CONTENTS

1.                   Executive Summary....................................................................................................................................................... 1

2.                   Basic Project Information............................................................................................................................................ 1

3.                   Noise...................................................................................................................................................................................... 5

4.                   Water Quality................................................................................................................................................................. 10

5.                   Waste.................................................................................................................................................................................. 15

6.                   Landfill Gas Monitoring.............................................................................................................................................. 16

7.                   SUMMARY OF MONITORING EXCEEDANCE, COMPLAINTS, NOTIFICATION OF SUMMONS AND PROSECUTIONS............................................................................................................................................................ 17

8.                   EM&A Site Inspection.................................................................................................................................................. 19

9.                   Conclusions and Recommendations.................................................................................................................... 20

 

 

Appendix A              Master Programme

 

Appendix B              Overview of Desalination Plant in Tseung Kwan O

 

Appendix C              Summary of Implementation Status of Environmental Mitigation

 

Appendix E              Event/Action Plan for Noise Exceedance

Appendix F              Event/Action Plan for Water Quality Exceedance

Appendix G              Waste Flow Table

Appendix H             Complaint Log

 

 

 

EXECUTIVE SUMMARY

 

INTRODUCTION

 

A1.      The Project, Design, Build and Operate First Stage of Tseung Kwan O Desalination Plant (TKODP), is a Designated Project under the Environmental Impact Assessment Ordinance (Cap. 499) (EIAO) and is currently governed by a Further Environmental Permit (EP No. FEP - 01/503/2015/A) for the construction and operation of the Project.

 

A2.      In accordance with the Updated Environmental Monitoring and Audit (EM&A) Manual for the Project, EM&A works for marine water quality, noise, waste management and ecology should be carried out by Environmental Team (ET), Acuity Sustainability Consulting Limited (ASCL), during the construction phase of the Project.

 

A3.      This is the 1st Quarterly EM&A Report, prepared by ASCL, for the Project summarizing the monitoring results and audit findings of the EM&A programme at and around Tseung Kwan O Area 137 (TKO 137) during the reporting period from 16 Mar 2020 to 31 May 2020.

 

A4.      The EM&A programme for this contract has covered environmental monitoring on construction noise level at selected NSRs and Contractor¡¦s environmental performance auditing in the aspects of construction dust, construction noise, water quality, waste management, Landscape and Visual and Ecology.

 

SUMMARY OF MAIN WORKS UNDERTAKEN & KEY MITIGATION MEASURES IMPLEMENTED

 

A5.      Key activities carried out in this reporting period for the Project included the following:

-                 Plate Load Test;

-                 Land Survey;

-                 Ground Levelling;

-                 Ground Investigation;

-                 Access Road Construction;

-                 Site office formation work and footing;

-                 Earth mat installation at 132kV substation;

-                 Construction of 132kV substation footing;

-                 Construction of Temp 11kV substation;

-                 Ducts laying for temp 11kV substation;

-                 Preboring for ELS installation at combine shaft;

-                 Excavation for combined shaft;

-                 Site Investigation in Sea;

-                 Installation of temporary watermain.

 

 


A6.      The major environmental impacts brought by the above construction works include:

-                 Construction dust and noise generation from the ground investigation works, access road construction and site office formation;

-                 Waste generation from the construction activities

 

A7.      The key environmental mitigation measures implemented for the Project in this reporting period associated with the above construction works include:

-                 Dust suppression by regular wetting and water spraying for construction works

-                 Reduction of noise from equipment and machinery on-site

-                 Sorting and storage of general refuse and construction waste

 

SUMMARY OF EXCEEDANCE & INVESTIGATION & FOLLOW-UP

 

A8.      No noise monitoring was conducted during the reporting period since there are no project- related construction activities undertaken within a radius of 300m from the monitoring locations. No project-related exceedance of the Action Level was recorded during the reporting period.

 

A9.      No impact water quality monitoring was conducted in the reporting period since the commencement of marine construction and dredging activities for the Project are scheduled in November 2020 the earliest. No project-related exceedance of the Action Level was recorded during the reporting period.

 

A10.   Weekly site inspections of the construction works were carried out by ET to audit the mitigation measures implementation status. Bi-weekly joint site inspections were carried out by ET and IEC.

 

COMPLAINT HANDLING AND PROSECUTION

 

A11.   No project-related environmental complaint was received during the reporting period.

A12.   Neither notifications of summons nor prosecution was received for the Project.

REPORTING CHANGE

 

A13.   There was no change to be reported that may affect the on-going EM&A programme.

 

 

 


1.        BASIC PROJECT INFORMATION

 

1.1.           BACKGROUND

The Jardine Engineering Corporation, Limited, China State Construction Engineering (Hong Kong) Limited and Acciona Agua, S.A. Trading As AJC Joint Venture (AJCJV) is contracted to carry out the Design, Build and Operate First Stage of Tseung Kwan O Desalination Plant (DPTKO) under Contract No. 13/WSD/17 (the Project).

Acuity Sustainability Consulting Limited (ASCL) is commissioned by AJCJV to undertake the Environmental Team (ET) services as required and/or implied, both explicitly and implicitly, in the Environmental Permit (EP), Environmental Impact Assessment Report (EIA Report) (Register No. AEIAR-192/2015) and Environmental Monitoring and Audit Manual (EM&A Manual) for the Project; and to carry out the Environmental Monitoring and Audit (EM&A) programme in fulfillment of the EIA Report¡¦s EM&A requirements and Contract No. 13/WSD/17 Specification requirements.

Pursuant to the Environmental Impact Assessment Ordinance (EIAO), the Director of Environmental Protection granted the Environmental Permit (No. EP-01/503/2015) and Variation of Environmental Permit (No. EP-01/503/2015/A) to Water Supplies Department (WSD); and granted the Further Environmental Permit (No. FEP-01/503/2015/A) to AJCJV for the Project.

 

1.2.           THE REPORTING SCOPE

This is the 1st Quarterly EM&A Report for the Project which summarizes the key findings of the EM&A programme during the reporting period from 16 Mar to 31 May 2020.

 

1.3.           PROJECT ORGANIZATION-

The Project Organization structure for Construction Phase is presented in Figure 1.1.

 

 

Figure 1.1       Project Organization Chart

.


Contact details of the key personnel are presented in Table 1.1 below:

 

Table 1.1         Contact Details of Key Personnel

 

Party

Position

Name

Telephone no.

Project Proponent

SE/CM2

Benny Lam

2634-3573

 

 

Supervising Officer (Black & Veatch)

Project Manager

Christina Ko

2608-7302

Chief Resident Engineer

 

Roger Wu

 

6343-1002

 

The Jardine Engineering Corporation, Limited, China State Construction Engineering (Hong Kong) Limited and Acciona Agua, S.A. Trading

 

Project Manager

Stephen Yeung

 

2807-4665

Environmental Monitoring Manager

 

Brian Kam

 

9456-9541

 

Acuity Sustainability Consulting Limited

Environmental Team Leader

 

Jacky Leung

 

2698-6833

 

ANewR Consulting Limited

Independent Environmental Checker (IEC)

 

Adi Lee

 

2618-2831

 

1.4.           SUMMARY OF CONSTRUCTION WORKS

Details of the major construction activities undertaken in this reporting period are shown in below. The construction programme is presented in Appendix A.

 

Key activities carried out in this reporting period for the Project included the following:

-                 Plate Load Test;

-                 Land Survey;

-                 Ground Levelling;

-                 Ground Investigation;

-                 Access Road Construction;

-                 Site office formation work and footing;

-                 Earth mat installation at 132kV substation;

-                 Construction of 132kV substation footing;

-                 Construction of Temp 11kV substation;

-                 Ducts laying for temp 11kV substation;

-                 Excavation for combined shaft.

 

1.5.           SUMMARY OF ENVIRONMENTAL STATUS

A summary of the valid permits, licences, and /or notifications on environmental protection for this Project is presented in Table 1.2.

Table 1.2      Summary of the Status of Valid Environmental Licence, Notification, Permit and Documentations

 

Permit/ Licenses/ Notification

Reference

Validity Period

Remarks

Environmental Permit

FEP - 01/503/2015/A

Throughout the Contract

 

Notification of Construction Works under the Air Pollution Control (Construction Dust) Regulation (Form NA)

Ref. No.: 451539

30/12/2019 -

30/03/2023

 

Wastewater Discharge Licence

-

-

Under Application

Chemical Waste Producer Registration

5213-839-A2987-01

Throughout the Contract

 

Construction Noise Permit (24 hours)

GW-RE0249-20

09/04/2020 -

08/10/2020

 

Billing Account for

Disposal of Construction Waste

7036276

Throughout the Contract

 

 

 

The status for all environmental aspects is presented in Table 1.3.

 


Table 1.3         Summary of Status for Key Environmental Aspects under the Updated EM&A Manual

 

Parameters

Status

Water Quality

Baseline Monitoring under EM&A Manual

The baseline water quality monitoring would be conducted from 12 May 2020 and completed on 6 June 2020

Impact Monitoring

The impact water quality monitoring has been scheduled after the commencement of marine construction works

Noise

Baseline Monitoring

The baseline noise monitoring result has been reported in Baseline Monitoring Report and submitted to EPD under EP

Condition 3.4

Impact Monitoring

On-going

Waste Management

Mitigation Measures in Waste Monitoring Plan

On-going

Environmental Audit

Site Inspection covering Measures of Air Quality, Noise Impact, Water Quality, Waste, Ecological Quality, Fisheries,

Landscape and Visual

On-going

 

 

Other than the EM&A work by ET, environmental briefings, trainings and regular environmental management meetings were conducted, in order to enhance environmental awareness and closely monitor the environmental performance of the contractors.

