/manhole 18. The approved sampling location was shown in Table 3.3, Figure 3.2 and Figure 3.3 below.
Table 3.43 Sampling location of dechlorinated effluent
System/Loop |
Discharge location |
Sampling Location |
Contact tank/ Product Water Tank (PWT) |
Culvert |
Contact tank/PWT |
Connection to dist. network |
Manhole 18 in connection point |
Sampling point T1GKC01AA502/manhole 18 |
Figure 3.2 Impact water quality
monitoring point for dechlorinated effluent (Contact
tank/PWT)
Figure 3.3 Impact water quality
monitoring point for dechlorinated effluent (Sampling
point T1GKC01AA502/manhole 18)
Marine Water Quality Monitoring
The Action and Limit Levels have been set based on the derivation criteria specified in the EM&A Manual. Based on the baseline water quality monitoring data and the derivation criteria, the Action/Limit Levels have been derived and are presented in Table 3.4.
Table 3.4 Derived Action and Limit Levels for Water Quality
Parameters |
Action |
Limit |
Marine Water
Quality Monitoring |
||
DO in mg/L |
Surface and
Middle |
Surface and
Middle |
|
7.30 mg L-1 |
4 mg L-1 |
|
Bottom |
Bottom |
|
7.31 mg L-1 |
2 mg L-1 |
|
Tung Lung Chau Fish
Culture Zone |
Tung Lung Chau Fish
Culture Zone |
|
5.1 mgL-1 or level at control
station |
5.0 mgL-1 or level
at control station |
|
(Whichever the lower) |
(Whichever the lower) |
Parameters |
Action |
Limit |
Marine Water
Quality Monitoring |
||
SS in mg/L
(Depth- averaged) |
5.00 mg L-1
or 20% exceedance of value at any impact station
compared with corresponding data from control station |
6.00 mg L-1 or 30% exceedance of value at any
impact station compared with corresponding data from control station |
Turbidity in NTU (Depth- averaged) |
2.41 NTU or 20% exceedance of
value at any impact station compared with corresponding data from control station |
2.84 NTU or 30% exceedance of
value at any impact station compared with corresponding data from control station |
Salinity in PSU (Depth-
averaged) |
34.25 PSU or 9% exceedance of
value at any impact station compared with corresponding data from control station |
34.56 PSU or 10% exceedance of
value at any impact station compared with corresponding data from control station |
Iron in mg/L
(Depth- averaged) |
0.3 mg/L |
0.3 mg/L |
Total residual chlorine in mg/L |
0.01 mg/L |
0.01 mg/L |
Total residual chlorine in mg/L (Disinfection) |
0.1 mg/L |
0.1 mg/L |
Notes:
i. "Depth-averaged" is calculated by taking the arithmetic means
of reading of all three
depths.
ii.
For DO, non-compliance of the water quality limits
occurs when monitoring result is lower than the limits.
iii. For Turbidity, SS, iron and Salinity, non-compliance of the water quality limits occurs when monitoring result is higher than the limits.
iv. For the Action and Limit Levels adopted during
First-year Operation Phase
Monitoring, further review
would be made according to the EM&A Manual during Operation Phase.
v. Monitoring of
Total Residual Chlorine (Disinfection) will be conducted when cleaning and
sterilization of the new freshwater
main is carried out.
vi. Monitoring of Iron and Total Residual
Chlorine were conducted during the pre-operation phase.
Marine Water Quality Monitoring
The ET of the Contract had conducted the construction phase impact water quality monitoring between 1 May 2023 and 31 August 2023 at the ten designated monitoring stations and the additional pre-operation phase marine water quality monitoring between 12 December 2023 and 30 April 2024 at the thirteen designated monitoring stations near TKO in accordance with the EM&A Manual and Contract Specification.
Effluent Monitoring from Main Disinfection
According to the approved EM&A Manual Section 5.1.6(b), Flushing and Disinfection Procedure and Supplementary of the Disinfection Procedure was prepared by ET and approved by EPD. The dechlorinated effluent was conducted by the contractor on 24 November 2023, 2 December 2023 and 3 December 2023 in accordance with the EM&A Manual and Contract Specification
Marine Water Quality Monitoring
The construction phase water quality monitoring was suspended on 1 September 2023 following the completion of marine-related construction works, and the pre-operation phase marine impact monitoring commenced in December 2023.
The water quality monitoring at the designated locations were conducted by the ET as scheduled in the reporting period. The graphical presentation of the water quality monitoring result was shown in Appendix D.
Construction Phase Impact Water Quality Monitoring was conducted as schedule in the reporting period. One hundred and fourteen (114) action level exceedances and ninety- two (92) limit level exceedances of Suspended Solid were recorded in the reporting period.
Pre-operation Phase Impact Water Quality Monitoring was conducted as schedule in the reporting period. One hundred and fifty-seven (157) action level exceedances and One hundred and nine (109) limit level exceedances of Suspended Solid were recorded in the reporting period
Details of the exceedance could be referring to Appendix L of the Monthly EM&A Report. Effluent Monitoring from Main Disinfection
Total eleven (11) of dechlorinated effluent sample were taken during the discharge of dechlorinated effluent by contractor. No TRC exceedance of action or limit levels was obtained during the discharge of dechlorinated effluent. Monitoring results are summarized in Table 3.5.
Table 3.5 Summary of dechlorinated effluent Monitoring Results
Location |
Contact Tank
/ Product Water
Tank Flushing after
Neutralization |
||||||||||
Date |
24 Nov 2023 |
2 Dec 2023 |
3 Dec 2023 |
||||||||
Time |
16:00 |
17:00 |
18:00 |
19:00 |
23:59 |
01:00 |
02:00 |
03:00 |
04:00 |
05:00 |
06:00 |
TRC (mg/L) |
0.08 |
0.03 |
0.02 |
0.01 |
0.04 |
0.04 |
0.03 |
0.02 |
0.01 |
0.00 |
0.01 |
The waste generated from this Project includes inert construction and demolition (C&D) materials, and non-inert C&D materials. Non-inert C&D materials are made up of general refuse, vegetative wastes and recyclable wastes such as plastics and paper/cardboard packaging waste. Steel materials generated from the project are also grouped into non-inert C&D materials as the materials were not disposed of with other inert C&D materials. Details of cumulative waste management data are presented as a waste flow table in Appendix F.
In according with Section 11 of the EM&A Manual, monitoring of landfill gas is required for construction works within the 250m Consultation Zone. Part of the desalination plant and the indicative area of natural slope mitigation works fall within the SENT Landfill Extension Consultation Zone; and part of the 1,200 mm diameter freshwater mains along Wan Po Road falls within the SENT Landfill and SENT Landfill Extension Consultation Zones, TKO Stage II/III Restored Landfill and TKO Stage I Restored Landfill Consultation Zones.
Since part of the desalination plant (Wan Po Road and MIC compound/Basketball Court) and the indicative area of natural slope mitigation works fall within the SENT Landfill Extension Consultation Zone in this contract (Figure 5.1), landfill gas monitoring would be required for Wan Po Road and MIC compound/Basketball Court (Figure 5.2) if excavations were conducted at more than 300mm deep. Although SENT Landfill Extension has commenced operation since November 2021, no excavation works were conducted at MIC compound/Basketball Court. Hence no landfill gas monitoring would be scheduled for MIC compound/Basketball Court at the current stage.
Figure 5.1 Overview of the SENT Extension Consultation Zone and the Contract Site Area
Figure 5.2 Location Map for Landfill
Gas Monitoring at Wan Po Road
LFG monitoring was carried out to identify any migration between the landfill and the Contract and to ensure the safety of the construction, operation and maintenance personnel working on-site, visitors and any other person within the Contract area.
The following parameters were monitored:
- Methane
- Oxygen
- Carbon Dioxide
- Barometric Pressure
Landfill Gas monitoring was carried out using intrinsically safe, portable multi-gas monitoring instruments. Detail of monitoring equipment used in the reporting period could be referred to Section 5.10 of the corresponding Monthly EM&A Report.
Nine hundred and seventy-three (973) times of landfill gas monitoring were conducted in the reporting period. No action or limit level exceedance was recorded in the reporting period.
Action and Limit Level are provided in Table 5.1.
Table 5.1 Action / Limit Levels and Event and Action Plan for LFG Hazard
Parameters |
Level |
Action |
|
Oxygen (O2) |
Action Level < 19% O2 |
Ventilate trench/void to restore O2 to > 19% |
|
|
Limit Level < 19% O2 |
Stop works Evacuate personnel/prohibit entry Increase ventilation to restore O2 to > 19% |
|
Methane (CH4) |
Action Level |
>10% LEL |
Post "No Smoking" signs Prohibit hot works Increase ventilation to restore CH4 to <10% LEL |
|
Limit Level |
>20% LEL |
Stop works Evacuate
personnel/prohibit entry Increase ventilation to restore CH4 to<10% LEL |
Carbon Dioxide (CO2) |
Action Level |
>0.5% CO2 |
Ventilate
to restore CO2 to < 0.5% |
|
Limit Level |
>1.5% CO2 |
Stop works Evacuate personnel / prohibit entry Increase
ventilation to restore CO2 to <0.5% |
Under the approval conditions of the EIA Report for the Project, an EM&A programme on coral for the pre-operation phase of the Project is recommended. Pursuant to these EIA approval conditions and Condition 3.1 of the EP and FEP, details of the regular coral monitoring programme have been proposed based on the baseline coral monitoring results in the Report on Pre-Operation Baseline Coral Monitoring and Regular Coral Monitoring Methodology.
Monitoring Location
In accordance with Appendix B Section 5.1 of the approved supplementary EM&A Manual, two indirect impact sites (C2 and C3) and one control site (C8) as shown in Figure 6.1 should be monitored during the pre-operation Phase. Pre- operation coral survey should be conducted at the indirect impact and control sites. Ten selected hard coral colonies with similar species should be tagged at each of the control and indirect impact sites before commencement of the operation phase. Tagged hard coral colonies should be monitored in open waters during the pre- operation phase and operation phase.
Figure 6.1 Spot Dive Check Areas Two Proposed Indirect Impact Sites (C2 and C3) and one control site (C8) during pre-operation Phase
Action and Limit Levels
The Action and Limit Levels have been set based on the derivation criteria specified in the EM&A Manual. The Action/Limit Levels have been derived and are presented in Table 6.1.
Table 6.1 Action and Limit Level for Coral Monitoring Equipment
Parameter |
Action Level Definition |
Limit Level Definition |
Mortality |
If during Impact
Monitoring a 15% increase in the percentage of partial mortality on the corals occurs at more than 20% of the tagged indirect impact site coral colonies that is not recorded on the tagged corals at the
control site, then the Action Level is exceeded |
If during Impact
Monitoring a 25% increase in the percentage of partial mortality on the corals occurs at more than 20% of the tagged indirect impact site
coral colonies that is not recorded on the tagged corals at the
control site, then the Limit Level is exceeded |
Note: If the defined
Action Level or Limit Level
for coral monitoring is exceeded, the actions as set out in Table E3 of Appendix E will be implemented.
If non-compliance were found
during the construction works, the actions in accordance with the Event and
Action Plan will be carried out according to Appendix G.
Monitoring Frequency
Pre-operation phase coral monitoring shall be monitored once per month as the requirement of the first year of operational phase.
Monitoring Result and Observation
Pre-operation phase coral monitoring was commenced in December 2023. There were no
AL/LL exceedances observed during the reporting period. The detailed result of
the monitoring is presented in Appendix I of the Monthly EM&A Report.
The purpose of the pre-operation phase regular fisheries monitoring programme is to monitor the potential impacts on fisheries resources in the vicinity of the project site. Apart from the regular fisheries monitoring programme, a water quality monitoring programme in addition to the water quality monitoring programme in the approved EM&A Manual is also described in Section 2.4 to (i) provide supplementary information in the interpretation of the findings of the fisheries monitoring and (ii) assist the monitoring of the potential impact on the Tung Lung Chau Fish Culture Zone (FCZ) in Joss House Bay.
Monitoring Location
In accordance with Section 2.3 of the approved Methodology Paper on Regular Fisheries Monitoring, it is recommended to set up six (6) fisheries monitoring locations in Joss House Bay and its vicinity to monitor the fisheries resources.
Two (2) sampling locations are set up in close proximity of the direct footprint of the proposed submarine utilities around TKO Area 137. These sampling locations represent the potential Project impact zones (i.e. areas at and in close proximity to the footprint of the proposed submarine utilities that will be directly affected by the Project works).
Two (2) gradient locations are proposed between the proposed submarine utilities and Tung Lung Chau FCZ to assist in the interpretation and identification of any potential fisheries impact in the vicinity of the FCZ.
Two (2) reference locations are proposed in the outer Joss House Bay between the waters of Tung Lung Chau and Fat Tong Mun. These reference locations are further away and will not be affected by the Project discharge (based on the EIA prediction) and will serve as control stations. Any significant fisheries impact identified at the reference locations should be caused by other natural factors or non-Project activities. The trends of fisheries conditions recorded in the reference locations will be used to assist in the interpretation of the trends of fisheries impact identified in the impact and gradient locations.
The coordinates of the proposed
monitoring locations are shown in Figure 7.1.
Figure 7.1 Monitoring location of regular fishery monitoring during pre-operation Phase
Monitoring Frequency
Pre-operation phase fishery monitoring shall be carried out 2 times in wet season (April to October) and 2 times in dry season (November to March) to examine the following:
- Fish species composition;
- Abundance: number of fish captured;
- Diversity of fish resources: species diversity and evenness;
- Size: range of total length; Biomass in weight; and
- Values of catches of commercial species: catch per unit effort (CPUE) and yield per unit effort (YPUE).
Monitoring Result and Observation
Pre-operation phase fishery monitoring for dry season 2024 was carried out on 17 and 24 February 2024. There is no AL/LL exceedance during the reporting period. The detailed result of the monitoring is presented in No. 50 April 2024 Monthly EM&A Report.