The EM&A programme has been implemented in accordance with the recommendations presented in the approved EIA Report and the EM&A Manual. A summary of implementation status of the environmental mitigation measures for the construction phase of the Project during the reporting period is provided in Appendix C.

 

.


2.        NOISE

 

2.1.           MONITORING REQUIREMENTS

To ensure no adverse noise impact, noise monitoring is recommended to be carried out within 300m radius from the nearby noise sensitive receivers (NSRs), during construction phase. The NSRs selected as monitoring station are (i) NSR4 - Creative Secondary School, (ii) NSR24 - PLK Laws Foundation College, and (iii) NSR31 - School of Continuing and Professional Studies - CUHK respectively.

In accordance with the EM&A Manual, baseline noise level at the noise monitoring stations were established as presented in the Baseline Monitoring Report. Impact noise monitoring will be conducted once per week in the form of 30-minutes measurements Leq, L10 and L90 levels recorded at each monitoring station between 0700 and 1900 hours on normal weekdays.

Referring to EM&A manual Section 4.1.2, the impact noise monitoring should be carried out at all the designated monitoring stations when there are project-related construction activities undertaken within a radius of 300m from the monitoring stations.

No impact monitoring for noise impact was conducted in the reporting period due to the overly distant monitoring station from the works location, where they were farther than 1 km from the closet monitoring station NSR4 to the works location.

Construction noise level measured in terms of the A-weighted equivalent continuous sound pressure level (LAeq). Leq 30min was used as the monitoring parameter for the time period between 0700 and 1900 hours on normal weekdays. Table 2.1 summarizes the monitoring parameters, frequency and duration of the impact noise monitoring.

Table 2.1          Noise Monitoring Parameters, Time, Frequency and Duration

 

Time

Duration

Interval

Parameters

 

Daytime:

0700-1900 hrs

Day time: 0700-1900 hrs

(during weekdays)

 

normal

Continuously in

Leq 5min/Leq 30min (average of 6 consecutive Leq 5min)

 

Leq L10

 

 

30min 30min

 

& L90

 

 

 

30min

 

2.2.           MONITORING LOCATIONS

The monitoring locations should normally be made at a point 1m from the exterior of the NSRs building façade and be at a position 1.2m above the ground. A correction of +3dB(A) should be made to the free-field measurements.

According to the environmental findings detailed in the EIA report and Baseline Monitoring Report, the designated locations for the construction noise monitoring are listed in Table 2.2 below.

Table 2.2          Noise Sensitive Receivers

 


 

NSR ID

Noise Sensitive Receivers

Monitoring Location

Position

NSR 4

Creative Secondary School

Roof Floor

1 m from facade

NSR 24

PLK Laws Foundation College

Pedestrian Road on Ground Floor

Free-field

NSR 31

School of Continuing and Professional Studies - CUHK

Roof Floor

1 m from facade

 

 

The monitoring locations should normally be made at a point 1m from the exterior of the NSRs building façade and be at a position 1.2m above the ground. A correction of +3dB(A) should be made to the free-field measurements. Three noise monitoring locations for impact monitoring at the nearby sensitive receivers are shown in Figure 2.1-2.3.

 

 

Figure 2.1 NSR4 Creative Secondary School

 

 

Figure 2.2 NSR24 PLK Laws Foundation College

 

 

Figure 2.3 NSR31 School of Continuing and Professional Studies - CUHK

 

 

 


2.3.           ACTION AND LIMIT LEVELS

The Action/Limit Levels in line with the criteria of Practice Note for Professional Persons (ProPECC PN 2/93) ¡§Noise from Construction Activities - Non-statutory Controls¡¨ and Technical Memorandum on Environmental Impact Assessment Process issued by HKSAR Environmental Protection Department [¡§EPD¡¨] under the Environmental Impact Assessment Ordinance, Cap 499, S.16 are presented in Table 2.4.

 

Table 3.4         Action and Limit Levels for Noise per Updated EM&A Manual

 

Time Period

Action

Limit (dB(A))

 

0700-1900 hours on normal weekdays

When one documented complaint is received from any one of the noise sensitive receivers

-          70 dB(A) for school and

-          65 dB(A) during examination period

Notes: Limits specified in the GW-TM and IND-TM for construction and operation noise, respectively.

 

If exceedances were found during noise monitoring, the actions in accordance with the Event and Action Plan shall be carried out according to Appendix E.

 

2.4.           MONITORING RESULTS AND OBSERVATIONS

Referring to EM&A manual Section 4.1.2, the impact noise monitoring should be carried out when there are project-related construction activities undertaken within a radius of 300m from the monitoring stations. No monitoring station was located within a radius of 300m of the Project site as shown in Figure 2.4, no impact monitoring for noise impact was conducted in the reporting period.

 

 

Figure 2.4       Site Layout Plan with Noise Sensitive Receivers and Desalination Plant

 

3.      WATER QUALITY

In accordance with the recommendations of the EIA, water quality EM&A is required during dredging for the submarine pipelines and, during operation phase. In addition, baseline water quality monitoring will be required prior to the commencement of marine construction activities. The following Section provides details of the water quality monitoring to be undertaken by the Environmental Team (ET) to verify the distance of sediment and brine plume dispersion and to identify whether the potential exists for any indirect impacts to occur to ecological sensitive receivers. The water quality monitoring programme will be carried out to allow any deteriorating water quality to be readily detected and timely action taken to rectify the situation. The status and locations of water quality sensitive receivers and the marine works location may change after issuing this Document. If required, the ET in consultation with IEC will propose updated  monitoring locations and seek approval from EPD.

Water quality monitoring for the Project can be divided into the following stages:

 

-                 Dredging activities during construction phase;

 

-                 Discharge of effluent from main disinfection during construction phase;

 

-                 Operation phase - first year upon commissioning; and,

 

-                 Continuous monitoring of effluent quality.

 

In addition, the marine works contractor is required to complete a silt curtain efficiency test for the combined use of floating silt curtain type and cage type silt curtain for dredging at seawater intake to confirm the silt curtain reduction efficiency assumptions of the assessment. The details of testing plan together with the silt curtain deployment plan updated testing plan shall be submitted by the ET to seek approval from the IEC and EPD.

 

3.1.           IMPACT MONITORING METHODOLOGY

 

3.1.1.      WATER QUALITY PARAMETERS

The parameters that have been selected for measurement in situ and in the laboratory are those that were either determined in the EIA to be those with the most potential to be affected by the construction works or are a standard check on water quality conditions. Parameters to be measured in the baseline monitoring are listed in Table 3.1.

 

Parameters

Unit

Abbreviation

In-situ measurements

Dissolved oxygen

mg/L

DO

Temperature

oC

-

pH

-

-

Turbidity

NTU

-

Salinity

0/00

-

Total Residual Chlorine NOTE1

mg/L

TRC

Laboratory measurements

Suspended Solids

mg/L

SS

Iron-Soluble NOTE2

mg/L

Fe

Anti-scalant as Reactive Phosphorus NOTE2

mg/L

PO4 as P-

NOTE 1: Monitoring of TRC will be conducted when cleaning and sterilization of the new freshwater main is carried out.

 

NOTE 2: The testing methods shall be submitted to EPD for approval prior to the commencement of monitoring programme

In addition to the water quality parameters, other relevant data will also be measured and recorded in Water Quality Monitoring Logs, including the location of the sampling stations, water depth, time, weather conditions, sea conditions, tidal stage, current direction and velocity, special phenomena and work activities undertaken around the monitoring and works area that may influence the monitoring results.

 

3.1.2.      MONITORING LOCATION

The water quality monitoring locations for baseline in accordance to the EM&A Manual and Contract Specification are shown in Figure 3.1 and Figure 4.1 respectively, and detailed in Table 3.3 below. A schedule for water quality monitoring shall be prepared by the ET and approved by IEC and EPD prior to the commencement of the monitoring.

 

Station

Easting

Northing

Description

CE

843550

815243

Upstream control station at ebb tide

CF

846843

810193

Upstream control station at flood tide

WSR1

846864

812014

Ecological sensitive receiver at Tung Lung Chau

WSR2

847645

812993

Fisheries sensitive receiver at Tung Lung Chau

WSR3

848023

813262

Ecological sensitive receiver at Tung Lung Chau

WSR4

847886

814154

Ecological sensitive receiver at Tai Miu Wan

WSR16

845039

815287

Ecological sensitive receiver at Fat Tong Chau

WSR33

847159

814488

Ecological sensitive receiver at Tai Miu Wan

WSR36

846878

814081

Ecological sensitive receiver at Kwun Tsai

WSR37

846655

813810

Ecological sensitive receiver at Tit Cham Chau

NF1

846542

813614

Edge of mixing zone, ~ 200m west of outfall diffuser

NF2

846942

813614

Edge of mixing zone, ~ 200m east of outfall diffuser

NF3

846742

813414

Edge of mixing zone, ~ 200m south of outfall diffuser

 

WSR1 to WSR37 were identified in accordance with Annex 14 of the EIAO-TM as well as Clause

3.4.4.2 of the Environmental Impact Assessment Study Brief for Desalination Plant at Tseung Kwan O (No. ESB-266/2013). WSR1 to WSR3 are sited near the Tung Lung Chau Fish Culture Zone; WSR16 and WSR36 are sited near the coral assemblages along the coastlines of Fat Tong Chau and Kwun Tsai respectively; WSR 4 and WSR33 are sited near the Coastal Protection Area and coral assemblages in waters of Tai Miu Wan; WSR37 is sited near the fisheries resource including spawning and nursery grounds at the coastal water of Tit Cham Chau.