The Environmental Complaint Handling Procedure is shown in below Figure 8.1:
Figure 8.1 Environmental Complaint Handling Procedures
No noise monitoring was conducted during the reporting period since there are no Contract-related construction activities undertaken within a radius of 300m from the monitoring locations.
The construction phase water quality monitoring was suspended on 1 September 2023 following the completion of marine-related construction works, and the pre-operation phase marine impact monitoring commenced in December 2023.
Seven hundred and fifty-two (752) of the general water quality monitoring results of SS obtained had exceeded the Action level. Six hundred and eighteen (618) of the general water quality monitoring results of SS obtained during the reporting period had exceeded the Limit Level.
Details of the exceedance could be referring to Appendix L of the corresponding Monthly Report.
Total eleven (11) of dechlorinated effluent sample were taken during the discharge of dechlorinated effluent by contractor. No TRC exceedance of action or limit levels was obtained during the discharge of dechlorinated effluent.
Nine hundred and seventy-three (973) times of landfill gas monitoring were conducted in the reporting period. No action or limit level exceedance was recorded in the reporting period.
Pre-operation phase coral monitoring was commenced in December 2023. There were no AL/LL exceedances observed during the reporting period.
One environmental complaint was received from EPD on 22 January 2024 in the reporting period. Detailed information could be referred January 2024 Monthly EM&A Report. No notification of summons and prosecution was received in the reporting period. Summary of complaint log are presented in Appendix H.
Site inspections were carried out on a weekly basis to monitor the implementation of proper environmental pollution control and mitigation measures under the Contract. In the reporting period, site inspections were carried out from May 2023 to April 2024.
Fifty-three (53) site inspection were carried out in the reporting period.
Environmental deficiencies were observed during weekly site inspection. Key observations during the site inspections and during the reporting period could be referring to Appendix E and corresponding Monthly Report.
According to the EIA Study
Report, Environmental Permit, contract documents and EM&A Manual, the
mitigation measures detailed in the documents should be implemented as much as
practical during the reporting period. An updated Implementation Status of
Environmental Mitigation Measures (EMIS) is provided in Appendix C.
This is the 4th Annual EM&A Review Report for the Project which summarizes the key findings of the EM&A programme during the reporting period from 1 May 2023 to 30 April 2024, in accordance with the EM&A Manual and the requirement under FEP - 01/503/2015/A and FEP - 01/503/2015/B.
No noise monitoring was conducted in the reporting period due to the over distant monitoring station from the works location, in which construction activities were not undertaken within a radius of 300m from the monitoring locations.
The EM&A works for water quality were conducted during the reporting period in accordance with the EM&A Manual.
Construction Phase Impact Water Quality Monitoring was conducted as schedule in the reporting period. One hundred and fourteen (114) action level exceedances and ninety- two (92) limit level exceedances of Suspended Solid were recorded in the reporting period. Pre-operation Phase Impact Water Quality Monitoring was conducted as schedule in the reporting period. One hundred and fifty-seven (157) action level exceedances and one hundred and nine (109) limit level exceedances of Suspended Solid were recorded in the reporting periodAll Action and Limit Level exceedances were unrelated to the project.
Details of the exceedance could be referring to Appendix L of the corresponding Monthly EM&A Report.
Total eleven (11) of dechlorinated effluent sample were taken during the discharge of dechlorinated effluent by contractor. No TRC exceedance of action or limit levels was obtained during the discharge of dechlorinated effluent.
Nine hundred and seventy-three (973) times of landfill gas monitoring were conducted in the reporting period. No action or limit level exceedance was recorded in the reporting period.
Pre-operation phase coral monitoring was commenced in December 2023. There were no AL/LL exceedances observed during the reporting period.
Pre-operation phase fishery monitoring for dry season 2024 was carried out on 17 and 24 February 2024. There is no AL/LL exceedance during the reporting period.
Weekly environmental site inspection was conducted during the reporting period. Minor deficiency was observed during site inspection. The environmental performance of the project was therefore considered satisfactory.
According to the environmental site inspections performed in the reporting period, the Contractor is reminded to pay attention on maintaining proper materials storage, site tidiness and chemical storage on site.
One (1) environmental complaint was received from EPD on 23 January 2024 in the reporting period. Detailed information could be referred January 2024 monthly EM&A report. No notification of summons or prosecution was received in the reporting period.
The ET will keep track on the construction works to confirm compliance of environmental requirements and the proper implementation of all necessary mitigation measures.
Appendix A
Master Programme
Appendix C
Summary of Implementation Status of Environmental Mitigation
EIA Reference |
Recommended
Environmental Protection Measures/ Mitigation Measures |
Objectives
of the recommended measures
& main concerns to address |
Implementation Agent |
Implementation Stage |
Implementation status |
Relevant Legislation & Guidelines |
||
D |
C |
O |
||||||
Air Quality |
|
|||||||
S4.8.1 |
Impervious dust screen or sheeting will be
provided to enclose scaffolding from the ground
floor level of building for construction of superstructure of
the new buildings. |
Land site/ During
Construction |
Contractor(s) |
|
ü |
|
Implemented |
Air Pollution Control (Construction Dust) |
S4.8.1 |
Impervious sheet
will be provided for skip hoist
for material transport. |
Land site/
During Construction, particularly dry season |
Contractor(s) |
|
ü |
|
NA |
- |
S4.8.1 |
The area where
dusty work takes
place should be sprayed with water or a dust suppression chemical
immediately prior to, during and immediately after dusty activities as far as practicable. |
Land site/ During
Construction |
Contractor(s) |
|
ü |
|
Implemented |
- |
S4.8.1 |
All dusty
materials should be sprayed with
water or a dust suppression chemical immediately prior
to any loading, unloading or
transfer operation. |
Land site/ During Construction |
Contractor(s) |
|
ü |
|
Implemented, reminder issued |
- |
S4.8.1 |
Dropping heights for excavated materials should be controlled to a practical height to
minimize the fugitive dust arising
from unloading. |
Land site/ During Construction |
Contractor(s) |
|
ü |
|
Implemented |
- |
S4.8.1 |
During transportation by truck, materials should
not be loaded to a level higher
than the side and tail boards and should
be dampened or covered before transport. |
Land site/ During
Construction |
Contractor(s) |
|
ü |
|
Implemented |
- |
S4.8.1 |
Wheel washing device should be provided at the exits of the work sites.
Immediately before leaving
a construction site, every vehicle shall be washed to
remove any dusty material from its
body and wheels as far as practicable. |
Land site/ During
Construction |
Contractor(s) |
|
ü |
|
Implemented |
- |
S4.8.1 |
Road sections between vehicle-wash areas and
vehicular entrance will be paved. |
Land site/ During Construction |
Contractor(s) |
|
ü |
|
Implemented |
- |
S4.8.1 |
Hoarding of not less than 2.4m
high from ground
level will be provided along
the length of the Project
Site boundary. |
Land site/ During
construction |
Contractor(s) |
ü |
ü |
|
N/A |
- |
S4.8.1 |
Haul roads will be kept clear of dusty materials and will be sprayed
with water so as to maintain the entire road
surface wet at all times. |
Land site/ During
construction |
Contractor(s) |
|
ü |
|
Implemented, reminder issued |
- |
EIA Reference |
Recommended
Environmental Protection Measures/ Mitigation Measures |
Objectives
of the recommended measures
& main concerns to address |
Implementation Agent |
Implementation Stage |
Implementation status |
Relevant Legislation & Guidelines |
||
D |
C |
O |
||||||
S4.8.1 |
Temporary
stockpiles of dusty materials will be either
covered entirely by impervious sheets or sprayed with water to maintain the entire surface wet
all the time. |
Land site/ During construction |
Contractor(s) |
|
ü |
|
Implemented, reminder issued |
- |
S4.8.1 |
Stockpiles of more than 20 bags of cement, dry pulverised fuel ash
and dusty construction materials will
be covered entirely by
impervious sheeting sheltered on top and 3-
sides. |
Land site/ During
construction |
Contractor(s) |
|
ü |
|
N/A |
- |
S4.8.1 |
All exposed
areas will be kept wet always to minimize dust emission. |
Land site/ During
construction |
Contractor(s) |
|
ü |
|
Implemented, reminder issued |
- |
S4.8.1 |
Ultra-low-sulphur diesel
(ULSD) will be used for all construction
plant on-site, as defined as diesel fuel containing
not more than 0.005% sulphur by weight) as stipulated in Environment, Transport and
Works Bureau Technical Circular
(ETWB-TC(W)) No 19/2005 on Environmental
Management on Construction Sites. |
Land site/ During construction/ During Operation |
Contractor(s) |
|
ü |
ü |
Implemented |
Environment, Transport and Works
Bureau Technical Circular (ETWB- TC(W)) No 19/2005 on Environmental Management on Construction Sites |
S4.8.1 |
The engine
of the construction equipment during idling
will be switched off. |
Land site/ During
construction |
Contractor(s) |
|
ü |
|
Implemented |
- |
S4.8.1 |
Concrete batching plant will be required on site.
control measures recommended in the
Guidance Note on a Best Practicable
Means for Cement Works (Concrete Batching Plant)
(BPM 3/2 (93)) will be implemented. The control measures recommended in the Guidance Note on a Best Practicable Means for Cement Works
(Concrete Batching Plant) (BPM 3/2
(93)) will be implemented. |
Land site/ During construction |
Contractor(s) |
|
ü |
|
N/A |
- |
S4.8.1 |
Regular maintenance of construction equipment deployed on-site
will be conducted to prevent black smoke emission. |
Land site/ During construction |
Contractor(s) |
|
ü |
|
Implemented |
- |
S4.10 |
To ensure proper implementation of the recommended dust mitigation measures and good
construction site practices during
the construction phase, environmental site audits
on weekly basis is recommended throughout the construction period. |
Land site/ During
construction |
Contractor(s)/ ET & IEC |
|
ü |
|
Implemented |
|
Note: D - Design
stage C - Construction O - Operation
EIA Reference |
Recommended Environmental Protection Measures/ Mitigation Measures |
Objectives of the
recommended measures & main concerns to address |
Implementation Agent |
Implementation Stage |
Implementation status |
Relevant Legislation & Guidelines |
||
D |
C |
O |
||||||
Noise |
||||||||
S5.7 |
Only well-maintained plant will be operated on-site and plant will be serviced regularly during
the construction phase. |
All area/
During construction |
Contractor(s) |
|
ü |
|
Implemented |
A Practical Guide
for the Reduction of Noise
from Construction Works |
S5.7 |
Silencers or mufflers on construction equipment
will be utilised
and will be properly maintained during the
construction phase. |
Noise control/ During construction |
Contractor(s) |
|
ü |
|
N/A |
|
S5.7 |
Mobile plant, if any, will be sited as far away
from NSRs as possible. |
Noise control/ During construction |
Contractor(s) |
|
ü |
|
N/A |
|
S5.7 |
Machines and plant (such as trucks) that may be in intermittent use will be shut down between
work periods or will be throttled down to a minimum. |
Noise control/ During construction |
Contractor(s) |
|
ü |
|
Implemented |
|
S5.7 |
Plants known to emit noise strongly in one
direction will, wherever possible,
be orientated so that the noise is directed
away from the nearby NSRs. |
Noise control/ During construction |
Contractor(s) |
|
ü |
|
N/A |
|
S5.7 |
Material stockpiles and other structures will be effectively utilised, wherever practicable, in screening noise
from on- site construction activities. |
Noise control/ During construction |
Contractor(s) |
|
ü |
|
N/A |
|
S5.7 |
Use of Quite Powered Mechanical Equipment
(QPME). |
Noise control/ During construction |
Contractor(s) |
|
ü |
|
Implemented |
|
S5.7 |
Movable noise barriers of 3m in height with skid
footing should be used and located
within a few metres of stationary plant and mobile plant
such that the line of sight to the NSR is blocked by the barriers.