 

Figure 3.1         Baseline water quality monitoring locations under EM&A Manual

 

 

 

3.2.          MONITORING PROGRAMME

 

The ET of the Project had conducted the baseline water monitoring between 12 May 2020 to 6 June 2020 at the thirteen designated monitoring stations and the six designated monitoring at waters near TKO in accordance with the EM&A Manual and Contract Specification respectively. The monitoring results was presented in Baseline Water Quality Monitoring Report separately.

The commencement of marine construction and dredging activities for the Project are scheduled in November 2020 the earliest. The impact water monitoring shall be scheduled after the commencement of marine construction and dredging activities. Hence, no impact water monitoring was conducted during the reporting month.

 

4.        WASTE

 

The waste generated from this Project includes inert construction and demolition (C&D) materials, and non-inert C&D materials. Non- inert C&D materials are made up of general refuse, vegetative wastes and recyclable wastes such as plastics and paper/cardboard packaging waste. Steel materials generated from the project are also grouped into non-inert C&D materials as the materials were not disposed of with other inert C&D materials. With reference to relevant handling records and trip tickets of this Project, the quantities of different types of waste generated in the reporting month are summarised in Table 4.1. Details of cumulative waste management data are presented as a waste flow table in Appendix G.

Table 4.1         Quantities of Waste Generated from the Project during reporting period

 

 

 

 

 

 

Reporting Month

Actual Quantities of Inert C&D Materials Generated Monthly

Actual Quantities of C&D Wastes Generated Monthly

 

 

Total Quantity Generated

 

Hard Rock and Large Broken Concrete

 

 

Reused in the Contract

 

 

Reused in other Projects

 

 

Disposed as Public Fill

 

 

Imported Fill

 

 

 

Metals

 

 

Paper / cardboard packaging

 

 

Plastics (see Note)

 

 

Chemical Waste

 

Others, e.g. general refuse

(in ,000kg)

(in ,000kg)

(in ,000kg)

(in ,000kg)

(in ,000kg)

(in ,000kg)

(in ,000kg)

(in ,000kg)

(in ,000kg)

(in ,000kg)

(in ,000kg)

Mar 2020

0

0

0

0

0

0

0

0

0

0

0.42

Apr 2020

0

0

0

0

0

0

0

0

0

0

2.4

May 2020

0

0

0

0

0

0

5.9

0

0

0

12.57

Notes:  (1) Plastics refer to plastic bottles / containers, plastic sheets / foam from packaging material

 

 


5.        LANDFILL GAS MONITORING

 

5.1.           MONITORING REQUIREMENT

In accordance with Section 11 of the EM&A Manual, monitoring of landfill gas is required for construction works within the 250m Consultation Zone. Part of the desalination plant and the indicative area of natural slope mitigation works fall within the SENT Landfill Extension Consultation Zone; and part of the 1,200 mm diameter fresh water mains along Wan Po Road falls within the SENT Landfill and SENT Landfill Extension Consultation Zones, TKO Stage II/III Restored Landfill and TKO Stage I Restored Landfill Consultation Zones.

 

5.2.           MONITORING LOCATION

Monitoring of oxygen, methane, carbon dioxide and barometric pressure was performed for excavations at 1m depth or more within the consultation Zone.

During construction of works within the consultation zones, excavations of 1m depth or more was monitored:

-                 At the ground surface before excavation commences;

-                 Immediately before any worker enters the excavation;

-                 At the beginning of each working day for the entire period the excavation remains open; and

-                 Periodically through the working day whilst workers are in the excavation.

 

For excavations between 300mm and 1m deep, measurements should be carried out:

 

-                 Directly after the excavation has been completed; and

-                 Periodically whilst the excavation remains open.

 

5.3.           MONITORING PROGRAMME

For the part of the desalination plant and the indicative area of natural slope mitigation works fall within the SENT Landfill Extension Consultation Zone in this contract. Since the SENT Landfill Extension is still under construction, the Landfill gas monitoring shall be conducted after the commencement of operation of the SENT Landfill Extension which will be 2021 Quarter 3 according to the latest construction programme shown in the monthly EM&A Report of SENT Landfill Extension. The Contractor¡¦s safety officer shall keep review the necessity of landfill gas monitoring during the construction stage. No landfill gas monitoring was conducted in the reporting period.

 

 

 


6.        SUMMARY OF MONITORING EXCEEDANCE, COMPLAINTS, NOTIFICATION OF SUMMONS AND PROSECUTIONS

The Environmental Complaint Handling Procedure is shown in below Figure 5.1:

 

 

Figure 8.1       Environmental Complaint Handling Procedures

 

 


No noise monitoring was conducted during the reporting period since there are no project-related construction activities undertaken within a radius of 300m from the monitoring locations.

The baseline water monitoring had been conducted between 12 May 2020 to 6 Jun 2020 at the thirteen designated monitoring stations and the six designated monitoring at waters near TKO. No impact water quality monitoring was conducted in the reporting period since the commencement  of marine construction and dredging activities for the Project are scheduled in November 2020 the earliest.

No project-related exceedance of the Action Level was recorded during the reporting period. No notification of summons and prosecution was received in the reporting period.

Statistics on complaints and regulatory compliance are summarized in Appendix H.

 

 

 


7.        EM&A SITE INSPECTION

Site inspections were carried out on a weekly basis to monitor the implementation of proper environmental pollution control and mitigation measures under the Contract.

Joint site inspection with IEC was carried out on a bi-weekly basis.

 

Minor deficiencies were observed during weekly site inspection. Key observations during the site inspections are summarized below:

-                 Prevention actions for oil/chemical spillage were not carried out properly

-                 Dust suppression mitigation measures were not implemented properly

 

The Contractor has rectified the observations identified during environmental site inspections in the reporting period.

According to the EIA Study Report, Environmental Permit, contract documents and EM&A Manual, the mitigation measures detailed in the documents are implemented as much as practical during the reporting period. An updated Implementation Status of Environmental Mitigation Measures (EMIS) is provided in Appendix C.

 


8.        CONCLUSIONS AND RECOMMENDATIONS

 

This is the 1st Quarterly EM&A Report for the Project which summarizes the key findings of the EM&A programme during the reporting period from 16 Mar to 31 May 2020., in accordance with the EM&A Manual and the requirement under FEP-01/503/2015/A.

No noise monitoring was conducted in the reporting period due to the over distant monitoring station from the works location.

The baseline water monitoring had been conducted between 12 May 2020 to 6 Jun 2020 at the thirteen designated monitoring stations and the six designated monitoring at waters near TKO. No impact water quality monitoring was conducted in the reporting period since the commencement of marine construction and dredging activities for the Project are scheduled in November 2020 the earliest.

No project-related exceedance of the Action / Limit Level was recorded during the reporting period.

 

Weekly environmental site inspection was conducted during the reporting period. Minor deficiency was observed during site inspection and was rectified. The environmental performance of the project was therefore considered satisfactory.

According to the environmental site inspections performed in the reporting period, the Contractor is reminded to pay attention on maintaining proper materials storage.

No environmental complaint was received in the reporting period.

 

No notification of summons or prosecution was received since commencement of the Contract.

 

The ET will keep track on the construction works to confirm compliance of environmental requirements and the proper implementation of all necessary mitigation measures.

 

 

 

 

 

 

 

 

 

Appendix A

 

Master Programme


 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Appendix B

 

Overview of Desalination Plant in Tseung Kwan O

 

 

 

 

 

 

 

 

 

 

 

 

Appendix C

 

Summary of Implementation Status of Environmental Mitigation

 

 

 

 

 

 

EIA Reference

 

Recommended Environmental Protection Measures/ Mitigation Measures

Objectives of the recommended measures & main concerns to address

 

Implementation Agent

Implementation Stage

 

Implementation status

Relevant Legislation & Guidelines

D

C

O

Air Quality

 

S4.8.1

Impervious dust screen or sheeting will be provided to enclose scaffolding from the ground floor level of building for construction of superstructure of the new buildings.

Land site/ During Construction

Contractor(s)

 

ü

 

N/A

Air Pollution Control (Construction Dust)

S4.8.1

Impervious sheet will be provided for skip hoist for material transport.

Land site/ During Construction, particularly dry season

Contractor(s)

 

ü

 

NA

 

S4.8.1

The area where dusty work takes place should be sprayed with water or a dust suppression chemical immediately prior to, during and immediately after dusty activities as far as practicable.

Land site/ During Construction

Contractor(s)

 

ü

 

Implemented

 

S4.8.1

All dusty materials should be sprayed with water or a dust suppression chemical immediately prior to any loading, unloading or transfer operation.

Land site/ During Construction

Contractor(s)

 

ü

 

Implemented

 

S4.8.1

Dropping heights for excavated materials should be controlled to a practical height to minimise the fugitive dust arising from unloading.

Land site/ During Construction

Contractor(s)

 

ü

 

N/A

 

S4.8.1

During transportation by truck, materials should not be loaded to a level higher than the side and tail boards, and should be dampened or covered before transport.

Land site/ During Construction

Contractor(s)

 

ü

 

N/A

 

S4.8.1

Wheel washing device should be provided at the exits of the work sites. Immediately before leaving a construction site, every vehicle shall be washed to remove any dusty material from its body and wheels as far as practicable.

Land site/ During Construction

Contractor(s)

 

ü

 

N/A

 


 

 

EIA Reference

 

Recommended Environmental Protection Measures/ Mitigation Measures

Objectives of the recommended measures & main concerns to address

 

Implementation Agent

Implementation Stage

 

Implementation status

Relevant Legislation & Guidelines

D

C

O

S4.8.1

Road sections between vehicle-wash areas and vehicular entrance will be paved.

Land site/ During Construction

Contractor(s)

 

ü

 

Implemented

 

S4.8.1

Hoarding of not less than 2.4m high from ground level will be provided along the length of the Project Site boundary.

Land site/ During construction

Contractor(s)

ü

ü

 

N/A

 

S4.8.1

Haul roads will be kept clear of dusty materials and will be sprayed with water so as to maintain the entire road surface wet at all times.

Land site/ During construction

Contractor(s)

 

ü

 

Implemented

 

S4.8.1

Temporary stockpiles of dusty materials will be either covered entirely by impervious sheets or sprayed with water to maintain the entire surface wet all the time.

Land site/ During construction

Contractor(s)

 

ü

 

Implemented

 

S4.8.1

Stockpiles of more than 20 bags of cement, dry pulverised fuel ash and dusty construction materials will be covered entirely by impervious sheeting sheltered on top and 3-sides.

Land site/ During construction

Contractor(s)

 

ü

 

N/A

 

S4.8.1

All exposed areas will be kept wet always to minimise dust emission.

Land site/ During construction

Contractor(s)

 

ü

 

Implemented

 

S4.8.1

Ultra-low-sulphur diesel (ULSD) will be used for all construction plant on-site, as defined as diesel fuel containing not more than 0.005% sulphur by weight) as stipulated in Environment, Transport and Works Bureau Technical Circular (ETWB-TC(W)) No 19/2005 on Environmental Management on Construction Sites.

Land site/ During construction/ During Operation

Contractor(s)

 

ü

ü

Implemented

Environment, Transport and Works Bureau Technical Circular (ETWB- TC(W)) No 19/2005 on

Environmental Management on Construction Sites


 

 

EIA Reference

 

Recommended Environmental Protection Measures/ Mitigation Measures

Objectives of the recommended measures & main concerns to address

 

Implementation Agent

Implementation Stage

 

Implementation status

Relevant Legislation & Guidelines

D

C

O

S4.8.1

The engine of the construction equipment during idling will be switched off.

Land site/ During construction

Contractor(s)

 

ü

 

Implemented

 

S4.8.1

Concrete batching plant will be required on site. control measures recommended in the Guidance Note on a Best Practicable Means for Cement Works (Concrete Batching Plant) (BPM 3/2 (93)) will be implemented. The control measures recommended in the Guidance Note on a Best Practicable Means for Cement Works (Concrete Batching Plant) (BPM 3/2 (93)) will be

Land site/ During construction

Contractor(s)

 

ü

 

N/A

Guidance Note on a Best

S4.8.1

Regular maintenance of construction equipment deployed on-site will be conducted to prevent black smoke emission.

Land site/ During construction

Contractor(s)

 

ü

 

Implemented

 

S4.10

To ensure proper implementation of the recommended dust mitigation measures and good construction site practices during the construction phase, environmental site audits on weekly basis is recommended throughout the construction period.

Land site/ During construction

Contractor(s)/ Environmental Team (ET) & Independent Environmental Checker (IEC)

 

ü

 

Implemented

 

Note: D - Design stage C - Construction O - Operation


 

 

EIA Reference

Recommended Environmental Protection Measures/ Mitigation Measures

Objectives of the recommended  measures &

main concerns to address

Implementation Agent

Implementation Stage

Implementation status

Relevant Legislation & Guidelines

D

C

O

Noise

S5.7

Only well-maintained plant will be operated on- site and plant will be serviced regularly during the construction phase.

All area/ During construction

Contractor(s)

 

ü

 

Implemented

A Practical Guide for the Reduction of Noise from Construction

Works,

S5.7

Silencers or mufflers on construction equipment will be utilised and will be properly maintained during the construction phase.

Noise control/ During construction

Contractor(s)

 

ü

 

N/A

A Practical Guide for the Reduction of Noise from Construction

Works,

S5.7

Mobile plant, if any, will be sited as far away from NSRs as possible.

Noise control/ During construction

Contractor(s)

 

ü

 

Implemented

A Practical Guide for the Reduction of Noise from Construction

Works,

S5.7

Machines and plant (such as trucks) that may be in intermittent use will be shut down

between work periods or will be throttled down to a minimum.

Noise control/ During construction

Contractor(s)

 

ü

 

Implemented

A Practical Guide for the Reduction of Noise

from              Construction Works,

S5.7

Plants known to emit noise strongly in one direction will, wherever possible, be orientated

so that the noise is directed away from the nearby NSRs.

Noise control/ During construction

Contractor(s)

 

ü

 

N/A

A Practical Guide for the Reduction of Noise

from              Construction Works,

S5.7

Material stockpiles and other structures will be effectively utilised, wherever practicable, in

screening noise from on-site construction activities.

Noise control/ During construction

Contractor(s)

 

ü

 

N/A

A Practical Guide for the Reduction of Noise

from              Construction Works,

S5.7

Use of Quite Powered Mechanical Equipment

(QPME).

Noise control/

During construction

Contractor(s)

 

ü

 

Implemented

A Practical Guide for

the Reduction of Noise from Construction Works,

S5.7

Movable noise barriers of 3m in height with skid footing should be used and located within a few metres of stationary plant and mobile plant such that the line of sight to the NSR is blocked by the barriers. The length of the barrier should be at least five times greater than its height. The

noise barrier material should have a superficial

Noise control/ During construction

Contractor(s)

 

ü

 

N/A

A Practical Guide for the Reduction of Noise from Construction Works,


 

 

EIA Reference

Recommended Environmental Protection Measures/ Mitigation Measures

Objectives of the recommended  measures &

main concerns to address

Implementation Agent

Implementation Stage

Implementation status

Relevant Legislation & Guidelines

D

C

O

 

surface density of at least 7 kg m-2 and have no openings or gaps.

 

 

 

 

 

 

 

S5.7

The noise insulating sheet should be deployed such that there would be no opening or gaps on the joints.

Noise control/ During construction

Contractor(s)

 

ü

 

N/A

A Practical Guide for the Reduction of Noise from Construction

Works,

S5.7

Construction activities (e.g. excavation/shoring, reinstatement (asphalt), and pipe jacking) will be planned and carried out in sequence, such that items of PME proposed for these activities will

not be operated simultaneously.

Noise control/ During construction

Contractor(s)

 

ü

 

Implemented

A Practical Guide for the Reduction of Noise from Construction Works

S5.7

PMEs will not be used at the works areas near educational institutions with residual impact (ie the ¡§influence area¡¨ within a radius of 40m) during school hours in order to reduce impact

to the educational institutions.

Noise control / During construction

Contractor(s)

 

ü

 

Implemented

A Practical Guide for the Reduction of Noise from Construction Works

S5.7

Noise enclosures or acoustic sheds would be used to cover stationary PME such as generators.

Portable/Movable noise enclosure made of material with superficial surface density of at least 7 kg m-2 may be used for screening the noise from operation of the saw/groover,

concrete.

Noise control/

Pre- construction/ During construction

Contractor(s)

ü

ü

 

N/A

 

S5.9

Sawcutting pavement, breaking up of pavement, excavation /shoring, pipe laying, backfilling, reinstatement (concrete) and

pipe jacking shall be scheduled outside the examination period.

Noise control/

Pre- construction/ During construction

Contractor(s)

ü

ü

 

N/A

 


 

 

EIA Reference

Recommended Environmental Protection Measures/ Mitigation Measures

Objectives of the recommended  measures &

main concerns to address

Implementation Agent

Implementation Stage

Implementation status

Relevant Legislation & Guidelines

D

C

O

S5.9

In view the duration of noise exceedance at Creative Secondary School, PLK Laws Foundation College, TKO Kei Tak Primary School and School of Continuing and Professional Studies-CUHK is limited to 8 weeks, the construction work in the influence areas near the four schools shall be scheduled during long school holidays (eg summer holiday, Easter holiday or Christmas holiday,

etc) as far as practicable. Scheduling the construction work for the four schools.

Noise control/ Pre- construction/ During construction

Contractor(s)

ü

ü

 

N/A

 

S5.10

A noise monitoring programme shall be implemented for the construction phase.

Designated monitoring stations as defined in EM&A Manual/During construction phase

Environmental Team (ET)

 

ü

 

Implemented

 

S5.10

The effectiveness of on-site control measures could also be evaluated through the regular site audits.

All facilities/ During construction

Contractor(s)/ Environmental Team (ET) & Independent

Environmental Checker (IEC)

 

ü

 

Implemented

-

Note: D - Design stage C - Construction O - Operation


 

 

EIA Reference

Recommended Environmental Protection Measures/ Mitigation Measures

Objectives of the recommende measures & main concerns to address

Implementatio n Agent

Implementation Stage

Implementation status

Relevant Legislation & Guidelines

D

C

O

Water Quality

S6.9

Dredged marine sediment will be disposed of in a gazetted marine disposal area in accordance with marine dumping permit conditions of the Dumping at Sea Ordinance (DASO).