The length of the barrier should
be at least five times
greater than its
height. The noise barrier
material should have a superficial surface density
of at least 7 kg
m-2 and have no o or gappeningss. |
Noise control/ During construction |
Contractor(s) |
|
ü |
|
N/A |
|
S5.7 |
The noise insulating sheet should be deployed such that there would be no opening or gaps on the
joints. |
Noise control/ During construction |
Contractor(s) |
|
ü |
|
N/A |
|
S5.7 |
Construction activities (e.g. excavation/shoring, reinstatement (asphalt), and pipe jacking) will be planned
and carried out in sequence, such that items of PME proposed for these activities will not be operated simultaneously. |
Noise control/ During construction |
Contractor(s) |
ü |
ü |
|
Implemented |
EIA Reference |
Recommended Environmental Protection Measures/ Mitigation Measures |
Objectives of the
recommended measures & main concerns to address |
Implementation Agent |
Implementation Stage |
Implementation status |
Relevant Legislation & Guidelines |
||
D |
C |
O |
||||||
S5.7 |
PMEs will not be used at the works
areas near educational institutions with residual impact (ie
the ¡§influence area¡¨ within a radius of 40m) during
school hours in order to reduce impact to the educational institutions. |
Noise control / During
construction |
Contractor(s) |
|
ü |
|
N/A |
|
S5.7 |
Noise enclosures or acoustic sheds
would be used to cover
stationary PME such as generators. Portable/Movable noise enclosure made of material with
superficial surface density of at least
7 kg m-2 may be used for screening the noise from operation of the saw/groover, concrete. |
Noise control/
Pre- construction/ During
construction |
Contractor(s) |
ü |
ü |
|
N/A |
- |
S5.9 |
Sawcutting pavement,
breaking up of pavement, excavation /shoring, pipe laying,
backfilling, reinstatement (concrete) and
pipe jacking shall
be scheduled outside the examination period. |
Noise control/
Pre- construction/ During
construction |
Contractor(s) |
ü |
ü |
|
N/A |
-- |
S5.9 |
In view the duration of noise exceedance at
Creative Secondary School, PLK Laws Foundation College, TKO Kei Tak Primary School and School of
Continuing and Professional
Studies-CUHK is limited to 8 weeks, the construction
work in the influence areas near the four schools
shall be scheduled during long school holidays (e.g., summer
holiday, Easter holiday
or Christmas holiday, etc.) as far as practicable. Scheduling the construction work for the four
schools. |
Noise control/
Pre- construction/ During
construction |
Contractor(s) |
ü |
ü |
|
N/A |
- |
S5.10 |
A noise
monitoring programme shall be implemented for the construction phase. |
Designated monitoring stations as defined in EM&A Manual/During construction phase |
ET |
|
ü |
|
N/A |
- |
S5.10 |
The effectiveness of on-site control
measures could also be evaluated through the regular site
audits. |
All facilities/ During construction |
Contractor(s)/ ET & IEC |
|
ü |
|
Implemented |
- |
Note: D - Design
stage C - Construction O - Operation
EIA Reference |
Recommended Environmental Protection Measures/ Mitigation Measures |
Objectives of the
recommended measures & main concerns to address |
Implementation Agent |
Implementation Stage |
Implementation status |
Relevant Legislation & Guidelines |
||
D |
C |
O |
||||||
Water Quality |
||||||||
S6.9 |
Dredged marine sediment will be disposed of in a gazetted marine
disposal area in accordance with marine dumping permit conditions of
the Dumping at Sea Ordinance (DASO). |
Marine Dredging/ During construction |
Contractor(s) |
|
ü |
|
Implemented |
Dumping at Sea Ordinance (DASO) |
S6.9 |
Disposal vessels will be fitted
with tight bottom seals in order
to prevent leakage of material during transport. |
Marine Dredging/ During construction |
Contractor(s) |
|
ü |
|
Implemented |
- |
S6.9 |
Barges will be filled to a level,
which ensures that material does not spill
over during transport to the disposal site and that adequate freeboard is maintained to ensure that the decks are not washed by wave action. |
Marine Dredging/ During construction |
Contractor(s) |
|
ü |
|
Implemented |
- |
S6.9 |
After dredging,
any excess materials will be
cleaned from decks and exposed
fittings before the vessel is moved from the
dredging area. |
Marine Dredging/ During construction |
Contractor(s) |
|
ü |
|
Implemented |
- |
S6.9 |
All vessels should
be well maintained and inspected before
use to limit any potential discharges to the marine environment. |
Marine Dredging/ During construction |
Contractor(s) |
|
ü |
|
Implemented |
- |
S6.9 |
All vessels
must have a clean ballast
system. |
Marine Dredging/ During construction |
Contractor(s) |
|
ü |
|
Implemented |
- |
S6.9 |
No discharge of sewage/grey wastewater should be allowed. Wastewater from potentially
contaminated area on working vessels should be minimized
and collected. These
kinds of wastewater should be brought back to port
and discharged at appropriate collection
and treatment system. |
Marine Dredging/ During construction |
Contractor(s) |
|
ü |
|
Implemented |
- |
S6.9 |
No soil
waste is allowed
to be disposed overboard. |
Marine Dredging/ During construction |
Contractor(s) |
|
ü |
|
N/A |
- |
EIA Reference |
Recommended Environmental Protection Measures/ Mitigation Measures |
Objectives of the
recommended measures & main concerns to address |
Implementation Agent |
Implementation Stage |
Implementation status |
Relevant Legislation & Guidelines |
||
D |
C |
O |
||||||
S6.9 |
Silt
removal facilities such as silt traps or sedimentation facilities will be provided to remove silt particles from runoff to meet the requirements of the TM standard under
the WPCO. The design of silt removal
facilities will be based on the guidelines provided in ProPECC PN 1/94. All drainage
facilities and erosion and sediment
control structures will be inspected on a regular basis and maintained to confirm proper and efficient operation at all times and particularly during rainstorms. Deposited silt and grit
will be removed regularly. |
Land site & drainage/ During construction |
Contractor(s) |
|
ü |
|
Implemented reminder issued |
ProPECC PN 1/94 TM Standard under
the WPCO |
S6.9 |
Earthworks to form the final
surfaces will be followed up with
surface protection and drainage works to prevent erosion caused by rainstorms. |
Land site & drainage/ During construction |
Contractor(s) |
|
ü |
|
Implemented |
- |
S6.9 |
Appropriate surface
drainage will be designed and provided
where necessary. |
Land site & drainage/ During construction |
Contractor(s) |
|
ü |
|
Implemented |
- |
S6.9 |
The precautions to be taken at any time of year
when rainstorms are likely together with the actions to be taken
when a rainstorm is imminent or forecasted and actions to be taken
during or after
rainstorms are summarized in Appendix A2 of ProPECC PN 1/94. |
Land site & drainage/ During construction |
Contractor(s) |
ü |
ü |
|
Implemented |
ProPECC PN 1/94 |
S6.9 |
Oil interceptors will be provided in the drainage
system where necessary and
regularly emptied to prevent the release
of oil and grease into the storm water drainage system after accidental spillages. |
Land site & drainage/ During construction |
Contractor(s) |
|
ü |
|
N/A |
- |
S6.9 |
Temporary and permanent drainage pipes and
culverts provided to facilitate
runoff discharge, if any, will be adequately
designed for the controlled release of storm
flows. |
Land site & drainage/ During construction |
Contractor(s) |
|
ü |
|
Implemented |
- |
S6.9 |
The temporary diverted drainage, if any, will be reinstated to the original condition when the
construction work has finished or
when the temporary diversion is no longer required. |
Land site & drainage/ During construction |
Contractor(s) |
|
ü |
|
N/A |
- |
EIA Reference |
Recommended Environmental Protection Measures/ Mitigation Measures |
Objectives of the
recommended measures & main concerns to address |
Implementation Agent |
Implementation Stage |
Implementation status |
Relevant Legislation & Guidelines |
||
D |
C |
O |
||||||
S6.9 |
Appropriate numbers of portable toilets shall be provided by a licensed contractor to serve
the construction workers over the construction site to prevent direct disposal of sewage into the water environment. |
Land site & drainage/ During construction |
Contractor(s) |
|
ü |
|
Implemented |
- |
S6.9 and S6.12 |
The sterilization water
should be dechlorinated with total residual chlorine (TRC) level below 1
mg/L before discharge to public
sewer. In situ testing of TRC should also be conducted for the discharge of
chlorinated water for pipeline
disinfection to ensure sufficient dichlorination before discharge to public sewer. |
Sterilization of water mains prior to commissioning |
Contractor(s) |
|
ü |
ü |
Implemented |
Technical Memorandum for Effluents Discharged into Drainage and Sewerage Systems |
S6.9 |
The cleaning and flushing water
should also be treated and desilted
to the relevant discharge requirement stipulated in TM-DSS before discharging. |
Sterilization of water mains prior to commissioning |
Contractor(s) |
|
ü |
ü |
Implemented, observation issued |
Technical Memorandum for Effluents Discharged into Drainage and |
S6.9 |
Site drainage should be well maintained, and good construction practices should be
observed to ensure that oil, fuels, solvents and other chemicals are managed, stored and handled properly
and do not enter the nearby water streams. |
Land site & drainage/ During construction/ During
operation |
Contractor(s) |
|
ü |
ü |
Implemented, reminder issued |
- |
S6.12 |
Regular site inspections will be carried out in
order to confirm that regulatory
requirements are being met and that
contractors are implementing the standard site practice and mitigation measures as proposed to reduce potential impacts to water quality. |
During construction |
Contractor(s)/ ET & IEC |
|
ü |
|
Implemented, reminder issued |
- |
Note: D - Design
stage C - Construction O -
Operation
EIA Reference |
Recommended Environmental Protection Measures/ Mitigation Measures |
Objectives of the
recommended measures & main concerns to address |
Implementation Agent |
Implementation Stage |
Implementation Status |
Relevant Legislation & Guidelines |
||
D |
C |
O |
||||||
Waste Management |
||||||||
S8.5 |
Nomination of approved personnel to be responsible
for standard site practices,
arrangements for collection and effective
disposal to an appropriate facility of all wastes generated at the site. |
Contract mobilization/ During construction |
Contractor(s) |
|
ü |
|
Implemented |
- |
S8.5 |
Training of site personnel in proper waste
management and chemical handling
procedures. Training will be provided
to workers on the concepts of
site cleanliness and appropriate
waste management procedures, including waste
reduction, reuse and recycling at the beginning of the construction works. |
Contract mobilization/ During construction |
Contractor(s) |
|
ü |
|
Implemented |
- |
S8.5 |
Provision of sufficient waste disposal
points and regular collection for
disposal. |
All area/ During construction/ During operation |
Contractor(s) |
|
ü |
ü |
Implemented, reminder issued |
DEVB TC(W) No. 8/2010, Enhanced Specification for Site Cleanliness and Tidiness. |
S8.5 |
Appropriate measures to reduce windblown litter and dust transportation of waste by either covering trucks
or by transporting wastes in
enclosed containers. |
All area/ During construction |
Contractor(s) |
|
ü |
|
Implemented |
|
S8.5 |
A waste management plan (WMP) as stated
in the ¡§ETWB TC(W) No. 19/2005, Environmental
Management on Construction Sites¡¨ for
the amount of waste generated, recycled and disposed of (including the disposal sites)
will be established and
implemented during the
construction phase as part of the Environmental Management Plan (EMP). The Contractor will be required to prepare the EMP and submits it to the Architect/ Engineer under the Contract for approval prior to
implementation. |
All area/ During construction |
Contractor(s) |
|
ü |
|
Implemented |
|
S8.5 |
Separation of chemical wastes for special handling
and appropriate treatment at the
Chemical Waste Treatment Centre at Tsing Yi. |
All area/ During construction |
Contractor(s) |
|
ü |
|
Implemented |
Chapters 2 & 3 Code of Practice on the Packaging, Labelling & Storage
of Chemical Wastes
published under the Waste
Disposal Ordinance (Cap 354), Section 35 |
EIA Reference |
Recommended Environmental Protection Measures/ Mitigation Measures |
Objectives of the
recommended measures & main concerns to address |
Implementation Agent |
Implementation Stage |
Implementation Status |
Relevant Legislation & Guidelines |
||
D |
C |
O |
||||||
S8.5 |
Regular cleaning and maintenance programme for drainage
systems, sumps and oil interceptors. |
Land site/ During construction |
Contractor(s) |
|
ü |
|
Implemented, reminder issued |
Waste Disposal Ordinance (Cap 354) |
S8.5 |
A recording system for the amount of wastes
generated/ recycled and disposal sites.