Marine Dredging/ During construction

Contractor(s)

 

ü

 

N/A

Dumping at Sea Ordinance (DASO)

S6.9

Disposal vessels will be fitted with tight bottom seals in order to prevent leakage of material during transport.

Marine Dredging/ During construction

Contractor(s)

 

ü

 

N/A

-

S6.9

Barges will be filled to a level, which ensures that material does not spill over during transport to the disposal site and that adequate freeboard is maintained to ensure that the decks are not washed by wave action.

Marine Dredging/ During construction

Contractor(s)

 

ü

 

N/A

-

S6.9

After dredging, any excess materials will be cleaned from decks and exposed fittings before the vessel is moved from the dredging area.

Marine Dredging/ During construction

Contractor(s)

 

ü

 

N/A

-

S6.9

All vessels should be well maintained and inspected before use to limit any potential discharges to the marine environment.

Marine Dredging/ During construction

Contractor(s)

 

ü

 

N/A

-

S6.9

All vessels must have a clean ballast system.

Marine Dredging/ During construction

Contractor(s)

 

ü

 

N/A

-

S6.9

No discharge of sewage/grey wastewater should be allowed. Waste water from potentially contaminated area on working vessels should be minimized and collected.                                These kinds of wastewater should be brought back to port and discharged at appropriate collection and treatment system.

Marine Dredging/ During construction

Contractor(s)

 

ü

 

N/A

-

S6.9

No soil waste is allowed to be disposed overboard.

Marine Dredging/ During construction

Contractor(s)

 

ü

 

N/A

-


 

 

EIA Reference

Recommended Environmental Protection Measures/ Mitigation Measures

Objectives of the recommende measures & main concerns to address

Implementatio n Agent

Implementation Stage

Implementation status

Relevant Legislation & Guidelines

D

C

O

S6.9

Silt removal facilities such as silt traps or sedimentation facilities will be provided to remove silt particles from runoff to meet the requirements of the TM standard under the WPCO.      The design of silt removal facilities will be based on the guidelines provided in ProPECC PN 1/94.                All drainage facilities and erosion and sediment control structures will be inspected on a regular basis and maintained to confirm proper and efficient operation at all times and particularly during rainstorms.                Deposited silt and grit will be removed regularly.

Land site & drainage/ During construction

Contractor(s)

 

ü

 

Implemented

ProPECC PN 1/94 TM

Standard under the WPCO

S6.9

Earthworks to form the final surfaces will be followed up with surface protection and drainage works to prevent erosion caused by rainstorms.

Land site & drainage/ During construction

Contractor(s)

 

ü

 

Implemented

-

S6.9

Appropriate surface drainage will be designed and provided where necessary.

Land site & drainage/ During construction

Contractor(s)

 

ü

 

N/A

-

S6.9

The precautions to be taken at any time of year when rainstorms are likely together with the actions to be taken when a rainstorm is imminent or forecasted and actions to be taken during or after rainstorms are summarised in Appendix A2 of ProPECC PN 1/94.

Land site & drainage/ During construction

Contractor(s)

 

ü

 

Implemented

ProPECC PN 1/94

S6.9

Oil interceptors will be provided in the drainage system where necessary and regularly emptied to prevent the release of oil and grease into the storm water drainage system after accidental spillages.

Land site & drainage/ During construction

Contractor(s)

 

ü

 

Implemented

-

S6.9

Temporary and permanent drainage pipes and culverts provided to facilitate runoff discharge, if any, will be adequately designed for the controlled release of storm flows.

Land site & drainage/ During construction

Contractor(s)

 

ü

 

N/A

-


 

 

EIA Reference

Recommended Environmental Protection Measures/ Mitigation Measures

Objectives of the recommende measures & main concerns to address

Implementatio n Agent

Implementation Stage

Implementation status

Relevant Legislation & Guidelines

D

C

O

S6.9

The temporary diverted drainage, if any, will be reinstated to the original condition when the construction work has finished or when the temporary diversion is no longer required.

Land site & drainage/ During construction

Contractor(s)

 

ü

 

N/A

-

S6.9

Appropriate numbers of portable toilets shall be provided by a licensed contractor to serve the construction workers over the construction site to prevent direct disposal of sewage into the water environment.

Land site & drainage/ During construction

Contractor(s)

 

ü

 

Implemented

-

S6.9 and S6.12

The sterilization water should be dechlorinated with total residual chlorine (TRC) level below 1 mg/L before discharge to public sewer. In situ testing of TRC should also be conducted for the discharge of chlorinated water for pipeline disinfection to ensure sufficient dechlorination before discharge to public sewer.

Sterilization of water mains prior to commissioning

Contractor(s)

 

ü

ü

N/A

Technical Memorandum for Effluents Discharged into Drainage and Sewerage Systems Inland and Coastal Waters

S6.9

The cleaning and flushing water should also be treated and desilted to the relevant discharge requirement stipulated in TM-DSS before discharging.

Sterilization of water mains prior to commissioning

Contractor(s)

 

ü

ü

N/A

Technical Memorandum for Effluents Discharged into Drainage and Sewerage Systems Inland and Coastal Waters

S6.9

Site drainage should be well maintained and good construction practices should be observed to ensure that oil, fuels, solvents and other chemicals are managed, stored and

handled properly and do not enter the nearby water streams.

Land site & drainage/ During construction/ During operation

Contractor(s)

 

ü

ü

Implemented

-


 

 

EIA Reference

Recommended Environmental Protection Measures/ Mitigation Measures

Objectives of the recommende measures & main concerns to address

Implementatio n Agent

Implementation Stage

Implementation status

Relevant Legislation & Guidelines

D

C

O

S6.12

Regular site inspections will be carried out in order to confirm that regulatory requirements are being met and that contractors are implementing the standard site practice and mitigation measures as proposed to reduce potential impacts to water quality.

During construction

Contractor(s)/ Environmental Team (ET) & Independent Environmental Checker (IEC)

 

ü

 

Implemented

-

Note: D - Design stage C - Construction O - Operation


 

 

EIA Reference

Recommended Environmental Protection Measures/ Mitigation Measures

Objectives of the recommended measures &

main concerns to address

Implementation Agent

Implementation Stage

Implementation Status

Relevant Legislation & Guidelines

D

C

O

Waste Management

S8.5

Nomination of approved personnel to be responsible for standard site practices, arrangements for collection and effective disposal to an appropriate facility of all wastes

generated at the site.

Contract mobilisation/ During construction

Contractor(s)

 

ü

 

Implemented

-

S8.5

Training of site personnel in proper waste management and chemical handling procedures. Training will be provided to workers on the concepts of site cleanliness and appropriate waste management procedures, including waste reduction, reuse and recycling at the beginning

of the construction works.

Contract mobilisation/ During construction

Contractor(s)

 

ü

 

Implemented

-

S8.5

Provision of sufficient waste disposal points and regular collection for disposal.

All area/ During construction/ During operation

Contractor(s)

 

ü

ü

Implemented

DEVB TC(W) No. 8/2010,

Enhanced Specification

for Site Cleanliness and Tidiness.

S8.5

Appropriate measures to reduce windblown litter and         dust transportation of waste by either

covering trucks or by transporting wastes in enclosed containers.

All area/ During construction

Contractor(s)

 

ü

 

Implemented

DEVB TC(W) No. 8/2010,

Enhanced Specification for Site Cleanliness

and Tidiness.

S8.5

A waste management plan (WMP) as  stated  in the ¡§ETWB TC(W) No. 19/2005, Environmental Management on Construction Sites¡¨                          for the amount of waste  generated, recycled and disposed of (including the disposal sites) will be established and implemented during the construction phase as part of the Environmental Management Plan (EMP).                          The Contractor will be required to prepare the EMP and submits it to the Architect/ Engineer under the Contract for

approval prior to implementation.

All area/ During construction

Contractor(s)

 

ü

 

Implemented

ETWB TC(W) No. 19/2005,

Environmental Management on Construction Sites

S8.5

Separation of chemical wastes for special handling and appropriate treatment at the Chemical Waste Treatment Centre at Tsing Yi.

All area/ During construction

Contractor(s)

 

ü

 

N/A

Chapters 2 & 3 Code of Practice on the Packaging Labelling & Storage of

Chemical Wastes publishe


 

 

EIA Reference

Recommended Environmental Protection Measures/ Mitigation Measures

Objectives of the recommended measures &

main concerns to address

Implementation Agent

Implementation Stage

Implementation Status

Relevant Legislation & Guidelines

D

C

O

 

 

 

 

 

 

 

 

under the Waste Disposal Ordinance (Cap 354),

Section 35

S8.5

Regular cleaning and maintenance programme

for drainage systems, sumps and oil interceptors.

Land site/ During construction

Contractor(s)

 

ü

 

Implemented

Waste Disposal Ordinance (Cap 354)

S8.5

A recording system for the amount of wastes generated/ recycled and disposal sites.                                    The trip- ticket system will be included as one of the contractual requirements and implemented by the

contractor(s).

Land site/ During construction

Contractor(s)

 

ü

 

Implemented

DEVB TC(W) No. 6/2010,

Trip Ticket System for Disposal of Construction & Demolition Materials

S8.5

Segregation and storage of different types of waste in different containers, skips or stockpiles to enhance reuse or recycling of

material and their proper disposal.

Land site/ During construction/ During operation

Contractor(s)

 

ü

 

Implemented

WBTC 32/92, The Use of Tropical Hard Wood on Construction Site

S8.5

Encourage collection of aluminium cans and waste paper by individual collectors during construction with separate labelled bins provided to segregate these wastes from other general refuse by the workforce.