The trip- ticket
system will be included
as one of the contractual requirements and
implemented by the contractor(s). |
Land site/ During construction |
Contractor(s) |
|
ü |
|
Implemented |
DEVB TC(W) No. 6/2010, Trip Ticket System for Disposal of Construction & Demolition Materials |
S8.5 |
Prior to disposal of construction waste, wood,
steel and other metals will be
separated to the extent practical, for re-use and/or
recycling to reduce
the quantity of waste to be
disposed of to landfill. |
All areas/ During construction |
Contractor(s) |
|
ü |
|
Implemented |
|
S8.5 |
Segregation and storage of different types of
waste in different containers, skips or stockpiles to enhance reuse or recycling of material and their proper
disposal. |
Land site/
During construction/ During
operation |
Contractor(s) |
|
ü |
|
Implemented, reminder issued |
WBTC 32/92, The Use
of Tropical Hard Wood on Construction Site |
S8.5 |
Use of reusable non-timber formwork to reduce
the amount of C&D
materials. |
All areas/ During construction |
Contractor(s) |
|
ü |
|
Implemented |
|
S8.5 |
Encourage collection of aluminium cans and
waste paper by individual collectors during construction with separate labelled bins provided to segregate
these wastes from other general
refuse by the workforce. |
Land site/ During construction |
Contractor(s) |
|
ü |
|
Implemented |
ETWB TCW No. 33/2002, Management of Construction and Demolition Material Including Rock |
S8.5 |
Any unused chemicals and those with remaining functional capacity will be recycled as far as possible. |
Land site/ During construction |
Contractor(s) |
|
ü |
|
N/A |
- |
S8.5 |
Proper storage
and site practices to reduce the potentialfor damage
or contamination of construction materials. |
All areas/ During construction |
Contractor(s) |
|
ü |
|
Implemented, reminder issued |
- |
S8.5 |
Plan and stock construction materials carefully to reduce
amount of waste generated and avoid unnecessary generation of waste. |
All areas/ During construction |
Contractor(s) |
|
ü |
|
Implemented |
- |
EIA Reference |
Recommended Environmental Protection Measures/ Mitigation Measures |
Objectives of the
recommended measures & main concerns to address |
Implementation Agent |
Implementation Stage |
Implementation Status |
Relevant Legislation & Guidelines |
||
D |
C |
O |
||||||
S8.5 |
A Sediment Quality Report (SQR) for sampling and chemical testing of the sediment will be
prepared and submitted to the EPD for approval. The approved
detailed sampling and chemical testing will be carried out prior
to the commencement of the dredging activities to confirm the sediment disposal method. |
Marine works/ During construction |
Contractor(s) |
|
ü |
|
N/A |
ETWB TC(W) No. 34/2002 and Dumping
at Sea Ordinance (DASO) |
S8.5 |
The management of dredged/
excavated sediment management requirement from ETWB TC(W) No. 34/2002 will be incorporated in the Specification of the Contract Documents. |
Marine works/ During construction |
WSD/ Contractor(s) |
|
ü |
|
Implemented |
|
S8.5 |
The contractor will open a billing account with
EPD in accordance with the Waste
Disposal (Charges for Disposal of Construction Waste) Regulation for
the payment of disposal charges. |
Contract mobilisation/ During construction |
Contractor(s) |
|
ü |
|
Implemented |
Cap 354N Waste Disposal (Charges for Disposal of Construction Waste) Regulation |
S8.5 |
A trip-ticket system
will be established in accordance with DEVB
TC(W) No. 6/2010 to monitor the reuse of surplus excavated materials off-site and
disposal of construction waste and general refuse at transfer facilities/
landfills, and to
control fly-tipping. |
Contract mobilisation/ During construction |
Contractor(s) |
|
ü |
|
Implemented |
DEVB TC(W) No. 6/2010, Trip Ticket
System for Disposal of Construction & Demolition Materials |
S8.5 |
The project proponent will also conduct
regular inspection of the waste management measures implemented on site as
described in the Waste Management Plan. |
All area/ During construction |
Contractor(s)/ ET/ IEC |
|
ü |
|
Implemented |
ETWB TC(W) No. 19/2005, Environmental Management on Construction Sites |
S8.5 |
A recording system
(similar to summary
table as shown
in Annex 5 and Annex 6 of
Appendix G of ETWB TC(W) No. 19/2005) for the amount
of waste generated, recycled and disposed of (including the disposal sites) will be established during the construction phase. |
All area/ During construction |
Contractor(s) |
|
ü |
|
Implemented |
Annex 5 and Annex
6 of Appendix G of ETWB
TC(W) No. 19/2005 |
S8.5 |
Inert C&D materials (public
fill) will be reused within
the Project as far as
practicable. |
All area/ During construction |
Contractor(s) |
|
ü |
|
Implemented |
- |
EIA Reference |
Recommended Environmental Protection Measures/ Mitigation Measures |
Objectives of the
recommended measures & main concerns to address |
Implementation Agent |
Implementation Stage |
Implementation Status |
Relevant Legislation & Guidelines |
||
D |
C |
O |
||||||
S8.5 |
Public fill
and construction waste
shall be segregated and stored in different containers or skips to facilitate reuse
or recycling of materials
and their proper disposal. |
All area/ During construction |
Contractor(s) |
|
ü |
|
Implemented |
- |
S8.5 |
Specific areas of the work site will be designated for
such segregation and storage
if immediate use is not practicable. |
All area/ During
construction |
Contractor(s) |
|
ü |
|
Implemented |
- |
S8.5 |
To reduce the potential dust and water quality impacts of site formation works, C&D materials
will be wetted as quickly as possible to the extent
practice after filling. |
All area/ During construction |
Contractor(s) |
|
ü |
|
Implemented |
Air Pollution Control (Construction Dust) Regulation (Cap
311R); WPCO (Cap 358) |
S8.5 |
Open stockpiles of excavated/ fill materials or construction wastes on-site should
be covered with tarpaulin or similar fabric. |
Land site/
During Construction, particularly dry
season |
Contractor(s) |
|
ü |
|
Implemented, rectified after
observation |
Air Pollution Control (Construction Dust) Regulation (Cap 311R) |
S8.5 |
Chemical waste container shall be suitable for the substance they are holding, resistant to
corrosion, maintained in a good
condition, and securely closed. |
All area/ During construction/ During operation |
Contractor(s)/ WSD |
|
ü |
ü |
Implemented, reminder issued |
Waste Disposal (Chemical Waste)
(General) Regulation; Code of Practice on the Packaging, Handling and Storage of Chemical Wastes |
S8.5 |
Chemical waste container shall have a capacity of less than 450 L unless the
specifications have been
approved by the EPD. |
All area/ During construction/ During operation |
Contractor(s)/ WSD |
|
ü |
ü |
Implemented |
|
S8.5 |
A label in English and Chinese shall be displayed
on the chemical container in accordance with instructions prescribed in Schedule 2 of the
Regulations. |
All area/ During construction/ During operation |
Contractor(s)/ WSD |
|
ü |
ü |
Implemented, rectified after observed issued |
|
S8.5 |
Storage areas
for chemical waste shall be enclosed on at least 3 sides. |
All
area/ During construction/ During operation |
Contractor(s)/ WSD |
|
ü |
ü |
Implemented |
|
S8.5 |
Storage areas for chemical waste shall have an impermeable floor and bunding, of
capacity to accommodate 110% of the volume of the largest
container or 20% by volume
of the chemical waste stored in that area, whichever is the greatest. |
All area/ During construction/ During operation |
Contractor(s)/ WSD |
|
ü |
ü |
Implemented |
|
S8.5 |
Storage areas
for chemical waste
shall have adequate ventilation. |
All area/ During construction/ During operation |
Contractor(s)/ WSD |
|
ü |
ü |
Implemented |
EIA Reference |
Recommended Environmental Protection Measures/ Mitigation Measures |
Objectives of the
recommended measures & main concerns to address |
Implementation Agent |
Implementation Stage |
Implementation Status |
Relevant Legislation & Guidelines |
||
D |
C |
O |
||||||
S8.5 |
Storage areas for chemical waste shall be covered
to prevent rainfall entering (water
collected within the bund must be tested and disposed of as
chemical waste, if necessary). |
All area/ During construction/ During operation |
Contractor(s)/ WSD |
|
ü |
ü |
Implemented |
|
S8.5 |
Storage areas
for chemical waste
shall be arranged so that incompatible materials are appropriately separated. |
All
area/ During construction/ During operation |
Contractor(s)/ WSD |
|
ü |
ü |
Implemented |
|
S8.5 |
General refuse will be stored in enclosed bins or compaction units separately from
construction and chemical wastes. |
All area/ During construction/ During operation |
Contractor(s)/ WSD |
|
ü |
ü |
Implemented, reminder and observation issued |
|
S8.5 |
Adequate number of waste containers will
be provided to avoid
over-spillage of waste. |
All area/ During construction/ During operation |
Contractor(s)/ WSD |
|
ü |
ü |
Implemented |
DEVB TC(W) No. 8/2010 Enhanced Specification for Site Cleanliness and Tidiness. |
S8.5 |
A reputable waste collector will be employed by
the Contractor to remove general
refuse from the site, separately
from construction and chemical wastes, on a
daily basis to minimise odour,
pest and litter impacts. |
All area/ During construction/ During operation |
Contractor(s)/ WSD |
|
ü |
ü |
Implemented, reminder issued |
- |
S8.5 |
Recycling binswill be provided at strategic locations within the Site to
facilitate recovery of recyclable materials (including aluminium
can, wastepaper, glass bottles and plastic bottles) from the Site.
Materials recovered will be sold
for recycling. |
All area/ During construction/ During operation |
Contractor(s)/ WSD |
|
ü |
ü |
Implemented |
- |
S8.5 |
To avoid
any odour and
litter impact, accurate
number of portable toilets will be provided for workers on-site. |
All area/ During construction |
Contractor(s) |
|
ü |
|
Implemented |
- |
S8.5 |
The burning
of refuse on construction sites
is prohibited by law. |
All area/ During construction |
Contractor(s) |
|
ü |
|
Implemented |
Air Pollution Control Ordinance (Cap
311) |
S8.7 |
To facilitate
monitoring and control
over the contractors¡¦ performance on waste management, a waste inspection and audit programme will be implemented throughout the construction phase. |
All facilities/ During construction |
ET/ IEC |
|
ü |
|
Implemented |
- |
Note: D -
Design stage C - Construction O - Operation
EIA Reference |
Recommended Environmental Protection Measures/ Mitigation Measures |
Objectives of the
recommended measures & main concerns to address |
Implementation Agent |
Implementation Stage |
Implementation Status |
Relevant Legislation & Guidelines |
||
D |
C |
O |
||||||
Ecology |
||||||||
S9.7 |
For slope mitigation works within the Clear Water
Bay Country Park, to avoid tree
felling and damages to trees, the exact locations of the flexible barrier foundation plates, soil
nails and rock
dowels can be adjusted during
detailed design, and a
setback distance from existing
trees is recommended to be maintained as far as practical. A detailed specification describing the exact
locations of the flexible
barrier foundation plates, soil nails and rock dowels will be prepared to illustrate how the setback distance from existing trees
would be implemented for tree avoidance. |
Slope mitigation works area/ During detailed
design/ During construction |
Contractor(s) |
ü |
ü |
|
N/A |
- |
S9.7 |
Pruning of tree canopies along the alignment of the flexible
barriers shall be limited to a minimum. |
Slope mitigation works area/ During construction |
Contractor(s) |
|
ü |
|
N/A |
|
S9.7 |
The alignment of flexible barriers shall be
optimized to preserve all species of conservation interest and minimize the impact to the existing vegetation as far as practicable. All individuals of Marsdenia lachnostoma within the slope mitigation areas shall be retained in- situ,
by positioning the alignment of
flexible barrier at a minimum 1.5m
in a radius away from these individuals. |
Slope mitigation works area/ During detailed
design/ During construction |
Contractor(s) |
ü |
ü |
|
N/A |
- |
S9.7 and 9.10 |
At the detailed design stage prior
to the commencement of the slope
mitigation works, a vegetation
survey shall be carried out at the slope mitigation areas within the Clear Water Bay Country Park
to assess the condition and identify
the location of each individual of Marsdenia lachnostoma and other flora species of conservation
interest that may be directly affected by the
construction works. |
Slope mitigation works area/ During detailed
design/ During construction |
Contractor(s) |
ü |
|
|
Implemented |
- |
S9.7 |
Temporary fencing will be installed to fence off
the concerned species
either in groups
of individually within
the works area and in the close
proximity to prevent
from being damaged and disturbed during
construction. A sign identifying the site shall be attached to the fence and flagging tape shall be attached to the individuals to visualize their locations. |
Slope mitigation works area/ During construction |
Contractor(s) |
|
ü |
|
N/A |
- |
EIA Reference |
Recommended Environmental Protection Measures/ Mitigation Measures |
Objectives of the
recommended measures & main concerns to address |
Implementation Agent |
Implementation Stage |
Implementation Status |
Relevant Legislation & Guidelines |
||
D |
C |
O |
||||||
S9.7 and S9.10 |
A specification for
fencing and demarcating individuals of Marsdenai lachnostoma (or other flora species of conservation interest, if found) adjacent to the proposed alignment of the flexible barriers will be prepared to protect the species. |
Slope mitigation works area/ During construction |
Contractor(s) |
|
ü |
|
N/A |
- |
S9.7 |
Induction training shall also be provided to all
site personnel in order to brief
them on this flora of conservation interest including the locations and their importance. |
Slope mitigation works area/ During construction |
Contractor(s) |
|
ü |
|
N/A |
- |
S9.7 |
The resident site supervisory staff
will closely monitor
the conditions of concernedindividuals during construction of flexible barriers
in the close proximity. |
Slope mitigation works area/ During construction |
Contractor(s) |
|
ü |
|
N/A |
- |
S9.7 |
Erect fences
along the boundary of the works
area before the commencement of works to prevent vehicle movements and encroachment of personnel onto adjacent areas. |
All area/ During construction |
Contractor(s) |
|
ü |
|
Implemented |
- |
S9.7 |
Regularly check
the work site boundaries to ensure that they
are not breached, and that damage
does not occur
to surrounding areas. |
All area/ During construction |
Contractor(s)/ Environmental Team (ET) |
|
ü |
|
Implemented. |
- |
S9.7 |
Avoid any damage
and disturbance, particularly those caused by filling and illegal dumping, to the surrounding habitats through
proper management of waste disposal. |
All area/ During
construction |
Contractor(s) |
|
ü |
|
Implemented |
- |
S9.7 |
Reinstate temporarily affected areas, particularly
the habitats of plantation and
shrubland-grassland immediately
after completion of construction works, through
on-site tree/shrub planting. The
tree/shrub species will
be chosen with
reference to those
in the surrounding area. |
All area/ During construction |
Contractor(s) |
|
ü |
|
N/A |
- |
S9.7 |
Affected habitats within
the Clear Water
Bay Country Bay shall
be reinstated by hydro-seeding and planting
of climbers and native shrub
seedlings where practical upon completion of the slope mitigation works. |
All area/ During construction |
Contractor(s) |
|
ü |
|
N/A |
- |
Note: D - Design
stage C - Construction O -
Operation
EIA Reference |
Recommended Environmental Protection Measures/ Mitigation Measures |
Objectives of the recommended measures & main concerns to address |
Implementation Agent |
Implementation Stage |
Implementation Status |
Relevant Legislation & Guidelines |
||
D |
C |
O |
||||||
Landscape & Visual |
||||||||
S11.10 & 11.11 |
The construction area and area allowed for
temporary structures, such as the
contractor¡¦s office, will be minimized
to a practical minimum. (MM1) |
All area/
Detailed design/ During
construction/ During operation |
WSD/ Contractor(s) |
ü |
ü |
ü |
Implemented |
- |
S11.10 & 11.11 |
At the detailed design stage, the design team will
seek to minimize the
landscape footprint of the Project and above ground facilities, while satisfying all
other requirements. (MM2) |
All area/
Detailed design/ During
construction/ During operation |
WSD/ Contractor(s) |
ü |
ü |
ü |
Implemented |
- |
S11.10 & 11.11 |
Design principles will be adopted to take into
account the surrounding area,
particularly Clear Water Bay Country Park