Land site/ During construction

Contractor(s)

 

ü

 

Implemented

ETWB TCW No. 33/2002,

Management of Construction and Demolition Material Including Rock

S8.5

Any unused chemicals and those with remaining functional capacity will be recycled as far as

possible.

Land site/ During construction

Contractor(s)

 

ü

 

N/A

-

S8.5

Use of reusable non-timber formwork to reduce the amount of C&D materials.

All areas/ During construction

Contractor(s)

 

ü

 

N/A

WBTC 32/92, The Use

of Tropical Hard Wood on Construction Site

S8.5

Prior to disposal of construction waste, wood, steel and other metals will be separated to the extent practical, for re-use and/or recycling to reduce the quantity of waste to

be disposed of to landfill.

All areas/ During construction

Contractor(s)

 

ü

 

Implemented

DEVB TC(W) No. 6/2010,

Trip Ticket System for Disposal of Construction & Demolition Materials

S8.5

Proper storage and site practices to reduce the potential for damage or contamination of construction materials.

All areas/ During construction

Contractor(s)

 

ü

 

Implemented, rectified after

observation

-

S8.5

Plan and stock construction materials

All areas/ During construction

Contractor(s)

 

ü

 

Implemented

-


 

 

EIA Reference

Recommended Environmental Protection Measures/ Mitigation Measures

Objectives of the recommended measures &

main concerns to address

Implementation Agent

Implementation Stage

Implementation Status

Relevant Legislation & Guidelines

D

C

O

 

carefully to reduce amount of waste generated and avoid unnecessary generation of waste.

 

 

 

 

 

 

 

S8.5

A Sediment Quality Report (SQR) for sampling and chemical testing of the sediment will be prepared and submitted to the EPD for approval. The approved detailed sampling and chemical testing will be carried out prior to the commencement of the dredging activities to confirm the sediment disposal method.

Marine works/ During construction

Contractor(s)

 

ü

 

N/A

ETWB TC(W) No. 34/2002

and Dumping at Sea Ordinance (DASO)

S8.5

The management of dredged/ excavated sediment management requirement from ETWB TC(W) No. 34/2002 will be incorporated in the Specification of the Contract Documents.

Marine works/ During construction

WSD/

Contractor(s)

 

ü

 

Implemented

ETWB TC(W) No.

34/2002 and Dumping at Sea Ordinance (DASO)

S8.5

The contractor will open a billing account with EPD in accordance with the Waste Disposal (Charges for Disposal of Construction Waste) Regulation for the payment of disposal charges.

Contract mobilisation/ During construction

Contractor(s)

 

ü

 

Implemented

Cap 354N Waste Disposal (Charges for Disposal of Construction Waste)

Regulation

S8.5

A trip-ticket system will be established in accordance with DEVB TC(W) No. 6/2010 to monitor the reuse of surplus excavated materials off-site and disposal of construction waste and general refuse at transfer facilities/ landfills, and

to control fly-tipping.

Contract mobilisation/ During construction

Contractor(s)

 

ü

 

Implemented

DEVB TC(W) No. 6/2010,

Trip Ticket System for Disposal of Construction & Demolition Materials

S8.5

The project proponent will also conduct regular inspection of the waste management measures implemented on site as described in the Waste Management Plan.

All area/ During construction

Contractor(s

)/      Environment al Team (ET) &       Independent Environment

al Checker (IEC)

 

ü

 

Implemented

ETWB TC(W) No. 19/2005,

Environmental Management on Construction Sites

S8.5

A recording system (similar to summary table as shown in Annex 5 and Annex 6 of

All area/ During construction

Contractor(s)

 

ü

 

Implemented

Annex 5 and Annex 6 of Appendix G of


 

 

EIA Reference

Recommended Environmental Protection Measures/ Mitigation Measures

Objectives of the recommended measures &

main concerns to address

Implementation Agent

Implementation Stage

Implementation Status

Relevant Legislation & Guidelines

D

C

O

 

Appendix G of ETWB TC(W) No. 19/2005) for the amount of waste generated, recycled and disposed of (including the disposal sites) will

be established during the construction phase.

 

 

 

 

 

 

ETWB TC(W) No. 19/2005

S8.5

Inert C&D materials (public fill) will be reused within the Project as far as practicable.

All area/ During construction

Contractor(s)

 

ü

 

N/A

-

S8.5

Public fill and construction waste shall be segregated and stored in different containers or skips to facilitate reuse or recycling of materials and their proper disposal.

All area/ During construction

Contractor(s)

 

ü

 

N/A

-

S8.5

Specific areas of the work site will be designated for such segregation and storage if immediate use is not practicable.

All area/ During construction

Contractor(s)

 

ü

 

N/A

-

S8.5

To reduce the potential dust and water quality impacts of site formation works, C&D materials will be wetted as quickly as possible to the

extent practice after filling.

All area/ During construction

Contractor(s)

 

ü

 

Implemented

Air Pollution Control (Construction Dust) Regulation (Cap 311R);

WPCO (Cap 358)

S8.5

Open stockpiles of excavated/ fill materials or construction wastes on-site should be covered with tarpaulin or similar fabric.

Land site/ During Construction, particularly dry season

Contractor(s)

 

ü

 

Implemented

Air Pollution Control (Construction Dust) Regulation (Cap 311R)

S8.5

Chemical waste container shall be suitable for the substance they are holding, resistant to corrosion, maintained in a good condition, and securely closed.

All area/ During construction/ During operation

Contractor(s)/ WSD

 

ü

ü

NA

Waste Disposal (Chemical Waste) (General) Regulation; Code of Practice on the Packaging, Handling and Storage of Chemical

Wastes

S8.5

Chemical waste container shall have a capacity of less than 450 L unless the specifications have been approved by the EPD.

All area/ During construction/ During operation

Contractor(s)/ WSD

 

ü

ü

NA

Waste Disposal (Chemical Waste) (General) Regulation; Code of Practice on the Packaging, Handling and

Storage of Chemical Wastes

S8.5

A label in English and Chinese shall be displayed on the chemical container in accordance with

All area/ During construction/ During

Contractor(s)/

WSD

 

ü

ü

NA

Waste Disposal (Chemical Waste)


 

 

EIA Reference

Recommended Environmental Protection Measures/ Mitigation Measures

Objectives of the recommended measures &

main concerns to address

Implementation Agent

Implementation Stage

Implementation Status

Relevant Legislation & Guidelines

D

C

O

 

instructions prescribed in Schedule 2 of the Regulations.

operation

 

 

 

 

 

(General) Regulation; Code of Practice on the Packaging, Handling and Storage of Chemical

Wastes

S8.5

Storage areas for chemical waste shall be enclosed on at least 3 sides.

All area/ During construction/ During operation

Contractor(s)/ WSD

 

ü

ü

Implemented

Waste Disposal (Chemical Waste) (General) Regulation; Code of Practice on the Packaging, Handling and Storage of Chemical

Wastes

S8.5

Storage areas for chemical waste shall have an impermeable floor and bunding, of capacity to accommodate 110% of the volume of the largest container or 20% by volume of the chemical waste stored in that area, whichever is the greatest.

All area/ During construction/ During operation

Contractor(s)/ WSD

 

ü

ü

Implemented

Waste Disposal (Chemical Waste) (General) Regulation; Code of Practice on the Packaging, Handling and Storage of Chemical

Wastes

S8.5

Storage areas for chemical waste shall have adequate ventilation.

All area/ During construction/ During operation

Contractor(s)/ WSD

 

ü

ü

Implemented

Waste Disposal (Chemical Waste) (General) Regulation; Code of Practice on the Packaging, Handling and Storage of Chemical

Wastes

S8.5

Storage areas for chemical waste shall be covered to prevent rainfall entering (water collected within the bund must be tested and disposed of as chemical waste, if necessary).

All area/ During construction/ During operation

Contractor(s)/ WSD

 

ü

ü

Implemented

Waste Disposal (Chemical Waste) (General) Regulation; Code of Practice on the Packaging, Handling and

Storage of Chemical Wastes

S8.5

Storage areas for chemical waste shall be arranged so that incompatible materials are

appropriately separated.

All area/ During construction/ During

operation

Contractor(s)/ WSD

 

ü

ü

Implemented

Waste Disposal (Chemical Waste)

(General) Regulation;


 

 

EIA Reference

Recommended Environmental Protection Measures/ Mitigation Measures

Objectives of the recommended measures &

main concerns to address

Implementation Agent

Implementation Stage

Implementation Status

Relevant Legislation & Guidelines

D

C

O

 

 

 

 

 

 

 

 

Code of Practice on the Packaging, Handling and Storage of Chemical

Wastes

S8.5

General refuse will be stored in enclosed bins or compaction units separately from construction and chemical wastes.

All area/ During construction/ During operation

Contractor(s)/ WSD

 

ü

ü

Implemented

Waste Disposal (Chemical Waste) (General) Regulation; Code of Practice on the Packaging, Handling and Storage of Chemical

Wastes

S8.5

Adequate number of waste containers will be provided to avoid over-spillage of waste.

All area/ During construction/ During operation

Contractor(s)/ WSD

 

ü

ü

Implemented

DEVB TC(W) No. 8/2010

Enhanced Specification

for Site Cleanliness and Tidiness.

S8.5

A reputable waste collector will be employed by the Contractor to remove general refuse from the site, separately from construction and chemical wastes, on a daily basis to minimise odour, pest

and litter impacts.

All area/ During construction/ During operation

Contractor(s)/ WSD

 

ü

ü

N/A

-

S8.5

Recycling bins will be provided at strategic locations within the Site to facilitate recovery of recyclable materials (including aluminium can, waste paper, glass bottles and plastic bottles) from the Site.

Materials recovered will be sold for recycling.

All area/ During construction/ During operation

Contractor(s)/ WSD

 

ü

ü

Implemented

-

S8.5

To avoid any odour and litter impact, accurate number of portable toilets will be provided for workers on-site.

All area/ During construction

Contractor(s)

 

ü

 

Implemented

-

S8.5

The burning of refuse on construction sites is prohibited by law.

All area/ During construction

Contractor(s)

 

ü

 

Implemented

Air Pollution Control Ordinance (Cap 311)

S8.7

To facilitate monitoring and control over the contractors¡¦ performance on waste management, a waste inspection and audit

programme will be implemented throughout the construction phase.

All facilities/ During construction

ET/ IEC

 

ü

 

Implemented

-


Note: D - Design stage C - Construction O - Operation


 

 

EIA Reference

Recommended Environmental Protection Measures/ Mitigation Measures

Objectives of the recommended measures &

main concerns to address

Implementation Agent

Implementation Stage

Implementation Status

Relevant Legislation & Guidelines

D

C

O

 

Ecology

S9.7

For slope mitigation works within the Clear Water Bay Country Park, to avoid tree felling and damages to trees, the exact locations of the flexible barrier foundation plates, soil nails and rock dowels can be adjusted during detailed design, and a setback distance from existing trees is recommended to be maintained as far as practical. A detailed specification describing the exact locations of the flexible barrier foundation plates, soil nails and rock  dowels will be prepared to illustrate how the setback distance from existing trees would be implemented for

tree avoidance.

Slope mitigation works area/ During detailed design/ During construction

Contractor(s)

ü

ü

 

Implemented

-

S9.7

Pruning of tree canopies along the alignment of the flexible barriers shall be limited to a minimum.

Slope mitigation works area/ During construction

Contractor(s)

 

ü

 

Implemented

 

S9.7

The alignment of flexible barriers shall be optimized to preserve all species of conservation interest and minimize the impact to the existing vegetation as far as practicable.                           All individuals of Marsdenia lachnostoma within the slope mitigation areas shall be retained in- situ, by positioning the alignment of flexible barrier at a minimum 1.5m in a radius away from these

individuals.

Slope mitigation works area/ During detailed design/ During construction

Contractor(s)

ü

ü

 

N/A

-

S9.7 and 9.10

At the detailed design stage prior to the commencement of the slope mitigation works, a vegetation survey shall be carried out at the slope mitigation areas within the Clear Water Bay Country Park to assess the condition and identify the location of each individual of Marsdenia lachnostoma and other flora species of conservation interest that may be directly

affected by the construction works.

Slope mitigation works area/ During detailed design/ During construction

Contractor(s)

ü

ü

 

N/A

-

S9.7

Temporary fencing will be installed to fence off

Slope mitigation works

Contractor(s)

 

ü

 

N/A

-


 

 

EIA Reference

Recommended Environmental Protection Measures/ Mitigation Measures

Objectives of the recommended measures &

main concerns to address

Implementation Agent

Implementation Stage

Implementation Status

Relevant Legislation & Guidelines

D

C

O

 

the concerned species either in groups of individually within the works area and in the close proximity to prevent from being damaged and disturbed during construction. A sign identifying the site shall be attached to the fence and flagging tape shall be attached to the

individuals to visualize their locations.

area/ During construction

 

 

 

 

 

 

S9.7 and S9.10

A specification for fencing and demarcating individuals of Marsdenai lachnostoma (or other flora species of conservation interest, if found) adjacent to the proposed alignment of the flexible barriers will be prepared to protect the

species.

Slope mitigation works area/ During construction

Contractor(s)

 

ü

 

N/A

-

S9.7

Induction training shall also be provided to all site personnel in order to brief them on this flora of

conservation interest including the locations and their importance.

Slope mitigation works area/ During construction

Contractor(s)

 

ü

 

N/A

-

S9.7

The resident site supervisory staff will closely monitor the conditions of concerned individuals during construction of flexible barriers in the close proximity.

Slope mitigation works area/ During construction

Contractor(s)

 

ü

 

N/A

-

S9.7

Erect fences along the boundary of the works area before the commencement of works to prevent vehicle movements and encroachment of personnel onto adjacent areas.

All area/ During construction

Contractor(s)

 

ü

 

Implemented

-

S9.7

Regularly check the work site boundaries to ensure that they are not breached and that

damage does not occur to surrounding areas.

All area/ During construction

Contractor(s)/ Environmental

Team (ET)

 

ü

 

Implemented

-

S9.7

Avoid any damage and disturbance, particularly those caused by filling and illegal dumping, to the surrounding habitats through proper management

of waste disposal.

All area/ During construction

Contractor(s)

 

ü

 

Implemented

-


 

 

EIA Reference

Recommended Environmental Protection Measures/ Mitigation Measures

Objectives of the recommended measures &

main concerns to address

Implementation Agent

Implementation Stage

Implementation Status

Relevant Legislation & Guidelines

D

C

O

S9.7

Reinstate temporarily affected areas, particularly the habitats of plantation and shrubland- grassland immediately after completion of construction works, through on-site tree/shrub planting. The tree/shrub  species will be chosen

with reference to those in the surrounding area.

All area/ During construction

Contractor(s)

 

ü

 

N/A

-

S9.7

Affected habitats within the Clear Water Bay Country Bay shall be reinstated by hydro-seeding and planting of climbers and native shrub

seedlings where practical upon completion of the slope mitigation works.

All area/ During construction

Contractor(s)

 

ü

 

N/A

-

Note: D - Design stage C - Construction O - Operation


 

 

EIA Reference

Recommended Environmental Protection Measures/ Mitigation Measures

Objectives of the recommended measures &

main concerns to address

Implementation Agent

Implementation Stage

Implementation Status

Relevant Legislation & Guidelines

D

C

O

 

Landscape & Visual

S11.10 & 11.11

The construction area and area allowed for temporary structures, such as the contractor¡¦s office, will be minimized to a practical minimum.

(MM1)

All area/ Detailed design/ During construction/ During operation

WSD/

Contractor(s)

ü

ü

ü

Implemented

-

S11.10 & 11.11

At the detailed design stage, the design team will seek to minimize the landscape footprint of the Project and above ground facilities, while satisfying all other requirements. (MM2)

All area/ Detailed design/ During construction/ During operation

WSD/

Contractor(s)

ü

ü

ü

Implemented

-

S11.10 & 11.11

Design principles will be adopted to take into account the surrounding area, particularly Clear Water Bay Country Park behind and the nearby waterfront, with due consideration given to:

-  green roofs where practical (ie without equipment on the roof);

-  roadside planting;

-  aesthetic treatment of all structures;

-  vertical greening;

screen planting along application site; and

- landscape enhancement with amenity planting where practical including planting along the edge (site boundary) fence with native shrubs where feasible,

- to reduce their visual impact and blend them into

the surrounding landscape.                               (MM3)

All area/ Detailed design/ During construction/ During operation

WSD/

Contractor(s)

ü

ü

ü

Implemented

-

S11.10 & 11.11

All trees within the Project Site or the potential slope mitigation works area will be carefully protected during construction according to DEVB TCW No.

10/2013 - Tree Preservation (MM4)

All area/ Detailed design/ During construction/ During operation

WSD/

Contractor(s)

ü

ü

ü

Implemented

ETWB TCW No. 3/2006 -

Tree Preservation.

S11.10 & 11.11

No tree within the Country Park will be felled. Trees within the Site unavoidably affected by the works will be transplanted where necessary and practical.      For trees that need to be felled,

compensatory planting will be provided to the satisfaction of relevant Government departments.

All area/ Detailed design/ During construction/ During operation

WSD/

Contractor(s)

ü

ü

ü

Implemented

DEVB TC(W) No. 10/2013


 

 

EIA Reference

Recommended Environmental Protection Measures/ Mitigation Measures

Objectives of the recommended measures &

main concerns to address

Implementation Agent

Implementation Stage

Implementation Status

Relevant Legislation & Guidelines

D

C

O

 

A compensatory tree planting proposal including locations of tree compensation will be submitted to seek relevant government department¡¦s approval, in accordance with DEVB TC(W) No.

10/2013.      (MM5)

 

 

 

 

 

 

 

S11.10 & 11.11

Any slope mitigation works necessary to address natural terrain hazards, will be minimized to minimize any potential environmental impact to the Country Park e.g. soil nailing and rock stabilization will aim to avoid existing trees e.g. should any restoration of vegetation be necessary, the best planting matrix with native species will be established, with the aim of

resembling the existing vegetation.                             (MM6)

All area/ Detailed design/ During construction/ During operation

WSD/

Contractor(s)

ü

ü

ü

N/A

 

S11.10 & 11.11

Dredging works for the installation of intake structures and outfall diffusers should be minimized to avoid or reduce any potential environmental impacts to as low as reasonably practicable (ALARP). The intake and outfall structures (e.g. intake openings and diffuser

heads) will be prefabricated and transferred to site for installation.                           (MM7)

All area/ Detailed design/ During construction/ During operation

WSD/

Contractor(s)

ü

ü

ü

N/A

 

S11.10 & 11.11

All night-time lighting will be reduced to a practical minimum both in terms of number of level and will be hooded and directional.