behind and the nearby waterfront, with due
consideration given to: - green
roofs where practical (i.e. without equipment on the roof); -
roadside planting; -
aesthetic treatment of all structures; -
vertical greening; -
screen planting along
application site; and -
landscape enhancement with
amenity planting where practical
including planting along the edge (site boundary)
fence with native shrubs where feasible, to
reduce their visual impact and blend them into the surrounding landscape. (MM3) |
All area/ Detailed design/ During construction/ During operation |
WSD/ Contractor(s) |
ü |
ü |
ü |
Implemented |
- |
S11.10 & 11.11 |
All trees within the Project Site or the potential
slope mitigation works area will be
carefully protected during construction
according to DEVB TCW No. 10/2013 - Tree Preservation (MM4) |
All area/
Detailed design/ During
construction/ During operation |
WSD/ Contractor(s) |
ü |
ü |
ü |
Implemented, reminder issued |
ETWB TCW No. 3/2006 - Tree Preservation. |
S11.10 & 11.11 |
No tree within
the Country Park will be felled. Trees
within the Site unavoidably
affected by the works will be transplanted where
necessary and practical. For trees that
need to be felled,
compensatory planting will be
provided to the satisfaction of
relevant Government departments. A compensatory tree planting proposal including locations of tree compensation will be submitted
to seek relevant government
department¡¦s approval, in accordance with DEVB
TC(W) No. 10/2013. (MM5) |
All area/ Detailed design/ During construction/ During operation |
WSD/ Contractor(s) |
ü |
ü |
ü |
Implemented |
DEVB TC(W) No. 10/2013 |
EIA Reference |
Recommended Environmental Protection Measures/ Mitigation Measures |
Objectives of the recommended measures & main concerns to address |
Implementation Agent |
Implementation Stage |
Implementation Status |
Relevant Legislation & Guidelines |
||
D |
C |
O |
||||||
S11.10 & 11.11 |
Any slope mitigation works necessary to address
natural terrain hazards, will be
minimized to minimize any potential
environmental impact to the Country Park e.g. soil nailing and rock stabilization will aim to avoid existing trees e.g. should any restoration of vegetation be necessary,
the best planting matrix with
native species will be established,
with the aim of resembling the existing vegetation. (MM6) |
All area/
Detailed design/ During
construction/ During operation |
WSD/ Contractor(s) |
ü |
ü |
ü |
N/A |
|
S11.10 & 11.11 |
Dredging works for the installation of intake
structures and outfall diffusers
should be minimized to avoid or reduce
any potential environmental impacts to as low as reasonably practicable (ALARP). The intake and outfall structures (e.g. intake openings and diffuser heads)
will be prefabricated and transferred to site for installation. (MM7) |
All area/
Detailed design/ During
construction/ During operation |
WSD/ Contractor(s) |
ü |
ü |
ü |
Implemented |
|
S11.10 & 11.11 |
All night-time lighting will be reduced to a
practical minimum both in terms of
number of level and will be hooded and directional. (MM8)
units and lux level and will be hooded and directional. (MM8) |
All area/
Detailed design/ During
construction/ During operation |
WSD/ Contractor(s) |
ü |
ü |
ü |
Implemented |
- |
Note: D - Design
stage C - Construction O -
Operation
EIA Reference |
Recommended
Environmental Protection Measures/ Mitigation Measures |
Objectives of the
recommended measures & main concerns to address |
Implementation Agent |
Implementation Stage |
Implementation Status |
Relevant Legislation & Guidelines |
||
D |
C |
O |
||||||
Landfill Gas
Hazard |
||||||||
S12.7 |
During all works, safety
procedures should be implemented to minimise the risks
of fires and explosions, asphyxiation of workers and toxicity effects resulting from contact with contaminated soil and
groundwater. |
All area/
Detailed design/ During
construction/ During operation |
Contractor(s) |
ü |
ü |
ü |
Implemented |
- |
S12.7 |
During trenching and excavation as well as
creation of confined spaces at near
to or below ground level, precautions
should be clearly laid down and rigidly Gas
detection equipment and
appropriate breathing apparatus should be available
and used when entering confined spaces
or trenches deeper than 1 metre. |
All area/
Detailed design/ During
construction/ During operation |
Contractor(s) |
ü |
ü |
ü |
Implemented |
- |
S12.7 |
The Contractor should make the workers are aware
of potential hazards of working in
confined spaces (any chamber,
manhole or culvert which is large enough to
permit access to personnel). Such
work in confined spaces is controlled by the Factories and Industrial Undertakings (Confined
Spaces) Regulations of the Factories and Industrial
Undertakings Ordinance. Following the Safety
Guide to Working
in Confined Spaces
ensures compliance with the
above regulations. |
All area/
Detailed design/ During
construction/ During operation |
Contractor(s) |
ü |
ü |
ü |
Implemented |
- |
S12.7 |
Safety officers, specifically trained with regard
to landfill gas and leachate
related hazards and the appropriate actions
to take in adverse circumstances, should be
present on the site throughout the works, in particular, when works
are undertaken below
grade. |
All area/
Detailed design/ During
construction/ During operation |
Contractor(s) |
ü |
ü |
ü |
Implemented |
- |
S12.7 |
All personnel who work on site and all visitors to
the site should be made aware of
the possibility of ignition of gas in
the vicinity of the works, the possible presence of contaminated water and the need to avoid
physical contact with
it. |
All area/
Detailed design/ During
construction/ During operation |
Contractor(s) |
ü |
ü |
ü |
Implemented |
- |
S12.7 |
Monitoring for landfill gas should be undertaken
in all excavations, manholes, chambers (particularly during
pipe jacking) and any
confined spaces through the use of an intrinsically
safe portable instrument, appropriately calibrated and capable of measuring the
concentrations of methane. carbon
dioxide and oxygen. |
All area/
Detailed design/ During
construction/ During operation |
Contractor(s) |
ü |
ü |
ü |
Implemented |
- |
EIA Reference |
Recommended
Environmental Protection Measures/ Mitigation Measures |
Objectives of the
recommended measures & main concerns to address |
Implementation Agent |
Implementation Stage |
Implementation Status |
Relevant Legislation & Guidelines |
||
D |
C |
O |
||||||
S12.7 |
Monitoring frequency and areas to be monitored should be specified prior to commencement of
groundwork, either by the Safety Officer, or by an appropriately qualified person. All
measurements should be recorded and documented. |
All area/
Detailed design/ During
construction/ During operation |
Contractor(s) |
ü |
ü |
ü |
Implemented |
- |
S12.7 |
Proceed drilling with adequate care and precautions against the potential hazards which may be encountered. |
All area/
Detailed design/ During
construction/ During operation |
Contractor(s) |
ü |
ü |
ü |
Implemented |
- |
S12.7 |
Prior to the
commencement of the site works, the drilling
contractor should devise a
'method-of- working' statement covering all
normal and emergency procedures (including but not limited to number of operatives,
experience and special skills of
operatives, normal method of operations, emergency
procedures, supervisors responsibilities, storage
and use of safety equipment, safety procedures and signs, barriers and guarding). The site supervisor and all operatives must be familiar with this statement. |
All area/ During construction/ During operation |
Contractor(s) |
ü |
ü |
ü |
Implemented |
- |
S12.7 |
Where below ground service entries are necessary
to the Incoming Switchgear Room,
132 kV Substation and Chlorine Store
(I) and (II),
the entry point
should be sealed
to prevent gas entry. In
addition, any below grade cable trenches entering the Incoming Switchgear Room and 132 kV Substation can become the
pathway for landfill gas and hence grilled
metal covers should
be used. |
All area/
Detailed design/ During
construction/ During operation |
Contractor(s) |
ü |
ü |
ü |
N/A |
- |
S12.7 |
It is recommended regular landfill gas monitoring
should be carried out at the
Incoming Switchgear Room, 132 kV Substation and Chlorine Store (I) and (II). The monitoring frequency will
be monthly for the first
year of operation. If the monitoring
results show no sign of landfill gas migration, reduce
the monitoring frequency to once every six months. |
All area/
Detailed design/ During
construction/ During operation |
Contractor(s) |
ü |
ü |
ü |
N/A |
- |
S12.7 |
The manholes and utility pits within the Project
Site and along the fresh water
mains. Each manhole/ utility pit should
be monitored with two measurements (at mid
depth and base). Each measurement should be
monitored for a minimum of 10 minutes. A steady reading
and peak reading should
be recorded at each manhole/ utility pit |
All area/
Detailed design/ During
construction/ During operation |
Contractor(s) |
ü |
ü |
ü |
Implemented |
- |
EIA Reference |
Recommended
Environmental Protection Measures/ Mitigation Measures |
Objectives of the
recommended measures & main concerns to address |
Implementation Agent |
Implementation Stage |
Implementation Status |
Relevant Legislation & Guidelines |
||
D |
C |
O |
||||||
|
and for each measurement. The need for venting the manhole/
utility pit and further monitoring will be
reviewed after the initial monitoring. |
|
|
|
|
|
|
|
S12.7 |
All construction, operation and maintenance
personnel working on-site as well
as visitors should be made aware of
the hazards of landfill gas and its possible
presence on- site. This should be
achieved through a combination of posting
warning signs in prominent places and also by access to detailed information on landfill gas hazards and the designs and
procedural means by which these
hazards are being minimized on-site. |
All area/
Detailed design/ During
construction/ During operation |
Contractor(s) |
ü |
ü |
ü |
Implemented |
- |
Note: D - Design
stage C - Construction O -
Operation
Appendix D
Water Quality Monitoring Graphical Presentation
- Appendix D.1 Weather Condition
- Appendix D.2 Key Activities Carried Out During the Reporting Quarter
- Appendix D.3 Other Factor Might Affect the Monitoring Results
Key Activities Carried Out During the Reporting Quarter
May 2023
Administration
Building - Installation of glass balustrade, metal cladding, building services, electrical switchboard, lift, cable laying -
carrying out interior finishes at 2/F, 3/F and
4/F -
Construction
of block wall
in the pipe
duct. |
Chemical building -
Installation of handrail, permanent doors,
building services, mechanical equipment, and cable laying -
Underground utility construction work |
Main Electrical &
Central Chiller Plant
Building -
Construction
of fuel tank
room - Installation metal Doors, chillers, building services, electrical switchboard, cable laying |
ActiDAFF - Underground utility construction work - Laying of roof floor screed and tiles - Construction of plinths for saturator tanks - Erection and dismantling of scaffolding, installation of mechanical equipment and piping, bubble test -
Installation
of underdrain |
Product Water Storage
Tank Building -
Resin Injection Work
& Water Test
for 1 Water Tanks -
Installation
of cat ladders in Water Tanks,
and door -
Installation of louvres, metal
cladding, building services, cable laying, mechanical equipment, steel pipe -
Underground
utility construction |
OSCG
Building -
Installation
of Design for Manufacturing and Assembly Panel
and metal door -
Underground utility construction work - Installation of building services and mechanical equipment |
Reverse Osmosis Building -
Installation
of Design for Manufacturing and Assembly Panels
at East Sides - Installation of metal door, metal cladding, hand railings, Louvres & Windows -
Installation
of building services, electrical switchboard, mechanical equipment, steel
pipe, Glass Reinforced Plastics (GRP) pipe and cable laying -
Underground utility construction work |
Post
Treatment Building -
Installation
of Louvres & Windows, metal door and
cat ladders -
Installation
of Design for Manufacturing and Assembly Panels - Installation of building services, mechanical equipment and GRP pipe -
Underground utility construction work |
Inspection corridor - Construction of bondek for segments 7 - construction of staircase 8 |
CO2 Tanks -
Installation
of pipes and building services Outfall Shaft -
GRP Diffuser Pipe installation and rock material back
fill Combined Shaft -
Installation
of building services, electrical equipment, switchboard, cable laying,
mechanical equipment and pipes, stoplogs and band screens -
Underground utility construction work -
Staircases and internal finishing Pump
room -
internal finishing and
screeding Other -
Excavation at slope toe
and access erection, Soil anchor and grouting construction -
Foundation &
structure construction at Elevated Walkway -
Watermain works at CLP 132 kV Substation -
Concrete Breaking, Structure Construction at Seawall |
June 2023
Administration
Building - Installation of glass balustrade, metal cladding, building services, electrical switchboard, lift, cable laying -
carrying out interior finishes at 2/F, 3/F and
4/F -
Construction
of block wall
in the pipe
duct. |
Chemical building -
Installation of handrail, permanent doors,
building services, mechanical equipment, and cable laying -
Underground utility construction work |
Main Electrical &
Central Chiller Plant
Building -
Construction
of fuel tank
room - Installation metal Doors, chillers, building services, electrical switchboard, cable laying |
ActiDAFF - Underground utility construction work - Laying of roof floor screed and tiles - Construction of plinths for saturator tanks - Erection and dismantling of scaffolding, installation of mechanical equipment and piping, bubble test -
Installation
of underdrain |
Product Water Storage
Tank Building -
Resin Injection Work
& Water Test
for 1 Water Tanks -
Installation
of cat ladders in Water Tanks,
and door -
Installation of louvres, metal
cladding, building services, cable laying, mechanical equipment, steel pipe -
Underground
utility construction |
OSCG
Building -
Installation
of Design for Manufacturing and Assembly (DfMA) Panel
and metal door -
Underground utility construction work - Installation of building services and mechanical equipment |
Reverse Osmosis Building -
Installation
of Design for Manufacturing and Assembly(DfMA) Panels at East Sides - Installation of metal door, metal cladding, hand railings, Louvres & Windows -
Installation
of building services, electrical switchboard, mechanical equipment, steel
pipe, Glass Reinforced Plastics (GRP) pipe and cable laying -
Underground utility construction work |
Post
Treatment Building -
Installation
of Louvres & Windows, metal door and
cat ladders -
Installation
of Design for Manufacturing and
Assembly(DfMA) Panels - Installation of building services, mechanical equipment and GRP pipe -
Underground utility construction work |
Inspection corridor - Construction of bondek for segments 7 - construction of staircase 8 |
CO2 Tanks -
Installation
of pipes and building services Outfall Shaft -
GRP Diffuser Pipe installation and rock material backfill Combined Shaft -
Installation
of building services, electrical equipment, switchboard, cable laying,
mechanical equipment and pipes, stoplogs and band screens -
Underground utility construction work -
Staircases and internal finishing Pump
room -
internal finishing and screeding Other -
Excavation works, access
erection, soil anchor
installation and grouting construction works at the slope toe -
Foundation &
structure construction at Elevated Walkway -
Watermain works at CLP 132 kV Substation -
Concrete Breaking, structure construction of Wave Deflector Wall at seawall area |
July 2023
Administration
Building -
Carrying out the floor tiles
works at 1/F and 2/F -
Installation
of building services, cable laying, electrical switchboard, doors and handrails -
Construction
of block wall
in the pipe
duct |
Chemical building -
Installation
of permanent doors -
Underground utility construction work -
Construction
of trunk load
pits |
Main Electrical &
Central Chiller Plant
Building -
Installation
of roof tile for fuel tank room,
chillers, building services, electrical switchboard
and cable laying |
ActiDAFF - Underground utility construction work - Construction of staircase no 2 -
Erection and dismantling of scaffolding, installation of underdrain media and electrical equipment and installation of access covers on
roof |
Product Water Storage
Tank Building -
Resin Injection Work
& Water Test
for 1 Water Tanks -
Installation
of cat ladders in Water Tanks -
Installation of metal cladding, building services, cable
laying, mechanical equipment, steel pipe -
Underground
utility construction -
Sealing slab opening |
OSCG Building -
Installation
of Design for Manufacturing and Assembly (DfMA) Panel
and metal door -
Underground utility construction work - Installation of building services, mechanical equipment, metal cladding and roller shutters and window |
Reverse Osmosis Building -
Installation
of building services, electrical switchboard, mechanical equipment, steel
pipe, Glass Reinforced Plastics (GRP) pipe and cable laying -
Installation
of metal cladding, handrailing and louvers -
Underground utility construction work -
Pipe laying at corridor |
Post Treatment Building -
Installation
of Louvres &
Windows, cat ladders, handrailing and metal
cladding - Installation of building services, mechanical equipment and GRP pipe -
Underground utility construction work |
Inspection corridor - Construction of roof concrete slab and column and wall |
CO2 Tanks -
Installation
of pipes and building services Combined Shaft and Pump room -
Underground utility construction work -
Installation
of door, window
and louver Other -
Watermain works at CLP 132 kV Substation -
Concrete breaking, structure construction of Wave
Deflector Wall at seawall area -
Foundation and staircases construction at elevated walkway -
Foot plinth concreting and barrier erection at flexible barrier |
August 2023
Administration
Building - Carrying out the floor tiles works at 1/F and 2/F - Installation of doors and handrails - Construction of block wall in the pipe duct -
Installation of building
services, cable laying, electrical switchboard |
Chemical building - Installation of permanent doors - Construction of trunk load pits - Underground utility construction work |
Main Electrical &
Central Chiller Plant
Building -
Installation of chillers,
building services, electrical switchboard and cable laying |
ActiDAFF - Underground utility construction work - Installation of access covers on roof - Construction of staircase no 2 -
Erection and dismantling of scaffolding,
installation of underdrain media and electrical equipment and installation of
access covers on roof |
Product Water Storage
Tank Building - Resin Injection Work & Water Test for Chlorine Contact Tank A - Installation of cat ladders in Water Tanks - Installation of metal cladding, building services, cable laying, mechanical equipment, steel pipe - Underground utility construction -
Sealing slab opening |
OSCG
Building - Installation of Design for Manufacturing and Assembly (DfMA) Panel and metal cladding - Underground utility construction work - Installation of building services, mechanical equipment, metal cladding and roller shutters and window |
Reverse Osmosis Building - Installation of building services, electrical switchboard, mechanical equipment, steel pipe, Glass Reinforced Plastics (GRP) pipe, pressure test of the GRP pipe, Membrane Loading, raised floor - Installation of metal cladding, handrailing and louvers - Underground utility construction work -
Pipe laying at corridor |
Post Treatment Building - Installation of louvres, cat ladders, handrailing and metal cladding - Installation of building services, mechanical equipment and GRP pipe -
Underground utility
construction work |
Inspection corridor - Construction of roof concrete slab and column and wall |
CO2 Tanks -
Installation
of pipes and building services Combined Shaft and Pump room -
Underground utility construction work -
Installation
of door, window
and louver Other -
Watermain works at CLP 132 kV Substation -
Concrete breaking, structure construction of Wave
Deflector Wall at seawall area -
Foundation and staircases construction at elevated walkway -
Foot plinth concreting and barrier erection at flexible barrier -
Finial check of Marine Diffuser Pipe |
September
2023
Administration
Building - Carrying out the floor tiles works at 1/F - Installation of building services, cable laying, electrical switchboard, doors and handrails - Construction of 3 dog houses on roof -
Construction of block wall in
the pipe duct |
Chemical building - Construction of concrete slab for safety shower - Installation of leakage collection pit cover -
Underground utility
construction work |
Main Electrical &
Central Chiller Plant
Building -
Installation of roof tile for
fuel tank room, chillers, building services, electrical switchboard and cable
laying |
ActiDAFF - Underground utility construction work - Installation of access covers on roof - Construction of staircase no 2 - Installation of mechanical equipment, piping system, building services, electrical switchboards and cable laying |
Product Water Storage
Tank Building - Installation of Cat Ladders in Water Tank A - Sealing Slab Openings in Water Tank A - Re-construction of Wall PW8 in Water Tank A - Underground utility construction -
Installation of building
services, cable laying, mechanical equipment and steel pipe |
OSCG
Building - Installation of Design for Manufacturing and Assembly (DfMA) Panel, metal cladding and roller shutters and window - Underground utility construction work - Installation of building services, mechanical equipment, metal cladding and roller shutters and window |
Reverse Osmosis Building - Installation of building services, electrical switchboard, mechanical equipment, steel pipe, Glass Reinforced Plastics (GRP) pipe, pressure test of the GRP pipe, Membrane Loading, raised floor - Installation of metal cladding, handrailing, roller shutters and glass canopy and glass house - Underground utility construction work -
Pipe laying at corridor and
Backfilling Work |
Post Treatment Building -
Installation of louvres, cat
ladders, handrailing and metal cladding |
- Installation of building services, mechanical equipment and GRP pipe -
Underground utility
construction work |
Inspection corridor - Construction of roof waterproofing works - Construction of staircase no. 1 and 2 -
Installation of building
services |
CO2 Tanks -
Installation
of pipes and electrical wiring Combined Shaft and Pump room -
Internal finishing,
door, window and louver Other -
Watermain works at CLP 132 kV Substation -
Structure Construction and steel fence
election of Wave
Deflector Wall at seawall area -
Staircases construction at elevated walkway -
Steel Bridge assembly and installation -
Rock anchor installation of slope work -
Marine works completed |
October 2023
Administration
Building - Carrying out the floor tiles works at G/F - Construction of 4 dog houses on the roof. - Construction of block wall in the pipe duct -
Installation of building
services, cable laying, electrical switchboard |
Chemical building - Installation of leakage collection pit cover - Construction of concrete slab for safety showers - Construction of trunk load pits - Underground utility construction work - Defect rectification |
Main Electrical &
Central Chiller Plant
Building - Installation of chillers, building services, electrical switchboard and cable laying -
Installation of Roof Tile for
Fuel Tank Room |
ActiDAFF - Underground utility construction work - Installation of access covers on roof - Construction of staircase no 2 - Installation of mechanical equipment, piping system, installation of building services, electrical switchboards and cable laying |
Product Water Storage
Tank Building - Installation of Cat Ladders in Water Tank A - Sealing slab opening in water Tank A - Re-construction of Wall PW8 in Water Tank A - Installation of metal cladding, building services, cable laying, mechanical equipment, steel pipe -
Underground utility
construction |
OSCG
Building - Installation of Design for Manufacturing and Assembly (DfMA) Panel and metal cladding - Installation of Roller Shutters and Window - Coating and Installation of Grating Cover for Brine Tank - Underground utility construction work -
Installation of building
services, mechanical equipment and cable laying |
Reverse Osmosis Building - Installation of building services, electrical switchboard, mechanical equipment, steel pipe, Glass Reinforced Plastics (GRP) pipe, pressure test of the GRP pipe, Membrane Loading, raised floor - Installation of metal cladding, handrailing, roller shutters, glass canopy and glass house - Underground utility construction work -
Pipe laying at corridor
outside Toilet and Backfilling Work |
Post Treatment Building - Installation of service staircase tower, louvres, cat ladders, handrailing and metal cladding - Installation of building services, Installation of mechanical equipment and piping system -
Underground utility
construction work |
Inspection corridor - Construction of roof waterproofing works - Construction of staircases no. 1 and 2 - Installation of Movement Joints - Construction of Screeding works on the deck level -
Installation of building
services |
CO2 Tanks -
Installation
of pipes and electrical wiring Combined Shaft and Pump room -
Internal finishing, Door;
window; Lover Installation Other -
Watermain works at CLP 132 kV Substation -
Structure Construction, steel
fence erection of Wave Deflector Wall at seawall
area -
Staircases construction; Steel
Bridge assembly and installation at elevated walkway -
Foot plinth concreting and barrier erection at flexible barrier |
November 2023
Administration Building - Carrying out the floor tiles works at G/F - External wall painting works - Construction of block work for pipe duct -
Installation of building
services, cable laying, electrical switchboard, testing and commissioning |
Chemical building - Installation of leakage collection pit cover - Underground utility construction work - Landscape work at roof -
Defect rectification |
Main Electrical &
Central Chiller Plant
Building ¡P
Installation of chillers, building services, electrical switchboard and cable
laying ¡P
Installation of Roof
Tile for Fuel
Tank Room |
ActiDAFF - Underground utility construction work - Installation of access opening cover - Construction of staircase no 2 -
Installation of mechanical
equipment, piping system, installation of building services, electrical
switchboards and cable laying, fiber-reinforced plastic cover Installation |
Product Water Storage Tank Building - Installation of Cat Ladders in Water Tank A - Sealing slab opening in water Tank A - Re-construction of Wall PW8 in Water Tank A - Installation of metal cladding, building services, cable laying, mechanical equipment, steel pipe -
Underground utility
construction |
OSCG Building - Protective Coating for dangerous goods Rooms - Placing Soil Mix at Roof - Installation of Metal Cladding (at East Side) - Installation of Roller Shutters and Window - Underground utility construction work -
Installation of building
services, mechanical equipment and cable laying, testing and commissioning |
Reverse Osmosis Building - Installation of building services, electrical switchboard, cable laying, Installation of mechanical equipment, steel pipe, GRP pipe, raised floor, testing and commissioning - Installation of metal cladding, handrailing, roller shutters, glass canopy and glass house - Underground utility construction work -
Construction of RC External
Wall for Male Toilet |
Post Treatment Building |
- Installation of building services, Installation of mechanical equipment and piping system, Pressure Test - Underground utility construction work - Installation of Cat Ladders in Water Tanks and Metal Cladding -
Placing Soil Mix at Roof |
Inspection corridor - Installation of building services, Lift installation - Construction of roof tiling works and staircases no. 2 -
Installation of Movement
Joints and glass window |
CO2 Tanks -
Installation
of pipes and electrical wiring,
testing and commissioning Combined Shaft and Pump
room -
Finishing, Grating; window; louvre installation
Other -
Watermain works at CLP 132 kV Substation -
Staircases construction; Steel
Bridge assembly and installation at elevated walkway -
Road Construction, Footpath Construction, Landscape Construction, Irrigation System Construction, Water Pressure Test for
Fire Services and Plumbing System in Zone
A, B, C -
Structure Construction, steel
fence erection of Wave Deflector Wall at seawall
area |
December 2023
Administration Building - Landscaping works on roof of building. - External wall aluminum features installation - Finishing works for doghouse. -
Installation of building services,
cable laying, electrical switchboard, Pressure Test, electrical switchboard,
testing and commissioning |
Chemical building - Landscape work at roof - Construction of hose reel cabinet. -
Defect rectification |
Main Electrical &
Central Chiller Plant
Building - Installation of Roof Tile for Fuel Tank Room -
Minor Installation of
building services, electrical switchboard, cable laying, pressure test |
ActiDAFF - Underground utility construction work - Installation of access opening covers for filtered water tank - Carrying out finishing works for staircase no. 3 -
Minor Installation of
mechanical equipment, piping system, building services, electrical
switchboards and cable laying, fiber-reinforced plastic cover Installation |
Product Water Storage Tank Building - Water Test in Tank A - Waterproofing work at Roof Slab on Tank A - Tank A water test and defect rectification -
Installation of building
services, cable laying, Installation of mechanical equipment, steel pipe,
Pressure Test |
OSCG Building - Installation of Railing on Brine Maker Tank - Protective Coating for dangerous goods Rooms -
Installation of building
services, mechanical equipment and cable laying, Lightning Installation,
testing and commissioning |
Reverse Osmosis
Building - Installation of Handrailings - Installation of Glass House - Installation of building services, electrical switchboard, cable laying, Photovoltaic Panel. Minor Installation of mechanical equipment and raised floor, testing and commissioning -
Underground utility
construction work |
Post Treatment Building - Installation of Cat Ladders in Water Tanks - Placing Soil Mix at Roof - Curb Construction for Rescue Opening at Water Tanks -
Installation of building
services, mechanical equipment and piping system, Pressure Test |
Inspection corridor - Construction of roof tiling works - Installation of steel balustrade at roof - Installation of Movement Joints - Installation of glass window -
Installation of building
services, Lift Installation |
CO2 Tanks -
Tank surface cleaning, testing and commissioning Combined Shaft and Pump
room -
Internal finishing, defect
rectification Guard House -
Installation of Building Services -
Workshop construction work Other -
Glass Roof and Glass Canopy
installation at elevated walkway -
Security Fence footing construction work -
Manhole 5 Glass
Reinforced Plastic Pipe
Installation work -
Underground utility rectification work -
Road Construction -
Traffic signage work -
Footpath Construction -
Landscape Construction -
Landscape planting work -
Irrigation System Construction -
Slope work - Shotcreting; Rock
anchor installation, Rock
break -
Water Pressure Test
for Fire Services and Plumbing System -
Traffic signage work |
January 2024
Administration Building - Carrying out the floor tiles works at G/F - External wall painting works - Construction of block work for pipe duct -
Installation of building
services, cable laying, electrical switchboard, testing and commissioning |
Chemical building - Installation of leakage collection pit cover - Underground utility construction work - Landscape work at roof -
Defect rectification |
Main Electrical &
Central Chiller Plant
Building - Installation of chillers, building services, electrical switchboard and cable laying -
Installation of Roof Tile for
Fuel Tank Room |
ActiDAFF - Underground utility construction work - Installation of access opening cover - Construction of staircase no 2 -
Installation of mechanical
equipment, piping system, installation of building services, electrical
switchboards and cable laying, fiber-reinforced plastic cover Installation |
Product Water Storage Tank Building - Installation of Cat Ladders in Water Tank A - Sealing slab opening in water Tank A - Re-construction of Wall PW8 in Water Tank A - Installation of metal cladding, building services, cable laying, mechanical equipment, steel pipe -
Underground utility
construction |
OSCG Building - Protective Coating for dangerous goods Rooms - Placing Soil Mix at Roof - Installation of Metal Cladding (at East Side) and Roller Shutters and Window - Underground utility construction work -
Installation of building
services, mechanical equipment and cable laying, testing and commissioning |