(MM8)units and lux level and will be hooded and directional. (MM8)

All area/ Detailed design/ During construction/ During operation

WSD/

Contractor(s)

ü

ü

ü

Implemented

-

Note: D - Design stage C - Construction O - Operation


 

 

EIA Reference

Recommended Environmental Protection Measures/ Mitigation Measures

Objectives of the recommended measures &

main concerns to address

Implementation Agent

Implementation Stage

Implementation Status

Relevant Legislation & Guidelines

D

C

O

 

Landfill Gas Hazard

S12.7

During all works, safety procedures should be implemented to minimise the risks of fires and explosions, asphyxiation of workers and toxicity effects resulting from contact with

contaminated soil and groundwater.

All area/ Detailed design/ During construction/ During operation

Contractor(s)

ü

ü

ü

Implemented

-

S12.7

During trenching and excavation as well as creation of confined spaces at near to or below ground level, precautions should be clearly laid down and rigidly Gas detection equipment and appropriate breathing apparatus should be available and used when entering confined

spaces or trenches deeper than 1 metre.

All area/ Detailed design/ During construction/ During operation

Contractor(s)

ü

ü

ü

Implemented

 

S12.7

The Contractor should make the workers are aware of potential hazards of working in confined spaces (any chamber, manhole or culvert which is large enough to permit access to personnel).         Such work in confined spaces is controlled by the Factories and Industrial Undertakings (Confined Spaces) Regulations of the Factories and Industrial Undertakings Ordinance.

Following the Safety Guide to Working in Confined Spaces ensures compliance with the

above regulations.

All area/ Detailed design/ During construction/ During operation

Contractor(s)

ü

ü

ü

Implemented

 

S12.7

Safety officers, specifically trained with regard to landfill gas and leachate related hazards and the appropriate actions to take in adverse circumstances, should be present on the site throughout the works, in particular, when works

are undertaken below grade.

All area/ Detailed design/ During construction/ During operation

Contractor(s)

ü

ü

ü

Implemented

 

S12.7

All personnel who work on site and all visitors to the site should be made aware of the possibility of       ignition of gas in the vicinity of the works, the possible presence of contaminated water and

the need to avoid physical contact with it.

All area/ Detailed design/ During construction/ During operation

Contractor(s)

ü

ü

ü

Implemented

 


 

 

EIA Reference

Recommended Environmental Protection Measures/ Mitigation Measures

Objectives of the recommended measures &

main concerns to address

Implementation Agent

Implementation Stage

Implementation Status

Relevant Legislation & Guidelines

D

C

O

S12.7

Monitoring for landfill gas should be undertaken in all excavations, manholes, chambers (particularly during pipe jacking) and any confined spaces through the use of an intrinsically safe portable instrument, appropriately calibrated and capable of measuring the concentrations of methane. carbon dioxide

and oxygen.

All area/ Detailed design/ During construction/ During operation

Contractor(s)

ü

ü

ü

Implemented

 

S12.7

Monitoring frequency and areas to be monitored should be specified prior to commencement of groundwork, either by the Safety Officer, or by an appropriately qualified person.                All measurements should be recorded and documented.

All area/ Detailed design/ During construction/ During operation

Contractor(s)

ü

ü

ü

Implemented

 

S12.7

Proceed drilling with adequate care and precautions against the potential hazards which may be encountered.

All area/ Detailed design/ During construction/ During operation

Contractor(s)

ü

ü

ü

Implemented

 

S12.7

Prior to the commencement of the site works, the drilling contractor should devise a 'method- of- working' statement covering all normal and emergency procedures (including but not limited to number of operatives, experience and special skills of operatives, normal method of operations, emergency procedures, supervisors responsibilities, storage and use of safety equipment, safety procedures and signs, barriers and guarding).                          The site supervisor and all operatives must be familiar with this

statement.

All area/ During construction/ During operation

Contractor(s)

ü

ü

ü

N/A

 

S12.7

Where below ground service entries are necessary to the Incoming Switchgear Room, 132 kV Substation and Chlorine Store (I) and (II), the entry point should be sealed to prevent gas entry. In addition, any below grade cable trenches entering the Incoming Switchgear Room and 132 kV Substation can become the pathway for

landfill gas and hence grilled metal covers should

All area/ Detailed design/ During construction/ During operation

Contractor(s)

ü

ü

ü

N/A

 


 

 

EIA Reference

Recommended Environmental Protection Measures/ Mitigation Measures

Objectives of the recommended measures &

main concerns to address

Implementation Agent

Implementation Stage

Implementation Status

Relevant Legislation & Guidelines

D

C

O

 

be used.

 

 

 

 

 

 

 

S12.7

It is recommended regular landfill gas monitoring should be carried out at the Incoming Switchgear Room, 132 kV Substation and Chlorine Store (I) and (II). The monitoring frequency will be monthly for the first year of operation. If the monitoring results show no sign of landfill gas migration, reduce

the monitoring frequency to once every six months.

All area/ Detailed design/ During construction/ During operation

Contractor(s)

ü

ü

ü

N/A

 

S12.7

The manholes and utility pits within the Project Site and along the fresh water mains. Each manhole/ utility pit should be monitored with two measurements (at mid depth and base).

Each measurement should be monitored for a minimum of 10 minutes. A steady reading and peak reading should be recorded at each manhole/ utility pit and for each measurement. The need for venting the manhole/ utility pit and

further monitoring will be reviewed after the initial monitoring.

All area/ Detailed design/ During construction/ During operation

Contractor(s)

ü

ü

ü

Impllemented

 

S12.7

All construction, operation and maintenance personnel working on-site as well as visitors should be made aware of the hazards of landfill gas and its possible presence on-site. This should be achieved through a combination of posting warning signs in prominent places and also by access to detailed information on landfill gas hazards and the designs and procedural means by which these hazards are being minimised

on-site.

All area/ Detailed design/ During construction/ During operation

Contractor(s)

ü

ü

ü

Implemented

 

Note: D - Design stage C - Construction O - Operation


 

 

 

 

 

 

 

 

Appendix D

 

Impact     Monitoring    Schedule     of    the Reporting Month (BLANK)


 

 

 

 

(BLANK)


 

 

 

 

 

 

 

 

 

 

 

 

Appendix E

 

Event/Action Plan for Noise Exceedance


 

 

 

 

 

 

 

 

 

 

 

 

 

Appendix F

 

Event/Action     Plan    for    Water    Quality Exceedance


 


 


 

 

 

 

 

 

 

 

Appendix G

Waste Flow Table


 

 

Appendix F - Monthly Summary Waste Flow Table

 

 

Name of Department: WSD                                                                                                              Contract No.: 13/ESD/17

 

Monthly Summary Waste Flow Table for 2020 (year)

 

 

 

 

Month

Actual Quantities of Inert C&D Materials Generated Monthly

Actual Quantities of C&D Wastes Generated Monthly

Total Quantity Generated

Hard Rock and Large Broken Concrete

Reused in the Contract

(see Note 6)

Reused in other Projects

Disposed as Public Fill

 

Imported Fill

 

Metals

Paper/ cardboard packaging

Plastics

 

(see Note 3)

 

Chemical Waste

Others, e.g. general refuse

(in '000kg)

(in '000kg)

(in '000kg)

(in '000kg)

(in '000kg)

(in '000kg)

(in '000 kg)

(in '000kg)

(in '000kg)

(in '000kg)

(in '000kg)

Jan

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

Feb

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

Mar

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.420

Apr

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

2.400

May

0.000

0.000

0.000

0.000

0.000

0.000

5.900

0.000

0.000

0.000

12.570

Jun

 

 

 

 

 

 

 

 

 

 

 

Sub-total

0.000

0.000

0.000

0.000

0.000

0.000

5.900

0.000

0.000

0.000

15.390

Jul

 

 

 

 

 

 

 

 

 

 

 

Aug

 

 

 

 

 

 

 

 

 

 

 

Sep

 

 

 

 

 

 

 

 

 

 

 

Oct

 

 

 

 

 

 

 

 

 

 

 

Nov

 

 

 

 

 

 

 

 

 

 

 

Dec

 

 

 

 

 

 

 

 

 

 

 

Total

0.000

0.000

0.000

0.000

0.000

0.000

5.900

0.000

0.000

0.000

15.390

Notes:      (1) The performance targets are given in Section 1.69 of Specification B

(2)   The waste flow table shall also include C&D materials that are specified in the Contract to be imported for use at the Site.

(3)   Plastics refer to plastic bottles/containers, plastic sheets/ foam from packaging material


 

 

 

 

 

 

 

Appendix H Complaint Log


 

 

Statistical Summary of Environmental Complaints

 

Reporting Period

Environmental Complaint Statistics

Frequency

Cumulative

Complaint Nature

16 Mar 2020 -

 

31 May 2020

 

 

0

 

 

0

 

 

N/A

 

 

 

Statistical Summary of Environmental Summons

 

Reporting Period

Environmental Summons Statistics

Frequency

Cumulative

Details

16 Mar 2020 -

 

31 May 2020

 

 

0

 

 

0

 

 

N/A

 

 

 

Statistical Summary of Environmental Prosecution

 

Reporting Period

Environmental Prosecution Statistics

Frequency

Cumulative

Details

16 Mar 2020 -

 

31 May 2020

 

 

0

 

 

0

 

 

N/A