Reverse Osmosis Building - Installation of building services, electrical switchboard, cable laying, Installation of mechanical equipment, steel pipe, Glass Reinforced Plastic pipe, raised floor, testing and commissioning - Installation of metal cladding, handrailing, roller shutters, glass canopy and glass house - Underground utility construction work -
Construction of Reinforced
Concrete External Wall for Male Toilet |
Post Treatment Building - Installation of building services, Installation of mechanical equipment and piping system, Pressure Test - Underground utility construction work - Installation of Cat Ladders in Water Tanks - Installation of Metal Cladding -
Placing Soil Mix at Roof |
Inspection corridor - Installation of building services, Lift installation - Construction of roof tiling works and staircases no. 2 -
Installation of Movement
Joints and glass window |
CO2 Tanks -
Installation
of pipes and electrical wiring,
testing and commissioning Combined Shaft and Pump
room -
Finishing, Grating; window; louvre installation
Other -
Watermain works at CLP 132 kV Substation -
Staircases construction; Steel
Bridge assembly and installation at elevated walkway -
Road Construction, Footpath Construction, Landscape Construction, Irrigation System Construction, Water Pressure Test for Fire
Services and Plumbing System in Zone A,
B, C -
Structure Construction, steel
fence erection of Wave Deflector Wall at seawall
area |
February 2024
Administration Building - Sealing up wall opening - External wall painting works - Construction of block work for pipe duct. - Installation of glass door for laboratory -
Minor Installation of
building services, cable laying and termination, Photovoltaic Panel
Installation, Testing & Commissioning |
Chemical building - Installation of Irrigation system - Construction of hose reel cabinet. -
Defect rectification |
Main Electrical &
Central Chiller Plant
Building - Installation of Roof Tile for Fuel Tank Room -
Minor Installation of
building services, electrical switchboard, cable laying, pressure test |
ActiDAFF - Underground utility construction work - Installation of drainpipe on corridor -
Minor Installation of
mechanical equipment, installation of building services, Minor cable laying
and termination, Installation of Lightning System, Installation of Fiber
Reinforced Polymer Cover Installation, Testing & Commissioning |
Product Water Storage Tank Building - Underground utility construction work - Water Test in Tank A and defect rectification - Waterproofing work at Roof Slab on Tank A - Tank A water test and defect rectification -
Installation of building
services, cable laying and termination, Testing & Commissioning |
OSCG Building - Installation of Railing on Brine Maker Tank - Protective Coating for dangerous goods Rooms -
Installation of building
services, mechanical equipment and cable laying and termination, testing and
commissioning |
Reverse Osmosis Building - Placing Soil Mix at Roof - Installation of Glass House - Underground utility construction work - Installation of building services, electrical switchboard of cable laying and termination, Minor -
Installation of mechanical
equipment and raised floor, testing and commissioning, Photovoltaic Panel
Installation |
Post Treatment Building - Installation of Cat Ladders in Irrigation Tanks - Placing Soil Mix at Roof - Curb Construction for Rescue Opening at Water Tanks -
Minor Installation of
building services, Minor Installation of mechanical equipment, Cable laying
and termination, Pressure Test |
Inspection corridor - Construction of roof tiling - Internal decoration and finishing works -
Installation of building
services, Lift Installation |
CO2 Tanks -
Tank surface cleaning, testing and commissioning Combined Shaft and Pump
room -
CCTV Installation, Installation of Lightning
System, Minor building services Installation, testing and commissioning -
Internal finishing, defect
rectification Guard House -
Installation of Building Services -
Workshop construction work -
Architectural
Builders Works and Finishes
Other -
Master meter Room
Architectural Builders Works
and Finishes -
Open Channel and Wave deflector Wall -
Glass Roof and Glass Canopy
installation at elevated walkway -
Security Fence footing construction work -
Manhole 5 Glass
Reinforced Plastic Pipe
Installation work -
Underground utility rectification work -
Road Construction -
Traffic signage work -
Footpath Construction -
Landscape Construction -
Landscape planting work -
Irrigation System Construction -
Slope work - Shotcreting; Rock
anchor installation, Rock
break -
Water Pressure Test
for Fire Services and Plumbing System -
Open Channel and Wave deflector Wall -
Traffic signage work |
March 2024
OSCG Building - Installation of Promat Board in Skid Room - Installation of Railing on Brine Maker Tank - Installation of building services, mechanical equipment and cable laying and termination, testing and commissioning |
Post Treatment Building - Installation of Cat Ladders in Irrigation Tanks - Placing Soil Mix at Roof - Curb Construction for Rescue Opening at Water Tanks - Minor Installation of building services, Minor Installation of mechanical equipment, Cable laying and termination, Pressure Test |
Inspection corridor - Construction of roof tiling - Internal decoration and finishing works - Installation of building services, Lift Installation |
Combined Shaft and Pump room - CCTV Installation, Installation of Lightning System, Minor building services Installation, testing and commissioning - Internal finishing, defect rectification Guard House - Installation of Building Services - Guard House B Guard House, Workshop construction work Other - Underground utility rectification work (Manhole and Draw pit) ¡V - Watermain installation works at CLP 132 Kv Substation - Security Fence footing construction work - Light Pole installation work - Road Construction - Footpath Construction - Landscape Construction - Irrigation System installation - Water Pressure Test for Fire Services and Plumbing System - Landscape planting work - Traffic signage work - Cladding installation for Elevated Walkway - Slope work ¡VRock anchors installation, Rock break, Concreting - Open Channel and Wave deflector Wall |
April 2024
Administration Building - Installation of signage - Installation of ceiling - Painting works - Installation of sanitary fitting - Installation of vinyl flooring - Installation of Aluminium Fins - Installation of Internal partition wall and ceiling - External wall finishing works - Installation of AP doors and cat ladders - Installation of wood decking - Minor Installation of building services, cable laying and termination, Photovoltaic Panel Installation, Testing & Commissioning |
Chemical building - Roof planting works - Defect rectification |
Main Electrical & Central Chiller Plant Building - Minor Installation of building services, electrical switchboard, cable laying, pressure test - Ladder and Cover installation at Roof |
ActiDAFF - Rectification works for roof tiles - Installation of signage - Minor Installation of mechanical equipment, building services, minor cable laying and termination, Installation of Fibre Reinforced Polymer Cover, Testing & Commissioning |
Product Water Storage Tank Building - Installation of signage - Installation of cladding works - Tiling work at Roof Slab on Tank A - Ladder and Cover installation at Roof - Roof Tiles installation - Minor Installation of building services, cable laying and termination, Testing & Commissioning |
OSCG Building - Installation of Promat Board in Skid Room - Installation of cladding works - Installation of Railing on Brine Maker Tank - Installation of building services, mechanical equipment and cable laying and termination, testing and commissioning |
Reverse Osmosis Building - Installation of AP doors - Installation of sanitary fitting - Sanitary Ware Installation in Toilet - Tiling Work in Toilet - Installation of Water Meter Cabinets - Installation of building services, electrical switchboard of cable laying and termination, - Minor Installation of mechanical equipment and raised floor, testing and commissioning, Photovoltaic Panel Installation |
Post Treatment Building - Installation of Cat Ladders in Irrigation Tanks - Green Roof - Minor Installation of building services, Minor Installation of mechanical equipment, Cable laying and termination, Pressure Test |
Inspection corridor - Installation of cat ladder - Internal decoration and finishing works |
Combined Shaft and Pump room - Minor cable laying and termination, testing and commissioning - Defect rectification Guard House - Installation of Building Services, testing and commissioning Slope Work - Rock Dowel Installation - Buttress Construction - Wire Mesh Laying - Drilling; Rock anchors installation, Rock break, Concreting Other - Watermain installation works at CLP 132 Kv Substation - Underground utility rectification work for Manhole and Draw pit - Underground utility Construction Work for Watermain water - Underground utility repair Work for Sewerage, Watermains work) - Security Fence footing construction work - Light Pole installation work - Road Construction - Footpath Construction - Landscape Construction - Irrigation System installation - Water Pressure Test for Fire Services and Plumbing System - Landscape planting work - Traffic signage work - Workshop construction - Cladding installation for Elevated Walkway |
- Wave deflector Wall |
Other Factor Might Affect the Monitoring Results
Month |
Other Factors might affect the monitoring results |
May 2023 |
N/A |
June 2023 |
N/A |
July 2023 |
N/A |
August 2023 |
N/A |
September 2023 |
N/A |
October 2023 |
N/A |
November 2023 |
N/A |
December 2023 |
N/A |
January 2024 |
N/A |
February 2024 |
N/A |
March 2024 |
N/A |
April 2024 |
N/A |
Appendix E
Site Inspection Proforma
Table E1 Site Inspection Observation Record
Date |
Environmental Observations |
Follow-up Status |
May 2023 |
||
2 May 2023 |
No major environmental deficiency was observed. |
N/A |
9 May 2023 |
No major environmental deficiency was observed. |
N/A |
16 May 2023 |
No major environmental deficiency was observed. |
N/A |
23 May 2023 |
Chemical containers found near the South end of the site near the slope shall be provided with a proper storage or drip tray to prevent leakage. |
Chemical was removed. |
30 May 2023 |
No major environmental deficiency was observed. |
N/A |
June 2023 |
||
6 Jun 2023 |
No major environmental deficiency was observed. |
N/A |
13 Jun 2023 |
No major environmental deficiency was observed. |
N/A |
20 Jun 2023 |
The Contractors are reminded to remove the chemical containers along the haul road of the open channel either proper storage or disposed to avoid possible leakage or contamination. |
The chemical along the haul road was removed. |
27 Jun 2023 |
Chemical containers found near the Chemical Building shall be stored on a drip tray to prevent leakage. |
The chemical was removed. |
July 2023 |
||
4 Jul 2023 |
No major environmental deficiency was observed. |
N/A |
11 Jul 2023 |
No major environmental deficiency was observed. |
N/A |
Date |
Environmental Observations |
Follow-up Status |
18 Jul 2023 |
The Chemical containers found near the R.O. Building shall be stored on a drip tray or proper storage. |
Chemical container near the R.O. Building was removed. |
25 Jul 2023 |
The chemical containers found near the R.O. Building shall store on a drip tray or provide proper storage to prevent leakage. |
Chemical container near the R.O. Building was removed. |
August 2023 |
||
1 Aug 2023 |
No major environmental deficiency was observed. |
N/A |
8 Aug 2023 |
No major environmental deficiency was observed. |
N/A |
15 Aug 2023 |
No major environmental deficiency was observed. |
N/A |
22 Aug 2023 |
No major environmental deficiency was observed. |
N/A |
29 Aug 2023 |
No major environmental deficiency was observed. |
N/A |
September 2023 |
||
5 Sept 2023 |
No major environmental deficiency was observed. |
N/A |
12 Sept 2023 |
No major environmental deficiency was observed. |
N/A |
19 Sept 2023 |
No major environmental deficiency was observed. |
N/A |
26 Sept 2023 |
Chemical container found near the OSCG shall be properly storage. |
Chemical was removed. |
October 2023 |
||
3 Oct 2023 |
No major environmental deficiency was observed. |
N/A |
10 Oct 2023 |
No major environmental deficiency was observed. |
N/A |
17 Oct 2023 |
No major environmental deficiency was observed. |
N/A |
27 Oct 2023 |
No major environmental deficiency was observed. |
N/A |
31 Oct 2023 |
Chemical containers found near the OSCG shall be store on a drip tray to prevent leakage. |
Chemical removed to proper storage area |
Date |
Environmental Observations |
Follow-up Status |
November 2023 |
||
7 Nov 2023 |
No major environmental deficiency was observed. |
N/A |
14 Nov 2023 |
No major environmental deficiency was observed. |
N/A |
21 Nov 2023 |
No major environmental deficiency was observed. |
N/A |
27 Nov 2023 |
No major environmental deficiency was observed. |
N/A |
December 2023 |
||
5 Dec 2023 |
No major environmental deficiency was observed. |
N/A |
12 Dec 2023 |
No major environmental deficiency was observed. |
N/A |
19 Dec 2023 |
No major environmental deficiency was observed. |
N/A |
27 Dec 2023 |
No major environmental deficiency was observed. |
N/A |
January 2024 |
||
2 Jan 2024 |
No major environmental deficiency was observed. |
N/A |
9 Jan 2024 |
No major environmental deficiency was observed. |
N/A |
16 Jan 2024 |
A chemical container found near RO Building without a drip tray, the contractors are reminded to provide a drip tray or proper storage for the chemical containers. |
The chemical container was removed. |
25 Jan 2024 |
No major environmental deficiency was observed. |
N/A |
29 Jan 2024 |
No major environmental deficiency was observed. |
N/A |
February 2024 |
||
7 Feb 2024 |
No major environmental deficiency was observed. |
N/A |
16 Feb 2024 |
No major environmental deficiency was observed. |
N/A |
20 Feb 2024 |
No major environmental deficiency was observed. |
N/A |
Date |
Environmental Observations |
Follow-up Status |
28 Feb 2024 |
No major environmental deficiency was observed. |
N/A |
March 2024 |
||
5 Mar 2024 |
No major environmental deficiency was observed. |
N/A |
12 Mar 2024 |
No major environmental deficiency was observed. |
N/A |
19 Mar 2024 |
No major environmental deficiency was observed. |
N/A |
25 Mar 2024 |
No major environmental deficiency was observed. |
N/A |
April 2024 |
||
2 Apr 2024 |
No major environmental deficiency was observed. |
N/A |
9 Apr 2024 |
No major environmental deficiency was observed. |
N/A |
16 Apr 2024 |
No major environmental deficiency was observed. |
N/A |
23 Apr 2024 |
No major environmental deficiency was observed. |
N/A |
29 Apr 2024 |
No major environmental deficiency was observed. |
N/A |
Appendix F
Waste Flow Table
Name of Department: WSD Contract No.: 13/WSD/17
Monthly
Summary Waste Flow Table for 2023 (year)
Month Actual Quantities of Inert C&D Materials Generated Monthly Actual Quantities of C&D Wastes Generated Monthly Total Quantity Generated Hard Rock and Large Broken Concrete Reused in the Contract Reused in other Projects Disposed as Public Fill Imported Fill Metals Paper/ cardboard packaging Plastics (see Note 3) Chemical Waste Others, e.g. general refuse (in '000kg) (in '000kg) (in '000kg) (in '000kg) (in '000kg) (in '000kg) (in '000 kg) (in '000kg) (in '000kg) (in '000kg) (in '000kg) Jan 3383.820 0.000 0.000 0.000 3383.820 0.000 0.000 0.000 0.000 0.000 143.690 Feb 0.000 0.000 0.000 0.000 0.000 0.000 0.002 0.138 0.010 0.000 115.880 Mar 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 205.410 Apr 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 255.720 May 2088.990 0.000 0.000 0.000 2088.990 0.000 0.000 0.000 0.000 0.000 202.270 Jun 1955.240 0.000 0.000 0.000 1955.240 0.000 0.000 0.000 0.0017 0.000 189.680 Sub-total 7428.050 0.000 0.000 0.000 7428.050 0.000 0.002 0.138 0.012 0.000 1112.650 Jul 121.060 0.000 0.000 0.000 121.060 0.000 0.008 0.150 0.042 0.000 186.110 Aug 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 168.220 Sep 762.550 0.000 0.000 0.000 762.550 0.000 0.000 148.944 0.000 0.000 172.440 Oct 568.600 0.000 0.000 0.000 568.600 0.000 0.000 18.574 0.010 0.000 185.010 Nov 15.430 0.000 0.000 0.000 15.430 0.000 0.000 0.000 0.000 0.000 116.960 Dec 215.220 0.000 0.000 0.000 215.220 0.000 0.000 0.000 0.000 0.000 79.680 Total 9110.910 0.000 0.000 0.000 9110.910 0.000 0.010 167.806 0.064 0.000 2021.070
w
Notes: (1) The performance targets
are given in Section 1.69 of Specification B
(2) The waste flow table shall also include C&D
materials that are specified in the Contract
to be imported for use at the Site.
(3) Plastics refer to plastic
bottles/containers, plastic sheets/
foam from packaging material
Name of Department: WSD Contract No.: 13/WSD/l 7
Monthly Summary
Waste Flow Table for 2024 (year)
w
Month |
Actual Quantities oflnert C&D Materials Generated Monthly |
I Actual Quantities of C&D Wastes
Generated Monthly |
||||||||||
Total Quantity Generated |
Hard Rock and Large Broken Concrete |
Reused in the Contract |
Reused in other Projects |
Disposed as Public
Fill |
Imported Fill |
Metals I Paper/
cardboarId Plastics packagmg (see Note 3) |
Chemical WastIe Others, e.g. general refuse |
|||||
I (in '000kg) I (in '000kg) I (in '000kg) I (in '000kg) I (in '000kg) I (in '000kg) II (in '000 kg) I (in '000kg) I (in '000kg) I (in '000kg) I (in '000kg) |
||||||||||||
Jan |
4978.345 |
0.000 |
0.000 |
4667.745 |
310.600 |
0.000 |
0.000 |
0.000 |
0.000 |
0.000 |
77.800 |
|
Feb |
22561.796 |
0.000 |
0.000 |
21883.006 |
678.790 |
0.000 |
0.000 |
0.000 |
0.000 |
0.000 |
53.480 |
|
Mar |
81.140 |
0.000 |
0.000 |
0.000 |
81.140 |
0.000 |
0.000 |
0.000 |
0.000 |
0.000 |
52.260 |
|
Apr |
57.130 |
0.000 |
0.000 |
0.000 |
57.130 |
0.000 |
0.000 |
0.000 |
0.000 |
0.000 |
47.390 |
|
May |
|
|
|
|
|
|
|
|
|
|
|
|
Jun |
|
|
|
|
|
|
|
|
|
|
|
|
Sub-total |
27678.411 |
0.000 |
0.000 |
26550.751 |
1127.660 |
0.000 |
0.000 |
0.000 |
0.000 |
0.000 |
230.930 |
|
Jul |
|
|
|
|
|
|
|
|
|
|
|
|
Aug |
|
|
|
|
|
|
|
|
|
|
|
|
Sep |
|
|
|
|
|
|
|
|
|
|
|
|
Oct |
|
|
|
|
|
|
|
|
|
|
|
|
Nov |
|
|
|
|
|
|
|
|
|
|
|
|
Dec |
|
|
|
|
|
|
|
|
|
|
|
|
Total |
27678.411 |
0.000 |
0.000 |
26550.751 |
1127.660 |
0.000 |
0.000 |
0.000 |
0.000 |
0.000 |
230.930 |
|
Notes: (I) The performance targets are given in Section 1.69 of
Specification B
(2) The waste flow table shall also include C&D materials that are specified in the Contract to be imported for use at
the Site.
(3) Plastics refer to plastic bottles/containers, plastic sheets/ foam from packaging material
* The record in EPD Transaction Records system was up to 19/04/2024, the data from 20/4 to 30/4 will be updated
in next reporting
period
Appendix G
Summary of Exceedances
Table G1 Cumulative Statistics on Exceedances
Environmental Monitoring |
Parameter |
No. of non-Project related exceedance in the reporting period |
Total No. of non- Project related exceedance in the reporting period |
No. of Project related exceedance in the reporting period |
Total No. of Project related exceedance in the reporting period |
Total No. recorded since the project commencement |
||
AL |
LL |
AL |
LL |
|||||
Noise |
Leq (30min) |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
Water Quality |
DO |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
Turbidity |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
SS |
271 |
201 |
472 |
0 |
0 |
0 |
2755 |
|
pH |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
Landfill Gas |
O2 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
CH4 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
CO2 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
Appendix H
Complaint Log
Statistical Summary
of Environmental Complaints
Reporting Period |
Environmental Complaint Statistics |
||
Frequency |
Cumulative |
Complaint Nature |
|
1 May 2023 ¡V 30 April 2024 |
1 |
2 |
Air
Quality, Noise and
Water Quality |
Statistical Summary
of Environmental Summons
Reporting Period |
Environmental Summons Statistics |
||
Frequency |
Cumulative |
Details |
|
1 May 2023
¡V 30 April 2024 |
0 |
0 |
N/A |
Statistical Summary
of Environmental Prosecution
Reporting Period |
Environmental Prosecution Statistics |
||
Frequency |
Cumulative |
Details |
|
1 May 2023
¡V 30 April 2024 |
0 |
0 |
N/A |
Appendix I
Event / Action Plan
Event |
Action |
|||
ET |
IEC |
ER |
Contractor |
|
Action Level |
1.
Carry out investigation to
identify the source and cause of
the complaint/ exceedance(s) 2. Notify
IEC, ER, and Contractor and report the results of investigation to the Contractor, ER and the IEC 3.
Discuss with the Contractor and IEC for remedial
measures required 4. If the complaint is related to the Project, conduct additional monitoring for checking mitigation effectiveness and report the findings and results to the IEC, ER and the Contractor |
1. Review
the analyzed results submitted by
the ET 2. Review
the proposed remedial measures by
the Contractor and advise the ER
accordingly 3. Supervise
the implementation of remedial measures |
1. Confirm receipt
of Notification of Exceedance in
writing 2. Require
Contractor to propose remedial measures for the
analyzed noise problem 3. Ensure remedial
measures are properly implemented |
1. Submit noise
mitigation proposals, if required, to the
IEC and ER 2. Implement noise mitigation
proposals |
Limit Level |
1.
Carry out investigation to identify the source and cause of the exceedance 2.
Notify IEC, ER, Project Proponent, EPD and Contractor 3.
Repeat measurements to confirm findings 4.
Provide investigation report
to IEC, ER, EPD
and Contractor he causes of the exceedances 5.
If the exceedance is related to the Project, assess effectiveness by additional monitoring 6.
Report the remedial action implemented and the additional monitoring results to IEC, EPD, ER and Contractor 7.
If exceedance stops, cease additional monitoring |
1. Review the
analyzed results submitted by the
ET 2. Discuss the
potential remedial measures with
ER, ET Leader and Contractor 3. Review
Contractors remedial actions
whenever necessary to assure their
effectiveness and advise the ER
accordingly 4. Supervise the
implementation of remedial measures |
1. Confirm receipt
of Notification of Exceedance in
writing 2. Require the
Contractor to propose remedial measures for the analyzed noise problem 3. Ensure remedial
measures are properly implemented 4. If exceedance
continues, consider what activity
of the work is responsible and
instruct the Contractor, in
agreement with the Project
Proponent, to stop that activity of
work until the exceedance is abated |
1. Take immediate action to avoid
further exceedance 2. Submit proposals
for remedial actions to IEC and ER within
3 working days of notification 3. Implement the
agreed proposals 4.
Resubmit proposals if problem still not under control 5. Stop the relevant activity of works as determined by the Project Proponent until the exceedance is abated |
Table I2 Event and Action Plan for Water Quality Monitoring
Event |
Action |
|||
ET |
IEC |
Contract(s) |
ER |
|
Action Level being exceeded by one sampling day |
1.
Repeat in situ measurement on the next day of exceedance to confirm findings; 2.
Check monitoring data, plant, equipment and Contractor(s)¡¦s working
methods; 3.
Identify source(s) of impact and record in notification of exceedance; 4.
Inform IEC, Contractor(s) and ER. |
1. Check monitoring
data submitted by ET and Contractor(s)¡¦s working methods; 2. Inform EPD. |
1. Confirm receipt
of notification of exceedance
in writing; 2. Check plant and
equipment and rectify unacceptable
practice |
1. Confirm receipt
of notification of exceedance
in writing. |
Action Level
being exceeded by two or more consecutive
sampling days |
1. Repeat in situ measurement on the next day of exceedance to confirm findings; 2. Check monitoring
data, plant, equipment and
Contractor(s)¡¦s working methods; 3. Identify
source(s) of impact and record in
notification of exceedance; 4. Inform IEC,
Contractor(s) and ER; 5. Discuss with
IEC and Contractor(s) on additional
mitigation measures and ensure that
they are implemented |
1.
Check monitoring data submitted by ET and Contractor(s)¡¦s working
methods; 2. Inform EPD; 3.
Discuss with ET and Contractor(s) on additional
mitigation measures and advise
ER accordingly; 4. Assess the
effectiveness of the implemented mitigation measures |
1.
Confirm receipt of notification of exceedance
in writing; 2.
Check plant and equipment and rectify unacceptable practice; 3.
Consider changes of working methods; 4.
Discuss with ET and IEC on additional mitigation measures and propose them to ER within 3 working days; 5. Implement the
agreed |
1. Confirm receipt
of notification of exceedance in
writing; 2. Discuss with the
IEC on the proposed additional
mitigation measures and agree on
the mitigation measures to be implemented. 3. Ensure
additional mitigation measures are properly
implemented. |
Limit Level being exceeded by one sampling day |
4. Repeat in situ measurement on the next day of exceedance to confirm findings; 5. Check monitoring
data, plant, equipment and
Contractor(s)¡¦s working methods; 6. Identify
source(s) of impact and record in
notification of exceedance; 7.
Inform IEC, Contractor(s) and ER; 8.
Discuss with IEC
and Contractor(s) on additional
mitigation measures and ensure that
they are implemented |
1. Check monitoring
data submitted by ET and Contractor(s)¡¦s working
methods; 2.
Inform EPD; 3. Discuss with ET
and Contractor(s) on additional mitigation measures and advise ER accordingly; 4. Assess the
effectiveness of the implemented mitigation measures. |
1. Confirm receipt
of notification of exceedance
in writing; 2. Check
plant and equipment and rectify
unacceptable practice; 3. Critically
review the need to change working
methods; 4.
Discuss with ET and IEC on additional mitigation measures and propose them to ER within 3 working days; 5. Implement the
agreed |
1. Confirm receipt
of notification of exceedance in
writing; 2. Discuss with the
IEC on the proposed additional
mitigation measures and agree on
the mitigation measures to be implemented. 3. Ensure
additional mitigation measures are properly
implemented. 4.
Request Contractor(s) to critically review the working methods. |
Event |
Action |
|||
ET |
IEC |
Contract(s) |
ER |
|
Limit Level being exceeded by two or more consecutive sampling days |
1. Repeat in situ measurement on the next day of exceedance to confirm findings; 2. Check monitoring
data, plant, equipment and
Contractor(s)¡¦s working methods; 3. Identify
source(s) of impact and record in
notification of exceedance; 4.
Inform IEC, Contractor(s) and ER; 5. Discuss with
IEC and Contractor(s) on additional
mitigation measures and ensure that
they are implemented |
1. Check monitoring
data submitted by ET and Contractor(s)¡¦s working
methods; 2.
Inform EPD; 3. Discuss with ET
and Contractor(s) on additional mitigation measures and advise ER accordingly; 4. Assess the
effectiveness of the implemented mitigation measures. |
1. Confirm receipt
of notification of exceedance
in writing; 2. Check plant and
equipment and rectify unacceptable
practice; 3. Critically
review the need to change working
methods; 4. Discuss with ET
and IEC on additional mitigation
measures and propose them to ER within
3 working days; 5. Implement the agreed
mitigation measures. 6. As directed by ER, slow
down or stop all or part of the marine construction works/ production volume
of the desalination plant
until no exceedance of Limit Level. |
1. Confirm receipt
of notification of exceedance in
writing; 2. Discuss with the
IEC on the proposed additional
mitigation measures and agree on
the mitigation measures to be implemented. 3. Ensure
additional mitigation measures are properly
implemented. 4. Request
Contractor(s) to critically review the working methods; 5. Consider and instruct, if necessary, the Contractor(s) to slow down or to stop all or part of the marine construction works/production volume of
the desalination plant until no exceedance of Limit Level. |